Substation Scout

Neville Substation

Named in 4 PJM planning documents for 2 projects, from February 14, 2025 to October 8, 2025.

Existingdescribed as
DLCOzone
138kVkV as printed
4mentions

PJM interconnection queue

A PJM queue substation page has the same name: Neville (PA) — 3 queue requests filed, 0 active.

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Neville, PA
DLC-2024-004
Not printed Not printed Not printed Not printed 2025-02-14
SRRTEP Western
Neville Substation Breaker
DLC-2025-004 · s3649
Conceptual $0.8 M 12/31/2025 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
DLCO local plan submission of the supplemental projects for 2025 RTEP p. 8
Neville Substation Breaker “one oil circuit breaker at Neville Substation has increased failure probability”
138kV
2025-10-08 TEAC
Informational Only - DLCO Local Plan Submission of the Supplemental Projects for 2025 p. 8
Neville Substation Breaker “one oil circuit breaker at Neville Substation has increased failure probability”
2025-03-14 SRRTEP Western
Item 04 - DLCO Supplemental Project p. 9
Neville Substation Breaker “one oil circuit breaker at Neville Substation has increased failure probability”
138kV
2025-02-14 SRRTEP Western
Item 02 - DLCO Supplemental Projects p. 6
Neville, PA “one oil circuit breaker at Neville Substation has increased failure probability”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this