Kimberly
Named in 3 PJM planning documents for 2 projects, from February 14, 2025 to October 8, 2025.
Existingdescribed as
ATSIzone
69 kVkV as printed
3mentions
Also printed as: Kimberly Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Ellsworth Substation – s1952 Scope Change s1952 |
Engineering | $36.3M | 4/30/2027 | 19 MW | 2025-02-14 SRRTEP Western |
| Ellsworth Substation – s1952 Scope Change ATSI-2019-008 · s1952 |
Not printed | $36.3M | 4/30/2027 | 19 MW | 2025-10-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate prior value printed on the same page |
$27 M → $36.3M | 2025-02-14 | 2025-02-14 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Western ATSI local plan submission of the supplemental projects for 2025 RTEP p. 34 |
Ellsworth Substation – s1952 Scope Change | “Install two 69 kV SCADA controlled switches” 69 kV |
| 2025-10-08 | TEAC Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 35 |
Ellsworth Substation – s1952 Scope Change | “At Kimberly
§ Install two 69 kV SCADA controlled switches” 69 kV |
| 2025-02-14 | SRRTEP Western Item 07 - ATSI Supplemental Project p. 3 |
Ellsworth Substation – s1952 Scope Change | “The Kimberly Substation is served from a 3.6-mile radial transmission line” 69 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.