Substation Scout

Markley

Named in 4 PJM planning documents for 1 project, from February 14, 2025 to October 8, 2025.

Existingdescribed as
DEOKzone
69/13 kVkV as printed
4mentions

Also printed as: Markley substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Markley
DEOK-2024-003 · s3599.1
Engineering $1,080,019 12/11/2026 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
DEOK local plan submission of the supplemental projects for 2025 RTEP p. 4
Markley “Markley substation has three 69/13 kV distribution transformers”
69/13 kV
2025-10-08 TEAC
Informational Only - DEOK Local Plan Submission of the Supplemental Projects for 2025 p. 4
Markley “Station Modifications Only”
2025-03-14 SRRTEP Western
Item 06 - DEOK Supplemental Projects p. 3
Markley “Markley substation has three 69/13 kV distribution transformers”
69/13 kV
2025-02-14 SRRTEP Western
Item 06 - DEOK Supplemental Projects p. 3
Markley “Markley substation has three 69/13 kV distribution transformers”
69/13 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.