Rutherford

Named in 3 PJM planning documents for 1 project, from February 13, 2025 to October 6, 2026.

Existingdescribed as
PPLzone
69-12kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Rutherford, PA
PPL-2025-0001
Conceptual $0.5 M 05/30/2027 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 5/2026 → 05/30/2027 2025-02-13 2025-09-18
Substations named RUTHERFORD → COPPERSTONE; HARRISBURG; RUTHERFORD 2026-10-06 Not reported
Substations named RUTHERFORD 69; RUTHERFORD DISTRIBUTION → RUTHERFORD 2025-09-18 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 2
Rutherford, PA “energize the on-site spare transformer at Rutherford 69-12kV Substation”
69-12kV
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 2
Rutherford, PA “energize the on-site spare transformer at Rutherford 69-12kV Substation”
69-12kV
2025-02-13 SRRTEP Mid-Atlantic
Item 01 - PPL Supplemental Projects p. 3
Rutherford, PA “energize the on-site spare transformer at Rutherford 69-12kV Substation”
69-12kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.