Bilter Road

Named in 1 PJM planning document for 1 project, on February 14, 2025.

Existingdescribed as
COMEDzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Aurora
ComEd-2024-022
Engineering $0M 12/31/27 91 MW 2025-02-14
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-02-14 SRRTEP Western
Item 03 - ComEd Supplemental Projects p. 10
Customer in Aurora “lines from Bilter Road substation”