Tyrone North Substation

Named in 4 PJM planning documents for 2 projects, from April 10, 2025 to October 16, 2026.

Existingdescribed as
PENELECzone
—kV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Eagle Valley-Westfall 115 kV EVW Line Rebuild
PN-2019-036
Conceptual $51.69 M 06/14/2030 Not printed 2026-10-16
SRRTEP Mid-Atlantic
Tyrone North – Tipton 46 kV Line
PN-2024-006 · s3635.1
Not printed $2.92 M 12/31/2027 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Mid-Atlantic
Item 08 - Penelec Supplemental Projects Presentation p. 4
Eagle Valley-Westfall 115 kV EVW Line Rebuild “Upgrade the substation conductor and 1200 A CT at Tyrone North Substation”
2026-09-08* SRRTEP Mid-Atlantic
Penelec local plan submission for 2025 RTEP p. 14
Tyrone North – Tipton 46 kV Line “Upgrade line relaying and limiting substation conductor at Tyrone North Substation.”
2025-10-08 TEAC
Informational Only - Penelec Local Plan Submission of the Supplemental Projects for 2025 p. 14
Tyrone North – Tipton 46 kV Line “Upgrade line relaying and limiting substation conductor at Tyrone North Substation.”
2025-04-10 SRRTEP Mid-Atlantic
Item 01 - PENELEC Supplemental Projects p. 6
Tyrone North – Tipton 46 kV Line “Upgrade line relaying and limiting substation conductor at Tyrone North Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.