Substation Scout

Gold Finch

Named in 1 PJM planning document for 1 project, on April 1, 2025.

Newdescribed as
DEOKzone
—kV as printed
1mentions

Described as new: “Potential Solution” — source, page 4

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Load Request
DEOK-2025-002
Conceptual $49.0M 06/01/2028 300 MW 2025-04-01
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 2028 → 06/01/2028 2025-02-04 2025-04-01
Substations named BECKJORD POWER → BECKJORD; GOLD FINCH; NEWTOWN; PIERCE; RED BANK; SILVER GROVE 2025-02-04 2025-04-01

Every mention

DateDocumentProjectWhat the document says about it
2025-04-01 TEAC
Item 09 - DEOK Supplemental Projects p. 4
New Customer Load Request “Potential Solution”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this