Named in 10 PJM planning documents for 15 projects, from October 8, 2024 to October 16, 2026.

Existingdescribed as
APSzone
138 kV, 500 kV, 500/138 kVkV as printed
28mentions

Also printed as: Pruntytown

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Buckhannon-Pruntytown 138 kV New Customer
APS-2021-012 · s3095.1
Not printed $5.0M 07/02/2025 40 MW 2024-10-08
TEAC
Misoperation Relay Projects
APS-2023-036, APS-2023-041 to APS-2023-043, APS-2023-045 to APS-2023-049
Not printed $2.2 M 11/29/2024 Not printed 2026-09-08*
SRRTEP Western
Misoperation Relay Projects
APS-2023-047 · s3113.1
Not printed $2.3 M 12/19/2023 Not printed 2024-10-08
TEAC
Harrison – Pruntytown 500 kV Misoperation Relays
APS-2023-056 · s3191.1
Not printed $0.86M 11/29/2024 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2023-064 to APS-2023-066, APS-2023-069
Not printed $1.7 06/01/2024 Not printed 2026-09-08*
SRRTEP Western
Misoperation Relay Projects
APS-2023-066 · s3160.1
Not printed $3.9 10/09/2024 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-005, APS-2024-006 · s3464.1, s3465.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-012, APS-2024-017 · s3368.1, s3369.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Pruntytown No. 3 500/138 kV Transformer
APS-2024-071 · s3574.1
Not printed $15.77 M 6/30/2029 Not printed 2025-10-08
TEAC
Pruntytown No. 1 500/138 kV Transformer
APS-2024-077 · S3655.1
Not printed $ 18.8 M 06/13/2031 Not printed 2025-10-08
TEAC
Pruntytown No. 2 500/138 kV Transformer
APS-2024-078 · S3653.1
Not printed $ 18.8 M 12/13/2030 Not printed 2025-10-08
TEAC
Misoperation Relay Projects
APS-2024-098 to 105, APS-2024-111 to 114, APS-2024-116, APS-2024-118
Not printed Not printed Not printed Not printed 2024-12-13
SRRTEP Western
Misoperation Relays
APS-2024-111
Conceptual $4.73 M 11/03/2028 Not printed 2026-09-18
SRRTEP Western
Misoperation Relays
APS-2024-118
Conceptual $6.51 M 09/30/2026 Not printed 2026-09-18
SRRTEP Western
Albright - Pruntytown 138 kV Line
APS-2026-014
Not printed Not printed Not printed Not printed 2026-10-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named FRANKLIN; PURSELY → ARMSTRONG; CABOT; EDGELAWN; FAIRVIEW; FRANKLIN; GILBOA; GRASSY FALLS; HOUSEVILLE; MCCALMONT; PRICE HILL; PRUNTYTOWN; PURSELY; SUTTON; TRISSLER 2024-10-08 Not reported
Substations named ALBRIGHT; KINGWOOD; PRUNTYTOWN → ALBRIGHT; FAWN; GOBAIN; KINGWOOD; PRUNTYTOWN 2024-10-08 Not reported
Substations named HARRISON; MT STORM DOM; PRUNTYTOWN; WYLIE RIDGE → HARRISON; PRUNTYTOWN; WYLIE RIDGE 2024-10-08 Not reported
Substations named BUTLER; CABOT; CABOT WEST; GRAFTON; PRUNTYTOWN → BUTLER; CABOT; GRAFTON; PRUNTYTOWN 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 3
Albright - Pruntytown 138 kV Line No role wording
138 kV
2026-09-18 SRRTEP Western
Item 01 - APS Supplemental Projects p. 13
Misoperation Relays “Pruntytown Substation - Replace wavetrap, meters, and relays”
2026-09-18 SRRTEP Western
Item 01 - APS Supplemental Projects p. 9
Misoperation Relays “At Pruntytown Substation: replace breaker, associated disconnect switches, substation conductor, wavetrap, and relays”
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 114
Misoperation Relay Projects “At Pruntytown, replace line trap, disconnect switches, substation conductor and relaying”
500 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 33
Buckhannon-Pruntytown 138 kV New Customer “Revise remote end relay settings at Buckhannon Substation and Pruntytown Substation”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 51
Misoperation Relay Projects “At Pruntytown Substation, replace line trap and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 62
Misoperation Relay Projects “At Pruntytown Substation, replace disconnect switches, line trap, substation conductor and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 62
Misoperation Relay Projects “At Pruntytown Substation, replace disconnect switches, line trap, substation conductor and relaying”
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 69
Harrison – Pruntytown 500 kV Misoperation Relays “Replace wave trap, line metering and relaying at Pruntytown Substation”
500 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 97
Misoperation Relay Projects “At Pruntytown Substation, replace disconnect switches, line trap, substation conductor and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 11
Pruntytown No. 3 500/138 kV Transformer “At Pruntytown Substation: ▪ Replace the existing 500/138 kV Transformer No. 3”
500/138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 39
Pruntytown No. 1 500/138 kV Transformer “Replace No. 1 500/138 kV Transformer at Pruntytown Substation”
500/138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 41
Pruntytown No. 2 500/138 kV Transformer “Replace No. 2 500/138 kV Transformer at Pruntytown Substation”
500/138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 11
Pruntytown No. 3 500/138 kV Transformer “At Pruntytown Substation: § Replace the existing 500/138 kV Transformer No. 3”
500/138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 39
Pruntytown No. 1 500/138 kV Transformer “Replace No. 1 500/138 kV Transformer at Pruntytown Substation”
500/138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 41
Pruntytown No. 2 500/138 kV Transformer “Replace No. 2 500/138 kV Transformer at Pruntytown Substation”
500/138 kV
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 6
Pruntytown No. 1 500/138 kV Transformer “Replace No. 1 500/138 kV Transformer at Pruntytown Substation”
500/138 kV
2025-04-01 TEAC
Item 04 - APS Supplemental Projects p. 8
Pruntytown No. 2 500/138 kV Transformer “Replace No. 2 500/138 kV Transformer at Pruntytown Substation”
500/138 kV
2025-01-07 TEAC
Item 05 - APS Supplemental Project p. 4
Pruntytown No. 3 500/138 kV Transformer “At Pruntytown Substation: • Replace the existing 500/138 kV Transformer No. 3”
500/138 kV
2024-12-13 SRRTEP Western
Item 15 - APS Supplemental Project p. 6
Misoperation Relay Projects No role wording
138 kV
2024-12-03 TEAC
Item 04 - APS Supplemental Projects p. 4
Pruntytown No. 2 500/138 kV Transformer “The Pruntytown No. 2 500/138 kV Transformer is approximately 56 years old and is approaching end of life.”
500/138 kV
2024-12-03 TEAC
Item 04 - APS Supplemental Projects p. 5
Pruntytown No. 1 500/138 kV Transformer “The Pruntytown No. 1 500/138 kV Transformer is approximately 54 years old and is approaching end of life.”
500/138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 114
Misoperation Relay Projects “At Pruntytown, replace line trap, disconnect switches, substation conductor and relaying”
500 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 33
Buckhannon-Pruntytown 138 kV New Customer “Revise remote end relay settings at Buckhannon Substation and Pruntytown Substation”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 51
Misoperation Relay Projects “At Pruntytown Substation, replace line trap and relaying”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 62
Misoperation Relay Projects “At Pruntytown Substation, replace disconnect switches, line trap, substation conductor and relaying”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 69
Harrison – Pruntytown 500 kV Misoperation Relays “Replace wave trap, line metering and relaying at Pruntytown Substation”
500 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 97
Misoperation Relay Projects “At Pruntytown Substation, replace disconnect switches, line trap, substation conductor and relaying”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.