Substation Scout

Metedeconk

Named in 2 PJM planning documents for 2 projects, from April 10, 2025 to July 7, 2026.

Existingdescribed as
JCPLzone
34.5 kVkV as printed
2mentions

Also printed as: Metedeconk Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Metedeconk Substation, NJ
JCPL-2025-003
Not printed Not printed 11/30/2026 17 MW 2025-04-10
SRRTEP Mid-Atlantic
Lakewood, NJ
JCPL-2026-026
Conceptual $292.4M 12/31/2032 Not printed 2026-07-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
Item 07 - JCPL Supplemental Projects p. 9
Lakewood, NJ “Expand the 34.5 kV yard with a new 34.5 kV string and two 34.5 kV breakers at Metedeconk.”
34.5 kV
2025-04-10 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 3
Metedeconk Substation, NJ No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this