Creek Walker

Named in 3 PJM planning documents for 1 project, from April 11, 2025 to October 6, 2026.

Not stateddescribed as
AEPzone
138kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone M-3 Process New Carlisle Customer Needs
AEP-2023-IM020 · s3764.1-2
Conceptual $30.463 M 05/09/2028 90 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 11
AEP Transmission Zone M-3 Process New Carlisle Customer Needs No role wording
138kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 11
AEP Transmission Zone M-3 Process New Carlisle Customer Needs No role wording
138kV
2025-04-11 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 6
AEP Transmission Zone M-3 Process New Carlisle Customer Needs No role wording
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this