Wellington

Named in 7 PJM planning documents for 3 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
ATSIzone
138 kV, 69 kVkV as printed
7mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process New New London 69 kV Project
AEP-2019-OH034 · s2748.8
Not printed $10.0M 9/3/2025 Not printed 2024-10-08
TEAC
Homer – Wellington 69 kV Line Customer Connection
ATSI-2025-014 · s3769.1
Not printed $0.9M 3/15/2026 Not printed 2026-10-06
TEAC
Beaver - Henrietta 138 kV Line
ATSI-2026-049
Conceptual $0.96 M 12/31/2027 Not printed 2026-08-14
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 5/14/2027 → 3/15/2026 2025-04-11 2025-07-18
Substations named BEAVER; HENRIETTA → BEAVER; BRIGHTON TAP; HENRIETTA; WELLINGTON 2026-07-17 2026-08-14

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2026 p. 6
Homer – Wellington 69 kV Line Customer Connection “Adjust relay settings at Homer and Wellington substations”
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 6
Homer – Wellington 69 kV Line Customer Connection “Adjust relay settings at Homer and Wellington substations”
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 4
ATSI Transmission Zone M-3 Process New New London 69 kV Project “Upgrade terminal equipment at Wellington”
2026-08-14 SRRTEP Western
Item 02 - ATSI Supplemental Projects p. 12
Beaver - Henrietta 138 kV Line No role wording
138 kV
2025-07-18 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 9
Homer – Wellington 69 kV Line Customer Connection “Adjust relay settings at Homer and Wellington substations”
69 kV
2025-04-11 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 5
Homer – Wellington 69 kV Line Customer Connection No role wording
69 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 4
ATSI Transmission Zone M-3 Process New New London 69 kV Project “Upgrade terminal equipment at Wellington”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.