Navistar
Named in 4 PJM planning documents for 2 projects, from April 1, 2025 to October 6, 2026.
Newdescribed as
AEPzone
345kVkV as printed
4mentions
Described as new: “Construct a new station” — source, page 9
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| New Carlisle, IN AEP-2024-IM016 · s3763.1 |
Conceptual | $50.364 M | 03/15/2027 | 437MW | 2026-10-06 TEAC |
| Olive, IN AEP-2025-IM007 |
Not printed | Not printed | June 2029 | 692MW | 2025-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-07* | SRRTEP Western AEP local plan submission of the supplemental projects for 2026 RTEP p. 9 |
New Carlisle, IN | “Construct a new station” 345kV |
| 2026-10-06 | TEAC Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 9 |
New Carlisle, IN | “Construct a new station in a breaker and a half configuration” 345kV |
| 2025-10-08 | TEAC Item 07 - AEP Supplemental Projects p. 3 |
Olive, IN | “proposed Navistar 345kV station” 345kV |
| 2025-04-01 | TEAC Item 05 - AEP Supplemental Projects p. 7 |
New Carlisle, IN | “Construct a new station” 345kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.