Named in 4 PJM planning documents for 2 projects, from April 1, 2025 to October 6, 2026.

Existingdescribed as
DEOKzone
138 kVkV as printed
4mentions

Also printed as: Beckjord Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Load Request
DEOK-2025-002
Conceptual $49.0M 06/01/2028 300 MW 2025-04-01
TEAC
Customer Load Request
DEOK-2026-004 · s3909.1 - .6
Conceptual $32.8M 06/01/2029 300 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 2028 → 06/01/2028 2025-02-04 2025-04-01
Substations named BECKJORD POWER → BECKJORD; GOLD FINCH; NEWTOWN; PIERCE; RED BANK; SILVER GROVE 2025-02-04 2025-04-01

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - DEOK Local Plan Submission of the supplemental projects for 2026 p. 12
Customer Load Request “Install two 138 kV, 3000 A, 63 kA interrupt circuit breakers in Beckjord 138 kV substation”
138 kV
2026-09-30* SRRTEP Western
DEOK local plan submission of the supplemental projects for 2026 RTEP p. 12
Customer Load Request “Install two 138 kV, 3000 A, 63 kA interrupt circuit breakers in Beckjord 138 kV substation”
138 kV
2026-08-04 TEAC
Item 11 - DEOK Supplemental Projects p. 5
Customer Load Request “Install two 138 kV, 3000 A, 63 kA interrupt circuit breakers in Beckjord 138 kV substation”
138 kV
2025-04-01 TEAC
Item 09 - DEOK Supplemental Projects p. 4
New Customer Load Request “adding a 138 kV circuit breaker at Beckjord”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.