Substation Scout

Shellhorn

Named in 3 PJM planning documents for 4 projects, from October 8, 2024 to April 1, 2025.

Existingdescribed as
DOMzone
—kV as printed
7mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line
B3800.210 – B3800.212
Not printed $439.92M 6/1/2027 Not printed 2025-04-01
TEAC
Prentice Drive 230kV Delivery - DEV
DOM-2022-0003 · s3056
Engineering $20.0 M 12/30/2024 100MW 2024-10-08
TEAC
Stratus 230kV Delivery - DEV
DOM-2022-0041 · s3033
Engineering $24.0M 08/29/2025 185.0 MW 2024-10-08
TEAC
Northwoods 230kV Delivery - NOVEC
DOM-2023-0039 · s3218.1
Engineering $20.0 M 04/01/2026 100MW 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$342.92M → $439.92M 2025-04-01 2025-04-01
Cost estimate
prior value printed on the same page
$342.92M → $431.62M 2025-12-08 2025-12-08
Cost estimate $439.92M → $431.62M 2025-04-01 2025-12-08
Substations named LOCKRIDGE; PRENTICE; PRENTICE DRIVE; SHELLHORN → LOCKRIDGE; PRENTICE DRIVE; SHELLHORN 2024-10-08 Not reported
Substations named ENTERPRISE; LOCKRIDGE; ROUNDTABLE; SHELLHORN; STRATUS → BARRISTER; ENTERPRISE; LOCKRIDGE; ROUNDTABLE; SHELLHORN; STRATUS 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 152
Northwoods 230kV Delivery - NOVEC “Line #2218 (Sojourner – Shellhorn)”
2026-09-08* SRRTEP Southern
Dominion p. 55
Stratus 230kV Delivery - DEV No role wording
2026-09-08* SRRTEP Southern
Dominion p. 69
Prentice Drive 230kV Delivery - DEV No role wording
2025-04-01 TEAC
Item 14 - Reliability Analysis Update p. 7
New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 152
Northwoods 230kV Delivery - NOVEC No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 55
Stratus 230kV Delivery - DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 69
Prentice Drive 230kV Delivery - DEV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this