Newark switching station

Named in 4 PJM planning documents for 1 project, from April 1, 2025 to October 6, 2026.

Existingdescribed as
PSEGzone
—kV as printed
4mentions

Also printed as: Newark Switch · Newark Switching station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Newark Area
PSEG-2025-0002 · s3735
Engineering $27.2M 12/31/2029 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/2029 → 12/31/2029 2025-07-08 2026-10-06
Status conceptual (Conceptual) → engineering (Engineering and Planning) 2025-07-08 2026-10-06
Substations named NEWARK → MCCARTER; NEWARK 2025-04-01 2025-07-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PSEG Local Plan Submission of the Supplemental Projects for 2026.xlsx p. 2
Newark Area “Networks fed from Newark switching station”
2026-09-08* SRRTEP Mid-Atlantic
PSEG local plan submission for 2026 RTEP p. 2
Newark Area “Newark Switching station existing spare circuits”
2025-07-08 TEAC
Item 09 - PSEG Supplemental Projects p. 3
Newark Area “Newark Switching station existing spare circuits”
2025-04-01 TEAC
Item 10 - PSEG Supplemental Projects p. 3
Newark Area “Newark Switching station existing spare circuits are not sufficient to resolve the excess to the network design limit.”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.