Substation Scout

Nursery Substation

Named in 4 PJM planning documents for 1 project, from April 11, 2025 to October 6, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
4mentions

Also printed as: Nursery

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Grand River – Leroy Center No. 1 138 kV Line
ATSI-2025-003 · s3940.1
Not printed $25.58M 04/28/2028 135 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named GRAND RIVER; LEROY CENTER; NURSERY → NURSERY 2026-04-15 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2026 p. 42
Grand River – Leroy Center No. 1 138 kV Line “Convert Nursery Substation 138 kV yard to breaker-and-a-half configuration.”
138 kV
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 43
Grand River – Leroy Center No. 1 138 kV Line “Convert Nursery Substation 138 kV yard to breaker-and-a-half configuration.”
138 kV
2026-04-15 SRRTEP Western
Item 03 - ATSI Supplemental Project p. 13
Grand River – Leroy Center No. 1 138 kV Line “Convert Nursery Substation 138 kV yard to breaker-and-a-half configuration”
138 kV
2025-04-11 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 3
Grand River – Leroy Center No. 1 138 kV Line “The 138 kV Breaker Q3T at Nursery is 77 years old with increasing maintenance concerns”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.