Tidd (AEP)

Named in 1 PJM planning document for 1 project, on April 11, 2025.

Not stateddescribed as
APSzone
138 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Tidd (AEP) - Weirton 138 kV Line
APS-2025-015
Not printed Not printed Not printed Not printed 2025-04-11
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CARNEGIE; TIDD AEP; WEIRTON → CARNEGIE; TIDD; WEIRTON 2025-04-11 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2025-04-11 SRRTEP Western
Item 06 - APS Supplemental Project p. 6
Tidd (AEP) - Weirton 138 kV Line No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.