Red Bank

Named in 2 PJM planning documents for 2 projects, from April 1, 2025 to October 16, 2026.

Existingdescribed as
DEOKzone
138 kV, 345 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Load Request
DEOK-2025-002
Conceptual $49.0M 06/01/2028 300 MW 2025-04-01
TEAC
Red Bank 138 kV Reliability Upgrade
DEOK-2026-008
Not printed Not printed Not printed Not printed 2026-10-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 2028 → 06/01/2028 2025-02-04 2025-04-01
Substations named BECKJORD POWER → BECKJORD; GOLD FINCH; NEWTOWN; PIERCE; RED BANK; SILVER GROVE 2025-02-04 2025-04-01

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 05 - DEOK Supplemental Projects Presentation p. 5
Red Bank 138 kV Reliability Upgrade “The two 138 kV buses in Red Bank transmission substation connect to six 138 kV circuits and two 345/138 kV transformers. Six 138 kV circuit breakers, as well as a number of other devices including CCVTs and RTUs, are due to be replaced”
138 kV
2025-04-01 TEAC
Item 09 - DEOK Supplemental Projects p. 4
New Customer Load Request No role wording
345 kV