Hollidaysburg
Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 8, 2025.
Existingdescribed as
PENELECzone
46 kVkV as printed
5mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Altoona — Hollidaysburg 46 kV ALH Line PN-2023-034 · s3271.1 |
Not printed | $1.5M | 12/31/2026 | Not printed | 2024-10-08 TEAC |
| Altoona - Hollidaysburg 46 AH kV Line PN-2024-005 · s3634.1 |
Not printed | $2.21 M | 12/01/2027 | Not printed | 2025-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2025 RTEP p. 11 |
Altoona - Hollidaysburg 46 AH kV Line | “Replace line relaying at Altoona and Hollidaysburg substations.” 46 kV |
| 2026-09-08* | SRRTEP Mid-Atlantic Penelec local plan submission for 2024 RTEP p. 10 |
Altoona — Hollidaysburg 46 kV ALH Line | “Replace relaying at Altoona and Hollidaysburg substations” |
| 2025-10-08 | TEAC Informational Only - Penelec Local Plan Submission of the Supplemental Projects for 2025 p. 12 |
Altoona - Hollidaysburg 46 AH kV Line | “Replace line relaying at Altoona and Hollidaysburg substations.” |
| 2025-04-10 | SRRTEP Mid-Atlantic Item 01 - PENELEC Supplemental Projects p. 4 |
Altoona - Hollidaysburg 46 AH kV Line | “Replace line relaying at Altoona and Hollidaysburg substations” |
| 2024-10-08 | TEAC Informational Only - PENELEC Local Plan submission of supplemental project 2024 p. 10 |
Altoona — Hollidaysburg 46 kV ALH Line | “Replace relaying at Altoona and Hollidaysburg substations” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.