Tamarack Substation
Tamarack 500-230kV Substation. Presented by PPL in PJM planning materials (PPL zone, PA (Gouldsboro, PA is printed for the same customer's earlier request, PPL-2025-0012)).
Profile
PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in December 2026, at a transmission cost estimate of $486 million and a projected in-service date of May 30, 2031. (p. 1, p. 5, p. 9) The need, first presented in November 2026 under the title Big Bass / Tamarack, is a request from the customer associated with need PPL-2025-0012 for a third 230kV delivery point with an additional 700MW of load, requested in service by May 2030. (p. 12, p. 5) PPL lists an initial load of 250 MW expected in May 2030 and a total of 700 MW expected in May 2032. (p. 5) That earlier need, Big Bass, PA, is a request to serve a facility from a 230kV source in Gouldsboro, Pennsylvania, with a total load of approximately 1,500 MW by 2030. (p. 9) The plan centers on a new Tamarack station with a 230kV switchyard ($118 million, with a STATCOM and a capacitor bank) and a 500kV yard ($88 million, two 750MVA 500-230kV transformers), fed by a new ~25 miles double circuit 500kV line from a new Sandy Run 500kV switchyard, the largest line item at $213 million. (p. 6, p. 7) Sandy Run would be cut into the existing Susquehanna - Wescosville (Orefield) 500kV line, and Tamarack into the Acahela - Big Bass 230kV line, with three 230kV circuits of ~1.0 miles between Tamarack and Big Bass. (p. 6, p. 7) PPL lists no feasible alternative and gives the project status as Project Development. (p. 9)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Sandy Run 500kV switchyard | New four bay 500kV switchyard; estimated $40 M | p. 6 |
| Susquehanna - Wescosville (Orefield) 500kV line | Bifurcate into the new Sandy Run 500kV switchyard; estimated $10 M | p. 6 |
| Tamarack 230kV yard | Seven bays of new BAAH 230kV switchyard with one 144 MVAR capacitor bank and one 250+/-MVAR STATCOM; estimated $118 M | p. 6 |
| Tamarack 500kV yard | Four bays of a 500kV yard with two 500-230kV (750MVA) transformers; estimated $88 M | p. 6 |
| Sandy Run - Tamarack 500kV line | New ~25 miles double circuit 500kV line from Sandy Run 500kV switchyard to the Tamarack 500-230kV substation (cost printed on the next slide) | p. 6 |
| Tamarack 230kV customer lead lines | Three 230kV lead lines, approximately 0.6 miles, to the customer's third substation; estimated $6 M | p. 7 |
| Acahela - Big Bass 230kV line | Bifurcate into the new Tamarack 230kV switchyard (~0.25 miles); estimated $4 M | p. 7 |
| Tamarack - Big Bass 230kV line | Three 230kV circuits between Big Bass and Tamarack 230kV yards (~1.0 miles); estimated $7 M | p. 7 |
Details as printed
| Need presented | Need Meeting TEAC - 11/03/2026, under the title Big Bass / Tamarack | p. 12 |
|---|---|---|
| Project driver | Customer Service | p. 5 |
| Customer request, third delivery point | The customer associated with PPL-2025-0012 requested a third 230kV delivery point with an additional 700MW of load; requested in service 05/2030 | p. 5 |
| Load ramp | Initial load 250 MW expected 05/2030; total load 700 MW expected 05/2032 | p. 5 |
| Same customer's earlier request (PPL-2025-0012) | PPL-2025-0012 (Big Bass, PA): facility served from a 230kV source in Gouldsboro, PA; approximately 1,500 MW total (2030); requested in service 05/2027 | p. 9 |
| Sandy Run - Tamarack 500kV line cost | Sandy Run - Tamarack line estimated $213 M (cost line continued from the previous slide) | p. 7 |
| Alternatives considered | No Feasible Alternative | p. 9 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| November 3, 2026 | Item 05 - PPL Supplemental Projects - Presentation | Big Bass / Tamarack | not printed | 05/2030 | Need Meeting TEAC - 11/03/2026 |
| December 1, 2026 | Item 05 - PPL Supplemental Projects - Presentation | Tamarack 500-230kV Substation | $486 M | 05/30/2031 | Project Development |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Big Bass (PPL): described as new
- Orefield (PPL): described as new
- Sandy Run (PPL): described as new
- Acahela (PPL): expansion described
- Susquehanna (PPL): expansion described
- Tamarack (PPL)
- Wescosville (PPL)
Not printed
- The decks name the customer only as the customer associated with PPL-2025-0012; they do not say what the facility is.
- No town, county or state is printed on the Tamarack slides themselves; the state comes from the same customer's earlier Big Bass request, which names Gouldsboro, PA.
- No location is printed for the new Sandy Run 500kV switchyard.
- The November 2026 need meeting printed no cost or solution; the only cost printed is the December 2026 estimate.
- PPL-2025-0012 (Big Bass, PA, $186.875 M) is the same customer's earlier, separately tracked project, so it is cited for context but is not a member.
- No news coverage naming Tamarack or Sandy Run was found as of 2026-11-27.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.