Tamarack Substation

Tamarack 500-230kV Substation. Presented by PPL in PJM planning materials (PPL zone, PA (Gouldsboro, PA is printed for the same customer's earlier request, PPL-2025-0012)).

$486 Mcost estimate as printed p. 9
05/30/2031projected in service p. 9
Project Developmentstatus as printed p. 9

Profile

PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in December 2026, at a transmission cost estimate of $486 million and a projected in-service date of May 30, 2031. (p. 1, p. 5, p. 9) The need, first presented in November 2026 under the title Big Bass / Tamarack, is a request from the customer associated with need PPL-2025-0012 for a third 230kV delivery point with an additional 700MW of load, requested in service by May 2030. (p. 12, p. 5) PPL lists an initial load of 250 MW expected in May 2030 and a total of 700 MW expected in May 2032. (p. 5) That earlier need, Big Bass, PA, is a request to serve a facility from a 230kV source in Gouldsboro, Pennsylvania, with a total load of approximately 1,500 MW by 2030. (p. 9) The plan centers on a new Tamarack station with a 230kV switchyard ($118 million, with a STATCOM and a capacitor bank) and a 500kV yard ($88 million, two 750MVA 500-230kV transformers), fed by a new ~25 miles double circuit 500kV line from a new Sandy Run 500kV switchyard, the largest line item at $213 million. (p. 6, p. 7) Sandy Run would be cut into the existing Susquehanna - Wescosville (Orefield) 500kV line, and Tamarack into the Acahela - Big Bass 230kV line, with three 230kV circuits of ~1.0 miles between Tamarack and Big Bass. (p. 6, p. 7) PPL lists no feasible alternative and gives the project status as Project Development. (p. 9)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Sandy Run 500kV switchyardNew four bay 500kV switchyard; estimated $40 Mp. 6
Susquehanna - Wescosville (Orefield) 500kV lineBifurcate into the new Sandy Run 500kV switchyard; estimated $10 Mp. 6
Tamarack 230kV yardSeven bays of new BAAH 230kV switchyard with one 144 MVAR capacitor bank and one 250+/-MVAR STATCOM; estimated $118 Mp. 6
Tamarack 500kV yardFour bays of a 500kV yard with two 500-230kV (750MVA) transformers; estimated $88 Mp. 6
Sandy Run - Tamarack 500kV lineNew ~25 miles double circuit 500kV line from Sandy Run 500kV switchyard to the Tamarack 500-230kV substation (cost printed on the next slide)p. 6
Tamarack 230kV customer lead linesThree 230kV lead lines, approximately 0.6 miles, to the customer's third substation; estimated $6 Mp. 7
Acahela - Big Bass 230kV lineBifurcate into the new Tamarack 230kV switchyard (~0.25 miles); estimated $4 Mp. 7
Tamarack - Big Bass 230kV lineThree 230kV circuits between Big Bass and Tamarack 230kV yards (~1.0 miles); estimated $7 Mp. 7

Details as printed

Need presentedNeed Meeting TEAC - 11/03/2026, under the title Big Bass / Tamarackp. 12
Project driverCustomer Servicep. 5
Customer request, third delivery pointThe customer associated with PPL-2025-0012 requested a third 230kV delivery point with an additional 700MW of load; requested in service 05/2030p. 5
Load rampInitial load 250 MW expected 05/2030; total load 700 MW expected 05/2032p. 5
Same customer's earlier request (PPL-2025-0012)PPL-2025-0012 (Big Bass, PA): facility served from a 230kV source in Gouldsboro, PA; approximately 1,500 MW total (2030); requested in service 05/2027p. 9
Sandy Run - Tamarack 500kV line costSandy Run - Tamarack line estimated $213 M (cost line continued from the previous slide)p. 7
Alternatives consideredNo Feasible Alternativep. 9

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 3, 2026Item 05 - PPL Supplemental Projects - PresentationBig Bass / Tamarack not printed05/2030Need Meeting TEAC - 11/03/2026
December 1, 2026Item 05 - PPL Supplemental Projects - PresentationTamarack 500-230kV Substation $486 M05/30/2031Project Development

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.