Project Avalon
Project Avalon. Presented by AEP in PJM planning materials (AEP zone, WV).
Profile
AEP presented Project Avalon to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $224.906 million and a projected in-service date in September 2029. (p. 1, p. 23, p. 25) The driver listed is customer service: a customer has requested new service for 1,200 MW in Putnam County, West Virginia by September 2029. (p. 23) AEP first presented the need at the May 2026 meeting under the heading Manilla Ridge, WV, with the same problem statement; that deck printed no cost or solution. (p. 3, p. 23) The plan is a new Manilla Ridge 765/345 kV station with two 765/345 kV 2250 MVA transformers and 345 kV metering on six customer feeds, estimated at $200.856 million, which AEP says does not include the portion to be paid by the customer. (p. 24) The station would be cut into the existing Culloden - Gavin 765 kV line by two new single circuit 765 kV extensions of approximately 2 miles, estimated at $24.05 million. (p. 24) AEP says no other viable alternatives were identified; service from a 765/138 kV transformer was considered but would have required more transformer banks. (p. 25) AEP lists the project status as Scoping. (p. 25)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Manilla Ridge 765 kV Extension | Cut in/out of the existing Culloden - Gavin 765 kV line; two new single circuit 765 kV extensions to the new Manilla Ridge station (approx. 2 miles), with line reactor/breakers toward Gavin and toward Culloden; estimated $24.05 M | p. 24 |
| Manilla Ridge 765/345 kV station | New station: six 765 kV circuit breakers, twelve 345 kV circuit breakers, two 765/345 kV 2250 MVA transformers, 345 kV metering on six customer feeds; excludes the customer-reimbursable portion; estimated $200.856 M | p. 24 |
Details as printed
| Previously presented | Need Meeting TEAC - 05/08/2026 | p. 23 |
|---|---|---|
| Need meeting, May 2026 | Need presented as "Manilla Ridge, WV", Need Meeting 05/08/2026 | p. 3 |
| Project driver | Customer Service | p. 23 |
| Customer request, Putnam County | 1200 MW in Putnam County, West Virginia by 9/2029 | p. 23 |
| Alternatives considered | No other viable alternatives identified; service from a 765/138 kV transformer was considered but would have required more transformer banks | p. 25 |
| Model | 2030 RTEP | p. 25 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| May 8, 2026 | Item 04 - AEP Supplemental Projects PDF | Manilla Ridge, WV | not printed | 9/2029 | Need Meeting 05/08/2026 |
| December 1, 2026 | Item 03 - AEP Supplemental Projects - Presentation | Project Avalon | $224.906 M | 09/01/2029 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Manilla Ridge (AEP): described as new
- Culloden (AEP)
- Gavin (AEP)
Not printed
- The deck names the customer only as a customer; it does not say what the load is.
- The deck does not print a county or state for Manilla Ridge station itself; West Virginia and Putnam County come from the customer request.
- The May 2026 need deck prints no cost, in-service date or status.
- No news article found that names Project Avalon or Manilla Ridge; none is listed. Press coverage of a Google data center site in Putnam County exists, but none ties it to this PJM need, so it is not linked.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.