Substation Scout

Project Avalon

Project Avalon. Presented by AEP in PJM planning materials (AEP zone, WV).

$224.906 Mcost estimate as printed p. 25
09/01/2029projected in service p. 25
Scopingstatus as printed p. 25

Profile

AEP presented Project Avalon to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $224.906 million and a projected in-service date in September 2029. (p. 1, p. 23, p. 25) The driver listed is customer service: a customer has requested new service for 1,200 MW in Putnam County, West Virginia by September 2029. (p. 23) AEP first presented the need at the May 2026 meeting under the heading Manilla Ridge, WV, with the same problem statement; that deck printed no cost or solution. (p. 3, p. 23) The plan is a new Manilla Ridge 765/345 kV station with two 765/345 kV 2250 MVA transformers and 345 kV metering on six customer feeds, estimated at $200.856 million, which AEP says does not include the portion to be paid by the customer. (p. 24) The station would be cut into the existing Culloden - Gavin 765 kV line by two new single circuit 765 kV extensions of approximately 2 miles, estimated at $24.05 million. (p. 24) AEP says no other viable alternatives were identified; service from a 765/138 kV transformer was considered but would have required more transformer banks. (p. 25) AEP lists the project status as Scoping. (p. 25)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Manilla Ridge 765 kV ExtensionCut in/out of the existing Culloden - Gavin 765 kV line; two new single circuit 765 kV extensions to the new Manilla Ridge station (approx. 2 miles), with line reactor/breakers toward Gavin and toward Culloden; estimated $24.05 Mp. 24
Manilla Ridge 765/345 kV stationNew station: six 765 kV circuit breakers, twelve 345 kV circuit breakers, two 765/345 kV 2250 MVA transformers, 345 kV metering on six customer feeds; excludes the customer-reimbursable portion; estimated $200.856 Mp. 24

Details as printed

Previously presentedNeed Meeting TEAC - 05/08/2026p. 23
Need meeting, May 2026Need presented as "Manilla Ridge, WV", Need Meeting 05/08/2026p. 3
Project driverCustomer Servicep. 23
Customer request, Putnam County1200 MW in Putnam County, West Virginia by 9/2029p. 23
Alternatives consideredNo other viable alternatives identified; service from a 765/138 kV transformer was considered but would have required more transformer banksp. 25
Model2030 RTEPp. 25

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
May 8, 2026Item 04 - AEP Supplemental Projects PDFManilla Ridge, WV not printed9/2029Need Meeting 05/08/2026
December 1, 2026Item 03 - AEP Supplemental Projects - PresentationProject Avalon $224.906 M09/01/2029Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first