Brandon Shores deactivation upgrades

Brandon Shores Deactivation Project. Presented by PJM in PJM planning materials (BGE zone).

$1,513.96 millioncost estimate as printed p. 15
12/31/2028projected in service p. 15
Previously approved; cost changes reportedstatus as printed p. 12

Profile

PJM Transmission Planning told PJM's Transmission Expansion Advisory Committee on February 4, 2025 that the estimated cost of the Brandon Shores deactivation upgrades had changed from $738.83 million to $1,513.96 million, an increase of $775.13 million. (p. 1, p. 13, p. 15) PJM's planning case for 2028 removes the Brandon Shores generators as per their deactivation notice, and the upgrades were approved under a Brandon Shores Deactivation Immediate Need. (p. 13, p. 20) The largest increases in the cost table are the Brighton STATCOM and capacitor ($63 million to $229 million), the Graceton 500 kV expansion ($82 million to $213.2 million) and the Solley Road substation and STATCOM ($109 million to $239.6 million). (p. 13) The drivers Exelon lists include vendor quotes above the earlier budgetary quotes, a change of the new Batavia substation from air insulated to gas insulated because of space constraints and wetland conditions, and higher construction and engineering labor rates. (p. 14) The February 2025 deck projects an in-service date of December 31, 2028 against a required date of June 1, 2025; the December 5, 2023 deck had projected 2026-2028. (p. 1, p. 15, p. 1, p. 21) In December 2023 PJM recommended canceling a planned 500/230 kV West Cooper substation, estimated at $60 million, and the 2025 table lists it as canceled and replaced with the new Bramah (North Delta) 500/230 kV substation. (p. 1, p. 20, p. 1, p. 15)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Peach Bottom North substation work (b3780.1)PECO; $33 M original, $76.63 M updatedp. 13
Peach Bottom - Graceton 500 kV line (PECO) (b3780.2)New 500 kV line, PECO; $48 M original, $63.74 M updatedp. 13
West Cooper substation (b3780.3)Canceledp. 13
Peach Bottom - Graceton (BGE) (b3780.4)BGE; $17 M original, $38.8 M updatedp. 13
Solley Road substation + STATCOM (b3780.5)Build substation + STATCOM, BGE; $109 M original, $239.6 M updatedp. 13
Granite substation + STATCOM (b3780.6)Build substation + STATCOM, BGE; $91 M original, $198.6 M updatedp. 13
Batavia Road substation (b3780.7)Build substation, BGE; $36 M original, $127.8 M updatedp. 13
Graceton 500 kV expansion (b3780.8)3 breaker bays, 2 autotransformers, capacitors, BGE; $82 M original, $213.2 M updatedp. 13
Graceton - Batavia Road 230 kV line (b3780.9)Double circuit, BGE; $195 M original, $207.2 M updatedp. 13
Conastone capacitor (b3780.10)BGE; $15 M original, $33.7 M updatedp. 13
Brighton STATCOM and capacitor (b3780.11)PEPCO; $63 M original, $229 M updatedp. 13
Burchess Hill capacitor (b3780.12)PEPCO; $15 M original, $12 M updatedp. 13
Batavia Road - Riverside 230 kV reconductor (b3780.13)BGE; $21 M original, $57.3 M updatedp. 13
Cooper - Bramah 230 kV line (b3780.14)New Cooper-Bramah 230 kV line, PECO; $3.6 M original, $6.73 M updatedp. 13
5012 line cut-in at Bramah (PECO) (b3780.15)PECO; $7.86 M original, $7.29 M updatedp. 13
Cooper - Bramah 230 kV termination at Bramah (b3780.16)Transource; $0.47 M, unchangedp. 13
5012 line cut-in at Bramah (Transource) (b3780.17)Transource; $1.1 M, unchangedp. 13
Doubs transformer 3 line drops (b3781)APS; $0.8 M, unchangedp. 13

Details as printed

MeetingTransmission Expansion Advisory Committee, February 4, 2025p. 1
Cost original$738.83 million (original estimate)p. 13
Cost change$775.13 million increasep. 13
Required in service6/1/2025 (required)p. 15
DriverPJM's 2028 base case removes the Brandon Shores generators as per the deactivation noticep. 13
Immediate needApproved under the Brandon Shores Deactivation Immediate Needp. 20
Meeting 2023Transmission Expansion Advisory Committee, December 5, 2023p. 1
Schedule 2023Required June 2025; projected 2026-2028p. 21
West cooper cancelPJM recommended canceling B3780.3, the 500/230 kV West Cooper substation, estimated at $60Mp. 20
West cooper replacedWest Cooper canceled, replaced with the new Bramah (North Delta) 500/230 kV substation (Transource B3737.47)p. 15
Cost driver quotesVendor quotes for long lead equipment came in above earlier budgetary quotesp. 14
Cost driver bataviaNew Batavia substation changed from air insulated to gas insulated, due to space constraints and wetland conditionsp. 14
Cost driver laborConstruction and engineering labor rates have increasedp. 14

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 3PJM recommended adjustments to Earlier Approved Brandon Shores De-Activation Scope $60M2026-2028
February 4, 2025Item 12 - Reliability Analysis Update PDFBrandon Shores Deactivation Project Updates: Summary of Cost Changes 1513.9612/31/2028

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.