Zeus 230kV Delivery
Zeus 230kV Delivery. Presented by Dominion in PJM planning materials (Dominion zone, VA).
Profile
Dominion presented this program to PJM's Transmission Expansion Advisory Committee as a supplemental project at its October 2026 solution meeting, at an estimated cost of $256 million ($37 million substation, $219 million transmission). (p. 1, p. 8) The driver printed is a delivery point request from Central Virginia Electric Cooperative (CVEC) to serve a 300 MW data center customer in Appomattox, Virginia, north of Dominion's South Creek 115kV substation; the deck does not name the customer. (p. 7, p. 3) Stage 1 taps the existing Pamplin - South Creek 115kV line to a new Willow Brook delivery point and adds a 33.67 MVAR capacitor bank at Pamplin, with the customer building the line from the tap point. (p. 8) Stage 2 builds a new Zeus 230kV substation and a new double circuit 230kV line of about 35 miles from Farmville, which is to be expanded; Zeus is laid out as a six-breaker ring with 4 breakers installed initially. (p. 8) Dominion lists Stage 1 for Q3 2027 and Stage 2 for Q4 2030, and the project status as Engineering. An alternative that would rebuild about 68 miles of existing 115kV lines to 230kV was estimated at $450 million. (p. 8) When the need was first presented in May 2025, the request was up to 50 MW via existing 115kV facilities in 18 to 24 months and 300 MW by May 2029; the October 2026 slide lists 20 MW of initial service, no date for the full 300 MW, and a projected 2031 load of 180 MW. (p. 3, p. 7, p. 8)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Stage 1: 115kV tap to Willow Brook DP | Tap Line #1006 (Pamplin - South Creek) and extend a single circuit 115kV line to the new Willow Brook delivery point; the customer builds the line from the tap point | p. 8 |
| Stage 1: Pamplin substation | Add a 33.67 MVAR capacitor bank | p. 8 |
| Stage 2: Farmville - Zeus 230kV line | New double circuit 230kV feed from Farmville 230kV substation, about 35 miles | p. 8 |
| Stage 2: Zeus 230kV substation | New substation; 230kV six-breaker ring arrangement with 4 installed initially | p. 8 |
| Stage 2: Farmville substation | Expanded, with additional breakers for the new lines | p. 8 |
Details as printed
| Need first presented | Need Meeting 05/06/2025 | p. 3 |
|---|---|---|
| Customer request, as presented May 2025 | CVEC delivery point request for a 300 MW data center customer in Appomattox, VA, north of South Creek 115kV substation; up to 50 MW via existing 115kV facilities in 18 to 24 months; 300 MW in May 2029 | p. 3 |
| Load table, May 2025 | Initial in-service load 50 MW; projected 2030 load 300 MW (summer and winter) | p. 3 |
| Customer request, as presented October 2026 | Same 300 MW data center request; initial service of 20 MW via existing 115kV facilities; no target date printed for the ultimate load | p. 7 |
| Load table, October 2026 | Initial in-service load 50 MW; projected 2031 load 180 MW (summer and winter) | p. 7 |
| Alternative considered | Convert existing 115kV facilities: rebuild about 68 miles of 115kV single circuit to 230kV double circuit and expand four substations; estimated $450M | p. 8 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| May 6, 2025 | Item 09 - DOM Supplemental Projects PDF | Dominion Transmission Zone: Supplemental Customer Load Request | not printed | May 2029 | Need Meeting 05/06/2025 |
| October 6, 2026 | Item 14 - DOM Supplemental Projects - Presentation PDF | Dominion Transmission Zone: Supplemental Zeus 230kV Delivery - DEV | $256M | Stage1 - Q3 2027, Stage 2 - Q4 2030 | Engineering |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Willow Brook DP (DOM): described as new
- Zeus (DOM): described as new
- Farmville (DOM)
- Pamplin (DOM)
- South Creek (DOM)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Dominion Energy plans Zeus power line for proposed Appomattox County data center, WSET, October 7, 2026. WSET reported that Dominion Energy mailed notices about the Zeus Project, a proposed transmission line tied to a planned data center in Appomattox County, to 6,015 property owners, and that Dominion must select a final route and get state approval before construction.
- Families push back against proposed Dominion Energy Transmission Line Project, WSET, November 6, 2026. WSET reported that Dominion renamed the Zeus 230 kV project the Elk Creek Project at a November community meeting, that the line would run from a substation in Farmville to Appomattox County to help power a new data center along one of three proposed routes, that it still needs State Corporation Commission approval, and that construction could begin in 2029 with completion by 2030; Appomattox families raised objections.
Not printed
- The decks name the customer only as a data center customer of CVEC; they do not name it.
- No county is printed; Appomattox appears as the customer's location ("Appomattox, VA"). No location is printed for the Zeus substation or the Willow Brook delivery point beyond the site being north of South Creek.
- The 2026 slide gives no date for the ultimate 300 MW load; its load table projects 180 MW in 2031.
- No upgrade (b-number) is printed for this need.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.