Harwood (Tomhicken switchyard)

Harwood, PA. Presented by PPL in PJM planning materials (PPL zone, PA).

$195.55 Mcost estimate as printed p. 13
06/01/2027projected in service p. 13
Conceptualstatus as printed p. 13

Profile

PPL included this customer service project in its 2026 Local Plan submission (stage date March 13, 2026), shown to PJM's Transmission Expansion Advisory Committee in October 2026, at a transmission cost estimate of $195.55 million and a projected in-service date of June 2027. (p. 13, p. 12) The need, first presented in June 2024, is a customer request to serve a facility from a 230kV source in Hazleton, Pennsylvania, with a total load of approximately 1,980 MW by 2033 and a requested in-service date of May 2026; PPL lists the load ramping from 240MW in 2026 to 720 MW in 2028 and 1,440 MW in 2031. (p. 12) The plan builds two new 230kV switchyards, Tomhicken (six bays with a 125MVAR capacitor bank, $45 million) and Nescopeck (three bays, $29.5 million), joined by a ~9-mile double circuit 230kV line built for 500kV and extended 2.7 miles to Harwood, at $80.5 million. (p. 13) It also cuts the Susquehanna - Harwood #1 & #2 and Sunbury - Susquehanna #1 230kV lines into the new switchyards, rebuilds 3.9 miles of the Sunbury - Susquehanna #1 line to double circuit at $17.2 million, expands the Susquehanna 230kV yard at $10 million, and adds four 230kV lead lines of approximately 0.1 miles to the customer facility. (p. 13) The 2024 Local Plan submission printed $196.55 million, with a Susquehanna T10 yard bay, a Glen Brook - Susquehanna line cut-in, and only a new line terminal ($2 million) at Susquehanna 230kV. (p. 30, p. 31) At an updated TEAC presentation in May 2025, PPL printed $197.55 million and marked the T10 bay and the Glen Brook cut-in as replaced by B3910.1; the 2026 submission omits both items and prints $195.55 million. (p. 13, p. 12, p. 13, p. 12) PPL lists one alternative, a rebuild and third 230kV circuit between Susquehanna and Harwood estimated at $199 million, which it called infeasible because of outage conflicts with the S2374 rebuild; the status changed from Development in May 2025 to Conceptual in the 2026 submission. (p. 13, p. 13, p. 12)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Tomhicken 230kV switchyardSix bay BAAH 230kV switchyard with a 125MVAR capacitor bank; estimated $45 M (s3528.1)p. 13
Nescopeck 230kV switchyardNew three bay BAAH 230kV switchyard; estimated $29.5 M (s3528.2)p. 13
Susquehanna 230kV switchyardExpand yard, extend busses, install two new bays, two dead-ends and four 230kV breakers; rebuild the East and West bus to higher capacity; estimated $10 M (s3528.3)p. 13
Harwood 230kV substationNew line terminal with one dead-end and two breakers; new bay DBDB initial, future BAAH; estimated $4 M (s3528.4)p. 13
Susquehanna - Harwood #1 & #2 230kV linesBifurcate the Susquehanna - Harwood #1 & #2 230kV and terminate at the new Tomhicken switchyard (approximately 0.25); estimated $3.7 M (s3528.5)p. 13
Sunbury - Susquehanna #1 230kV lineBifurcate into the new Nescopeck switchyard (approximately 0.2); estimated $1.85 M (s3528.6)p. 13
Sunbury - Susquehanna #1 230kV partial rebuildRebuild to double circuit 230kV for 3.9 miles from the Susquehanna yard to the new Nescopeck switchyard; estimated $17.2 M (s3528.7)p. 13
Nescopeck - Tomhicken / Harwood 230kV linesDouble circuit 230kV (built for 500kV) for ~9 miles from Nescopeck to Tomhicken on existing PPL ROW, then single circuit 230kV for 2.7 miles from Tomhicken to Harwood; estimated $80.5 M (s3528.8)p. 13
Tomhicken customer tapsFour 230kV lead lines for approximately 0.1 miles from the Tomhicken switchyard to the customer facility; estimated $3.8 M (s3528.9)p. 13

Details as printed

Project driverCustomer Servicep. 12
Customer request, HazletonFacility served from a 230kV source in Hazleton, PA; approximately 1,980 MW total (2033); requested in service 05/2026p. 12
Load ramp240MW initial in-service 2026; 720 MW projected 2028; 1,440 MW projected 2031p. 12
2024 Local PlanSubmission of Supplemental Project for inclusion in the Local Plan 10/15/2024p. 30
Cost, 2024 Local Plan$196.55 Mp. 31
In-service, 2024 Local Plan6/1/2026 for S3528.1, S3528.6 and S3528.11; 6/1/2027 for the restp. 31
Susquehanna yard, 2024 Local PlanSusquehanna 230kV yard: a new line terminal; estimated $2 Mp. 31
Solution updatedSolution Meeting TEAC 08/06/2024, updated at TEAC 5/6/2025p. 13
Cost, May 2025 update$197.55 Mp. 13
Status, May 2025 updateDevelopmentp. 13
Item replaced, May 2025Susquehanna T10 230kV yard bay ($6M), marked Replaced by B3910.1p. 12
Item replaced, May 2025Glen Brook - Susquehanna 230kV line cut into the Susquehanna T10 yard ($3 M), marked Replaced by B3910.1p. 12
Alternative consideredRebuild the Susquehanna - Harwood #1 & #2, install a third 230kV circuit from Susquehanna to Harwood, and break GLBR-SUSQ into the SU10 yard; infeasible due to outage conflicts with the HARW-SIEG/EPAL 230kV rebuild under S2374 and lack of operational flexibility; estimated $199 millionp. 13

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
May 6, 2025Item 07 - PPL Supplemental Projects PDF $197.55 M06/01/2027Development
October 6, 2026Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 PDFHarwood, PA $195.55 M06/01/2027Conceptual
Date not printedPPL&nbsp PDFHarwood, PA $195.55 M06/01/2027Conceptual
Date not printedPPL&nbsp PDF $196.55 M6/1/2026: S3528.1, S3528.6, & S3528.11 6/1/2027: S3528.2, S3528.3, S3528.4, S3528.5, S3528.7, S3528.8, S3528.9, S3528.10Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.