Customer in Dekalb (ComEd-2024-001)
Customer in Dekalb. Presented by ComEd in PJM planning materials (ComEd zone).
Profile
ComEd presented Customer in Dekalb (need ComEd-2024-001, supplemental projects s3342.1 and s3342.2) to PJM's TEAC Western Committee on October 8, 2025 as a scope change, at an estimated transmission cost of $215 million, up from the $175 million printed beside it. (p. 8, p. 1) The deck describes a new customer looking for transmission service in the Dekalb area, with initial loading of 49 MW in June 2027, 160 MW in 2028 and an ultimate load of 210 MW in 2029, plus a ComEd distribution request for 15 MW of load growth. (p. 8) The solution is a new Keslinger substation: two 6 mile 345 kV extensions from line 15502 to a breaker-and-a-half bus, four radial 345 kV leads to customer owned transformers, a 138 kV bus fed by four 0.4 mile extensions from lines 11106 and 11307, and new 345/138 kV and 138/34 kV transformers. (p. 8) The same slide gives the reason for the scope change as the substation location changing on the customer property, lists the projected in-service date as 12/31/27, and gives the status as Engineering. (p. 8) ComEd's 2024 Local Plan submission, dated July 10, 2024, listed the project at $175 million with the status Conceptual, 53 MW of initial load in June 2027, the 345 kV bus by 12/31/2026, and 0.7 mile extensions from lines 8309 and 11307; it says the need meeting was 1/9/2024 and the solution meeting 2/6/2024. (p. 14, p. 15) Two later Customer in DeKalb needs, each for a separate new customer, built on Keslinger: ComEd-2025-009 (ultimate 504 MW in 2033, a $245 million solution including a new 1.5-mile line from Keslinger to a new Gurler substation) and ComEd-2025-010 (ultimate 860 MW in 2030, a $30 million solution with 4 new 345kV breakers at Keslinger). (p. 4, p. 5, p. 6, p. 7) ComEd's supplemental needs withdrawal lists in its March 2026 and July 2026 TEAC decks mark ComEd-2025-009 and ComEd-2025-010 as Withdraw Need. (p. 2, p. 2)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Keslinger 345kV substation (new) | Cut into 345kV line 15502, extend 2 lines 6 miles each to a new Keslinger 345 kV breaker-and-a-half bus by 6/30/2027 | p. 8 |
| Customer leads | Four radial 345kV leads to customer owned transformers | p. 8 |
| Keslinger 138kV bus (new) | Cut into 138 kV lines 11106 and 11307, extend 4 lines 0.4 miles to a new Keslinger 138 kV breaker-and-a-half bus by 12/31/2027 | p. 8 |
| Keslinger distribution transformers | Two new 138/34 kV distribution transformers | p. 8 |
| Keslinger 345/138 kV transformers | Two new 345/138 kV transformers | p. 8 |
Details as printed
| Reason for the scope change | Location of substation changed on customer property | p. 8 |
|---|---|---|
| Project driver | Customer Service | p. 14 |
| Customer request, Dekalb | 49 MW in June 2027, 160 MW in 2028, ultimate 210 MW in 2029 | p. 8 |
| Distribution request, Dekalb | ComEd Distribution Capacity Planning requested capacity for 15 MW of load growth | p. 8 |
| Model | 2029 RTEP | p. 8 |
| Local Plan submission | Submission of Supplemental Project for inclusion in the Local Plan July 10, 2024 | p. 14 |
| Previously presented | Solution Meeting 2/6/2024; Need Meeting 1/9/2024 | p. 14 |
| Customer request, Local Plan version | 53 MW in June 2027, 160 MW in 2028, ultimate 210 MW | p. 14 |
| Cost in the Local Plan submission | $175M | p. 15 |
| Status in the Local Plan submission | Conceptual | p. 15 |
| 345 kV date, Local Plan version | 345 kV breaker-and-a-half bus at Keslinger by 12/31/2026 | p. 15 |
| 138 kV lines, Local Plan version | Cut into 138 kV lines 8309 and 11307, extend 4 lines 0.7 miles to Keslinger | p. 15 |
| Customer request, ComEd-2025-009 | 12 MW in 2029, 48 MW in June 2030, ultimate 504 MW in 2033 | p. 4 |
| ComEd-2025-009 proposed solution (ties to Keslinger) | New 1.5-mile 345kV line from Keslinger substation (s3342.1) to a new Gurler substation | p. 5 |
| ComEd-2025-009 cost, February 2026 | $245M, projected in service 12/4/2029, Conceptual | p. 5 |
| ComEd-2025-009 withdrawn, March 10, 2026 | Customer in DeKalb (ComEd-2025-009) listed as Withdraw Need | p. 2 |
| Customer request, ComEd-2025-010 | 50 MW in June 2029, ultimate 860 MW in 2030 | p. 6 |
| ComEd-2025-010 proposed solution (at Keslinger) | Install 4 new 345kV breakers at Keslinger to connect new radial lines to the customer | p. 7 |
| ComEd-2025-010 cost, February 2026 | $30M, projected in service 10/31/2028 | p. 7 |
| ComEd-2025-010 withdrawn, July 7, 2026 | ComEd-2025-010 on the withdrawal list | p. 2 |
| TO note, ComEd-2025-009 | Withdraw Need | p. 2 |
| Later DeKalb need ComEd-2025-010 | Separate Customer in DeKalb need ComEd-2025-010 | p. 6 |
| TO note, ComEd-2025-010 | Withdraw Need | p. 2 |
| Later DeKalb need ComEd-2025-009 | Separate Customer in DeKalb need ComEd-2025-009, need meeting 9/9/2025 | p. 4 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| October 8, 2024 | Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2024 PDF | Customer in Dekalb | $175M | 12/31/27 | Conceptual |
| October 8, 2025 | Item 11 - ComEd Supplemental Projects PDF | Customer in Dekalb | $215M | 12/31/27 | Engineering |
| Date not printed | ComEd  PDF | Customer in Dekalb | $175M | 12/31/27 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Keslinger (COMED): described as new
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- KARE Transmission Project in DeKalb, Illinois, Gets Construction Approval, Construction Review Online, August 24, 2026. Construction Review Online reported that the Illinois Commerce Commission granted ComEd a certificate for its Kishwaukee Area Reliability Extension (KARE) project, about 6.8 miles of new 345 kV line and a new 345/138 kV substation near Keslinger Road and Crego Road in Afton Township, at about $197 million for the preferred route according to ICC filings, serving an unnamed customer seeking up to 210 MW.
- ComEd Receives Green Light on Transmission Project in DeKalb County, T&D World, September 23, 2026. T&D World reported that the Illinois Commerce Commission approved ComEd's KARE project, about 6 miles of double-circuit 345 kV line and a new 345 kV and 138 kV substation near Keslinger Road and Crego Road south of DeKalb, the first ComEd line needing ICC siting approval since Grand Prairie Gateway.
Not printed
- No state or county is printed on the cited pages; Illinois is not printed. The news articles place the substation in Afton Township south of DeKalb; that is attributed to them, not to PJM.
- The PJM slides never use the name KARE (Kishwaukee Area Reliability Extension); the link to this need rests on the news articles' description (new 345/138 kV substation on Keslinger Road, a 210 MW customer).
- The deck names the customer only as a new customer; it does not say what the load is.
- The October 8, 2025 slide prints $175M and $215M side by side, read here as a revision from $175M to $215M; the PDF text does not show strike-through formatting.
- ComEd-2025-009 and ComEd-2025-010 are separate needs for separate new customers that connect at Keslinger (s3342.1); both were withdrawn, so they are listed as context, not members. Charter Grove, part of the ComEd-2025-009 solution, reappears in the 345KV STATCOMS program (comed-345kv-statcoms).
- The 2024 Local Plan was also reposted (PDF created March 26, 2025, no meeting date); its Dekalb pages match the October 2024 copy cited here.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.