Customer in Dekalb (ComEd-2024-001)

Customer in Dekalb. Presented by ComEd in PJM planning materials (ComEd zone).

$215Mcost estimate as printed p. 8
12/31/27projected in service p. 8
Engineeringstatus as printed p. 8

Profile

ComEd presented Customer in Dekalb (need ComEd-2024-001, supplemental projects s3342.1 and s3342.2) to PJM's TEAC Western Committee on October 8, 2025 as a scope change, at an estimated transmission cost of $215 million, up from the $175 million printed beside it. (p. 8, p. 1) The deck describes a new customer looking for transmission service in the Dekalb area, with initial loading of 49 MW in June 2027, 160 MW in 2028 and an ultimate load of 210 MW in 2029, plus a ComEd distribution request for 15 MW of load growth. (p. 8) The solution is a new Keslinger substation: two 6 mile 345 kV extensions from line 15502 to a breaker-and-a-half bus, four radial 345 kV leads to customer owned transformers, a 138 kV bus fed by four 0.4 mile extensions from lines 11106 and 11307, and new 345/138 kV and 138/34 kV transformers. (p. 8) The same slide gives the reason for the scope change as the substation location changing on the customer property, lists the projected in-service date as 12/31/27, and gives the status as Engineering. (p. 8) ComEd's 2024 Local Plan submission, dated July 10, 2024, listed the project at $175 million with the status Conceptual, 53 MW of initial load in June 2027, the 345 kV bus by 12/31/2026, and 0.7 mile extensions from lines 8309 and 11307; it says the need meeting was 1/9/2024 and the solution meeting 2/6/2024. (p. 14, p. 15) Two later Customer in DeKalb needs, each for a separate new customer, built on Keslinger: ComEd-2025-009 (ultimate 504 MW in 2033, a $245 million solution including a new 1.5-mile line from Keslinger to a new Gurler substation) and ComEd-2025-010 (ultimate 860 MW in 2030, a $30 million solution with 4 new 345kV breakers at Keslinger). (p. 4, p. 5, p. 6, p. 7) ComEd's supplemental needs withdrawal lists in its March 2026 and July 2026 TEAC decks mark ComEd-2025-009 and ComEd-2025-010 as Withdraw Need. (p. 2, p. 2)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Keslinger 345kV substation (new)Cut into 345kV line 15502, extend 2 lines 6 miles each to a new Keslinger 345 kV breaker-and-a-half bus by 6/30/2027p. 8
Customer leadsFour radial 345kV leads to customer owned transformersp. 8
Keslinger 138kV bus (new)Cut into 138 kV lines 11106 and 11307, extend 4 lines 0.4 miles to a new Keslinger 138 kV breaker-and-a-half bus by 12/31/2027p. 8
Keslinger distribution transformersTwo new 138/34 kV distribution transformersp. 8
Keslinger 345/138 kV transformersTwo new 345/138 kV transformersp. 8

Details as printed

Reason for the scope changeLocation of substation changed on customer propertyp. 8
Project driverCustomer Servicep. 14
Customer request, Dekalb49 MW in June 2027, 160 MW in 2028, ultimate 210 MW in 2029p. 8
Distribution request, DekalbComEd Distribution Capacity Planning requested capacity for 15 MW of load growthp. 8
Model2029 RTEPp. 8
Local Plan submissionSubmission of Supplemental Project for inclusion in the Local Plan July 10, 2024p. 14
Previously presentedSolution Meeting 2/6/2024; Need Meeting 1/9/2024p. 14
Customer request, Local Plan version53 MW in June 2027, 160 MW in 2028, ultimate 210 MWp. 14
Cost in the Local Plan submission$175Mp. 15
Status in the Local Plan submissionConceptualp. 15
345 kV date, Local Plan version345 kV breaker-and-a-half bus at Keslinger by 12/31/2026p. 15
138 kV lines, Local Plan versionCut into 138 kV lines 8309 and 11307, extend 4 lines 0.7 miles to Keslingerp. 15
Customer request, ComEd-2025-00912 MW in 2029, 48 MW in June 2030, ultimate 504 MW in 2033p. 4
ComEd-2025-009 proposed solution (ties to Keslinger)New 1.5-mile 345kV line from Keslinger substation (s3342.1) to a new Gurler substationp. 5
ComEd-2025-009 cost, February 2026$245M, projected in service 12/4/2029, Conceptualp. 5
ComEd-2025-009 withdrawn, March 10, 2026Customer in DeKalb (ComEd-2025-009) listed as Withdraw Needp. 2
Customer request, ComEd-2025-01050 MW in June 2029, ultimate 860 MW in 2030p. 6
ComEd-2025-010 proposed solution (at Keslinger)Install 4 new 345kV breakers at Keslinger to connect new radial lines to the customerp. 7
ComEd-2025-010 cost, February 2026$30M, projected in service 10/31/2028p. 7
ComEd-2025-010 withdrawn, July 7, 2026ComEd-2025-010 on the withdrawal listp. 2
TO note, ComEd-2025-009Withdraw Needp. 2
Later DeKalb need ComEd-2025-010Separate Customer in DeKalb need ComEd-2025-010p. 6
TO note, ComEd-2025-010Withdraw Needp. 2
Later DeKalb need ComEd-2025-009Separate Customer in DeKalb need ComEd-2025-009, need meeting 9/9/2025p. 4

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
October 8, 2024Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2024 PDFCustomer in Dekalb $175M12/31/27Conceptual
October 8, 2025Item 11 - ComEd Supplemental Projects PDFCustomer in Dekalb $215M12/31/27Engineering
Date not printedComEd&nbsp PDFCustomer in Dekalb $175M12/31/27Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.