Substation Scout

Project Amazing Sites 100 and 201

Project Amazing Sites 100 and 201. Presented by AEP in PJM planning materials (AEP zone, IN).

$184.977Mcost estimate as printed p. 12
12/15/2026projected in service p. 12
Scopingstatus as printed p. 12

Profile

Project Amazing Sites 100 and 201 is an AEP customer service project in the New Carlisle, Indiana area, submitted to PJM for inclusion in AEP's 2025 local plan at a transmission cost estimate of $184.977 million and a projected in-service date of December 15, 2026. (p. 11, p. 1, p. 12) The problem statement says a customer requested new service for 1,100 MW of load in the New Carlisle area, with initial service by December 15, 2026; the deck does not name the customer. (p. 11) The plan centers on two new 345kV breaker-and-a-half stations, Larrison Drive ($70.38 million, described as serving 550 MW of new load) and New Prairie ($79.53 million), each with six bus ties to the customer station and cut into the Elderberry-Dumont and Dumont-Olive Bypass 345kV lines. (p. 12) The largest remaining item is $29.287 million of breaker work at Olive 345kV station, alongside remote end work at Sorenson, Elderberry and Dumont and a sag study on the Kenzie Creek - Thomson 345kV line. (p. 12) The 2025 slide lists earlier presentations at an October 31, 2023 needs meeting and solution meetings in June and October 2024; the October 2024 slide prints two figures on its cost line, $155.69 million and $184.977 million. (p. 11, p. 6) AEP states that, given the location of the load and the land available on the customer sites, no other alternatives were viable, and lists the project status as Scoping. (p. 12)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Larrison Drive 345kV stationNew breaker-and-a-half station, sixteen 345kV breakers, to serve 550MW of new load; six bus ties to the customer station; estimated $70.38 Mp. 12
New Prairie 345kV stationNew breaker-and-a-half station, sixteen 345kV breakers; six bus ties to the customer station; estimated $79.53 Mp. 12
Sorenson remote end workRemote end work; estimated $1.72 Mp. 12
Elderberry remote end workRemote end settings work; estimated $1.72 Mp. 12
Dumont remote end workRemote end work; estimated $1.72 Mp. 12
Kenzie Creek - Thomson 345kV lineSag study and mitigation; estimated $0.62 Mp. 12
Olive 345kV stationReplace overdutied 345kV breakers, bring in the Olive Bypass and add 3 new 345kV breakers for a new string; estimated $29.287 Mp. 12

Details as printed

Previously presentedSolution Meetings 10/8/2024 and 6/4/2024; Needs Meeting 10/31/2023p. 11
Supplemental project IDs3588.1-.7p. 12
DriverCustomer Servicep. 11
Customer request, New Carlisle1100MW of new load in the New Carlisle, IN area; initial service requested by 12/15/2026p. 11
Cost line, October 2024 solution meetingTwo figures printed on the cost line: $155.69 M and $184.977Mp. 6
Process stage, October 2024Solution Meeting 10/8/2024p. 5
Alternatives consideredNo other alternatives were viable, given the location of the requested load and land available on the customer sitesp. 12

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
October 8, 2024Item 06 - AEP Supplemental Projects PDFProject Amazing Sites 100 and 201 $184.977M12/15/2026Scoping
October 8, 2025Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 PDFAEP Transmission Zone M-3 Process Project Amazing Sites 100 and 201 $184.977M12/15/2026Scoping
Date not printedAEP&nbsp PDFProject Amazing Sites 100 and 201 $184.977M12/15/2026Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first