Project Amazing Sites 100 and 201
Project Amazing Sites 100 and 201. Presented by AEP in PJM planning materials (AEP zone, IN).
Profile
Project Amazing Sites 100 and 201 is an AEP customer service project in the New Carlisle, Indiana area, submitted to PJM for inclusion in AEP's 2025 local plan at a transmission cost estimate of $184.977 million and a projected in-service date of December 15, 2026. (p. 11, p. 1, p. 12) The problem statement says a customer requested new service for 1,100 MW of load in the New Carlisle area, with initial service by December 15, 2026; the deck does not name the customer. (p. 11) The plan centers on two new 345kV breaker-and-a-half stations, Larrison Drive ($70.38 million, described as serving 550 MW of new load) and New Prairie ($79.53 million), each with six bus ties to the customer station and cut into the Elderberry-Dumont and Dumont-Olive Bypass 345kV lines. (p. 12) The largest remaining item is $29.287 million of breaker work at Olive 345kV station, alongside remote end work at Sorenson, Elderberry and Dumont and a sag study on the Kenzie Creek - Thomson 345kV line. (p. 12) The 2025 slide lists earlier presentations at an October 31, 2023 needs meeting and solution meetings in June and October 2024; the October 2024 slide prints two figures on its cost line, $155.69 million and $184.977 million. (p. 11, p. 6) AEP states that, given the location of the load and the land available on the customer sites, no other alternatives were viable, and lists the project status as Scoping. (p. 12)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Larrison Drive 345kV station | New breaker-and-a-half station, sixteen 345kV breakers, to serve 550MW of new load; six bus ties to the customer station; estimated $70.38 M | p. 12 |
| New Prairie 345kV station | New breaker-and-a-half station, sixteen 345kV breakers; six bus ties to the customer station; estimated $79.53 M | p. 12 |
| Sorenson remote end work | Remote end work; estimated $1.72 M | p. 12 |
| Elderberry remote end work | Remote end settings work; estimated $1.72 M | p. 12 |
| Dumont remote end work | Remote end work; estimated $1.72 M | p. 12 |
| Kenzie Creek - Thomson 345kV line | Sag study and mitigation; estimated $0.62 M | p. 12 |
| Olive 345kV station | Replace overdutied 345kV breakers, bring in the Olive Bypass and add 3 new 345kV breakers for a new string; estimated $29.287 M | p. 12 |
Details as printed
| Previously presented | Solution Meetings 10/8/2024 and 6/4/2024; Needs Meeting 10/31/2023 | p. 11 |
|---|---|---|
| Supplemental project ID | s3588.1-.7 | p. 12 |
| Driver | Customer Service | p. 11 |
| Customer request, New Carlisle | 1100MW of new load in the New Carlisle, IN area; initial service requested by 12/15/2026 | p. 11 |
| Cost line, October 2024 solution meeting | Two figures printed on the cost line: $155.69 M and $184.977M | p. 6 |
| Process stage, October 2024 | Solution Meeting 10/8/2024 | p. 5 |
| Alternatives considered | No other alternatives were viable, given the location of the requested load and land available on the customer sites | p. 12 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| October 8, 2024 | Item 06 - AEP Supplemental Projects PDF | Project Amazing Sites 100 and 201 | $184.977M | 12/15/2026 | Scoping |
| October 8, 2025 | Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 PDF | AEP Transmission Zone M-3 Process Project Amazing Sites 100 and 201 | $184.977M | 12/15/2026 | Scoping |
| Date not printed | AEP  PDF | Project Amazing Sites 100 and 201 | $184.977M | 12/15/2026 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Larrison Drive (AEP): described as new
- New Prairie (AEP): described as new
- Dumont (AEP)
- Elderberry station (AEP)
- Kenzie Creek (AEP)
- Olive (AEP)
- Sorenson (AEP)
- Thomson (AEP)
Not printed
- The deck names the customer only as a customer; it does not say what the load is.
- No county or street location is printed for Larrison Drive or New Prairie.
- No news article about this transmission program could be found and opened; coverage of the New Carlisle area does not mention these stations.
- The June 2024 solution meeting and October 2023 needs meeting decks are not in the archive.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.