2022 Window 3 West Cluster Incumbent Upgrades

Preferred Projects to Address Clusters - West. Presented by PJM in PJM planning materials (FE, Dominion, AEP zone).

$392.55Mcost estimate as printed p. 64
6/1/2027 – 6/1/2030projected in service p. 64
Recommended (baseline)status as printed p. 8

Profile

This is the incumbent utility work in PJM's 2022 Window 3 West cluster, presented on December 5, 2023: the FE, Dominion and AEP scopes of proposal 2022-W3-853, the same proposal whose NextEra scope is profiled separately as the MidAtlantic Resiliency Link (MARL). (p. 1, p. 8, p. 64, p. 65, p. 66, p. 63) The FE scope, estimated at $392.55 million, rebuilds about 16 miles of the Gore - Stonewall 138 kV line, about 15 miles of the Stonewall - Millville line and about 6 miles of the Millville - Doubs line with 500 kV overbuild, a piece FE estimated at $341 million. (p. 64) It also adds two breakers each at the Stonewall 138 kV and 502 Junction 500 kV substations, builds two 138 kV lines from the new Woodside 500 kV substation to Stonewall and terminates the Doubs end of the Doubs - Bismark line into Woodside, with a projected in-service range of June 1, 2027 to June 1, 2030. (p. 64) The Dominion scope, $35.59 million in December 2023, covered Aspen substation work to terminate the new NextEra line and the termination of the Doubs - Bismark line into Woodside; the AEP scope is a $0.1 million LIDAR sag study of the Kammer - 502 Junction 500 kV line. (p. 1, p. 65, p. 66) At the October 6, 2026 TEAC, the Dominion portion was printed at $73.94 million, up from $51.19 million: b3800.120 now terminates the NextEra line from Woodside into Goose Creek, and a new Woodside - Goose Creek 500 kV line of about 3 miles (b3800.375, first presented 7/10/2024) is included. (p. 1, p. 7) Dominion's projected in-service dates moved to September 30, 2030 for b3800.120 and b3800.375 and June 1, 2028 for b3800.118, and the slide attributes the cost increase to upgraded conductor design, geotechnical conditions, crossing requirements, taller structures for EMF and clearance compliance, and forestry and access work, among other items. (p. 7) PJM printed a $940.85 million proposal cost for the West cluster as a whole, which includes NextEra's $512.61 million scope, and framed the window around about 7,500 MW of data center load growth forecast in Dominion (Northern Virginia) and APS (Doubs) and 11,100 MW of announced deactivations. (p. 6, p. 63, p. 2)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Gore - Stonewall - Millville - Doubs 138 kV rebuilds with 500 kV overbuild (FE)Rebuild ~16 miles of Gore - Stonewall, ~15 miles of Stonewall - Millville and ~6 miles of Millville - Doubs 138 kV line with 500 kV overbuild; FE cost estimate $341M (incumbent)p. 64
Stonewall 138 kV breaker expansion (FE)Stonewall 138 kV substation two 138 kV breaker expansion; FE cost estimate $8.3M (incumbent)p. 64
502 Junction 500 kV breaker expansion (FE)502 Junction substation two 500 kV circuit breaker expansion; FE cost estimate $30.6M (incumbent)p. 64
Doubs - Bismark termination, Doubs end (FE)Line termination scope for the Doubs end of the Doubs - Bismark line into the Woodside 500 kV substation; FE cost estimate $0.06M (incumbent)p. 64
Woodside - Stonewall 138 kV lines (FE)Two 138 kV lines from Woodside 500 kV substation to FE Stonewall 138 kV substation; FE cost estimate $12.59M (incumbent)p. 64
Aspen termination of the NextEra line (Dominion, December 2023)Aspen substation work to terminate the new NextEra 500 kV line; cost estimate $30.49M (incumbent)p. 65
Doubs - Bismark termination into Woodside (Dominion)Line termination scope for terminating the Doubs - Bismark line into the Woodside 500 kV substation; cost estimate $5.1M (incumbent)p. 65
Kammer - 502 Junction 500 kV sag study (AEP)LIDAR sag study of the Kammer to 502 Junction 500 kV line to assess its SE rating and needed upgrades; cost estimate $0.1Mp. 66
NextEra line terminated into Goose Creek (Dominion, b3800.120, October 2026)Terminate the new NextEra 500 kV line from Woodside into Goose Creek substation; the Goose Creek 500 kV cap bank moves to Aspen; $30.49Mp. 7
Woodside - Goose Creek 500 kV line (Dominion, b3800.375)New Woodside - Goose Creek 500 kV line for ~3 miles on single circuit monopole structures within the Doubs - Goose Creek corridorp. 7

Details as printed

FE scopeFE scope of proposal 2022-W3-853, on a West cluster slidep. 64
Incumbent workEach FE item is marked as incumbent workp. 64
Dominion scopeDominion scope of proposal 2022-W3-853, on a West cluster slidep. 65
Dominion scope, December 2023Estimated cost $35.59M for b3800.118 and b3800.120; required and projected in service 6/1/2027p. 65
AEP scopeAEP scope of proposal 2022-W3-853, on a West cluster slidep. 66
AEP scope, December 2023Estimated cost $0.1M for b3800.121; required and projected in service 6/1/2027p. 66
Related: NextEra scope of the same proposal (profiled as MARL)NextEra scope of proposal 2022-W3-853 (bypass Black Oak, terminate at Aspen instead of Gant)p. 63
Related: NextEra scope cost (December 2023)Estimated cost $512.61M for the NextEra scope (b3800.102 and others)p. 63
West cluster proposal cost (all scopes, December 2023)$940.85M proposal cost for the West cluster: new 500 kV line, new 500 kV station, new voltage support devicesp. 6
2022 Window 3 purposePJM: unprecedented data center load growth (~7,500 MW) forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs)p. 2
2022 Window 3 purpose11,100 MW deactivation announcedp. 2
First presentedSelected proposals were previously presented at the Oct 31st TEACp. 14
Dominion cost change meetingPJM, Reliability Analysis Update, TEAC October 6, 2026p. 1
Dominion scope items, October 2026Dominion scope of proposal 2022-W3-853 as updated: b3800.118 Doubs - Bismark termination into Woodside ($5.1M), b3800.120 termination of the NextEra line into Goose Creek ($30.49M), and a new ~3 mile Woodside - Goose Creek 500 kV linep. 7
Dominion portion total, October 2026Transmission estimated cost $73.94M, updated from $51.19Mp. 7
Dominion portion in service, October 2026Required 6/1/2027 (b3800.118/b3800.120) and 6/1/2029 (b3800.375); projected 9/30/2030 (b3800.120 and b3800.375) and 6/1/2028 (b3800.118)p. 7
Dominion portion, previously presented12/5/2023 (b3800.118/b3800.120) and 7/10/2024 (b3800.375)p. 7
Reasons for the Dominion cost changeUpgraded conductor design, catwalk installation, updated geotechnical conditions, additional splice boxes, increased crossing requirements, taller structures for EMF and clearance compliance, and forestry and access work not in the previous projectp. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 3Preferred Projects to Address Clusters - West $392.55M6/1/2027 – 6/1/2030
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 3Preferred Projects to Address Clusters - West $35.59M6/1/2027
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 3Preferred Projects to Address Clusters – West $0.1M6/1/2027
October 6, 2026Item 16 - Reliability Analysis Update - Presentation PDFBaseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion) $73.94M9/30/2030 (b3800.120 & b3800.375), 6/1/2028 (b3800.118)

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.