2022 Window 3 West Cluster Incumbent Upgrades
Preferred Projects to Address Clusters - West. Presented by PJM in PJM planning materials (FE, Dominion, AEP zone).
Profile
This is the incumbent utility work in PJM's 2022 Window 3 West cluster, presented on December 5, 2023: the FE, Dominion and AEP scopes of proposal 2022-W3-853, the same proposal whose NextEra scope is profiled separately as the MidAtlantic Resiliency Link (MARL). (p. 1, p. 8, p. 64, p. 65, p. 66, p. 63) The FE scope, estimated at $392.55 million, rebuilds about 16 miles of the Gore - Stonewall 138 kV line, about 15 miles of the Stonewall - Millville line and about 6 miles of the Millville - Doubs line with 500 kV overbuild, a piece FE estimated at $341 million. (p. 64) It also adds two breakers each at the Stonewall 138 kV and 502 Junction 500 kV substations, builds two 138 kV lines from the new Woodside 500 kV substation to Stonewall and terminates the Doubs end of the Doubs - Bismark line into Woodside, with a projected in-service range of June 1, 2027 to June 1, 2030. (p. 64) The Dominion scope, $35.59 million in December 2023, covered Aspen substation work to terminate the new NextEra line and the termination of the Doubs - Bismark line into Woodside; the AEP scope is a $0.1 million LIDAR sag study of the Kammer - 502 Junction 500 kV line. (p. 1, p. 65, p. 66) At the October 6, 2026 TEAC, the Dominion portion was printed at $73.94 million, up from $51.19 million: b3800.120 now terminates the NextEra line from Woodside into Goose Creek, and a new Woodside - Goose Creek 500 kV line of about 3 miles (b3800.375, first presented 7/10/2024) is included. (p. 1, p. 7) Dominion's projected in-service dates moved to September 30, 2030 for b3800.120 and b3800.375 and June 1, 2028 for b3800.118, and the slide attributes the cost increase to upgraded conductor design, geotechnical conditions, crossing requirements, taller structures for EMF and clearance compliance, and forestry and access work, among other items. (p. 7) PJM printed a $940.85 million proposal cost for the West cluster as a whole, which includes NextEra's $512.61 million scope, and framed the window around about 7,500 MW of data center load growth forecast in Dominion (Northern Virginia) and APS (Doubs) and 11,100 MW of announced deactivations. (p. 6, p. 63, p. 2)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Gore - Stonewall - Millville - Doubs 138 kV rebuilds with 500 kV overbuild (FE) | Rebuild ~16 miles of Gore - Stonewall, ~15 miles of Stonewall - Millville and ~6 miles of Millville - Doubs 138 kV line with 500 kV overbuild; FE cost estimate $341M (incumbent) | p. 64 |
| Stonewall 138 kV breaker expansion (FE) | Stonewall 138 kV substation two 138 kV breaker expansion; FE cost estimate $8.3M (incumbent) | p. 64 |
| 502 Junction 500 kV breaker expansion (FE) | 502 Junction substation two 500 kV circuit breaker expansion; FE cost estimate $30.6M (incumbent) | p. 64 |
| Doubs - Bismark termination, Doubs end (FE) | Line termination scope for the Doubs end of the Doubs - Bismark line into the Woodside 500 kV substation; FE cost estimate $0.06M (incumbent) | p. 64 |
| Woodside - Stonewall 138 kV lines (FE) | Two 138 kV lines from Woodside 500 kV substation to FE Stonewall 138 kV substation; FE cost estimate $12.59M (incumbent) | p. 64 |
| Aspen termination of the NextEra line (Dominion, December 2023) | Aspen substation work to terminate the new NextEra 500 kV line; cost estimate $30.49M (incumbent) | p. 65 |
| Doubs - Bismark termination into Woodside (Dominion) | Line termination scope for terminating the Doubs - Bismark line into the Woodside 500 kV substation; cost estimate $5.1M (incumbent) | p. 65 |
| Kammer - 502 Junction 500 kV sag study (AEP) | LIDAR sag study of the Kammer to 502 Junction 500 kV line to assess its SE rating and needed upgrades; cost estimate $0.1M | p. 66 |
| NextEra line terminated into Goose Creek (Dominion, b3800.120, October 2026) | Terminate the new NextEra 500 kV line from Woodside into Goose Creek substation; the Goose Creek 500 kV cap bank moves to Aspen; $30.49M | p. 7 |
| Woodside - Goose Creek 500 kV line (Dominion, b3800.375) | New Woodside - Goose Creek 500 kV line for ~3 miles on single circuit monopole structures within the Doubs - Goose Creek corridor | p. 7 |
Details as printed
| FE scope | FE scope of proposal 2022-W3-853, on a West cluster slide | p. 64 |
|---|---|---|
| Incumbent work | Each FE item is marked as incumbent work | p. 64 |
| Dominion scope | Dominion scope of proposal 2022-W3-853, on a West cluster slide | p. 65 |
| Dominion scope, December 2023 | Estimated cost $35.59M for b3800.118 and b3800.120; required and projected in service 6/1/2027 | p. 65 |
| AEP scope | AEP scope of proposal 2022-W3-853, on a West cluster slide | p. 66 |
| AEP scope, December 2023 | Estimated cost $0.1M for b3800.121; required and projected in service 6/1/2027 | p. 66 |
| Related: NextEra scope of the same proposal (profiled as MARL) | NextEra scope of proposal 2022-W3-853 (bypass Black Oak, terminate at Aspen instead of Gant) | p. 63 |
| Related: NextEra scope cost (December 2023) | Estimated cost $512.61M for the NextEra scope (b3800.102 and others) | p. 63 |
| West cluster proposal cost (all scopes, December 2023) | $940.85M proposal cost for the West cluster: new 500 kV line, new 500 kV station, new voltage support devices | p. 6 |
| 2022 Window 3 purpose | PJM: unprecedented data center load growth (~7,500 MW) forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) | p. 2 |
| 2022 Window 3 purpose | 11,100 MW deactivation announced | p. 2 |
| First presented | Selected proposals were previously presented at the Oct 31st TEAC | p. 14 |
| Dominion cost change meeting | PJM, Reliability Analysis Update, TEAC October 6, 2026 | p. 1 |
| Dominion scope items, October 2026 | Dominion scope of proposal 2022-W3-853 as updated: b3800.118 Doubs - Bismark termination into Woodside ($5.1M), b3800.120 termination of the NextEra line into Goose Creek ($30.49M), and a new ~3 mile Woodside - Goose Creek 500 kV line | p. 7 |
| Dominion portion total, October 2026 | Transmission estimated cost $73.94M, updated from $51.19M | p. 7 |
| Dominion portion in service, October 2026 | Required 6/1/2027 (b3800.118/b3800.120) and 6/1/2029 (b3800.375); projected 9/30/2030 (b3800.120 and b3800.375) and 6/1/2028 (b3800.118) | p. 7 |
| Dominion portion, previously presented | 12/5/2023 (b3800.118/b3800.120) and 7/10/2024 (b3800.375) | p. 7 |
| Reasons for the Dominion cost change | Upgraded conductor design, catwalk installation, updated geotechnical conditions, additional splice boxes, increased crossing requirements, taller structures for EMF and clearance compliance, and forestry and access work not in the previous project | p. 7 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Preferred Projects to Address Clusters - West | $392.55M | 6/1/2027 – 6/1/2030 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Preferred Projects to Address Clusters - West | $35.59M | 6/1/2027 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Preferred Projects to Address Clusters – West | $0.1M | 6/1/2027 | |
| October 6, 2026 | Item 16 - Reliability Analysis Update - Presentation PDF | Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion) | $73.94M | 9/30/2030 (b3800.120 & b3800.375), 6/1/2028 (b3800.118) |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Aspen (DOM): described as new
- 502 Junction (PJM system-wide)
- Aspen (PJM system-wide)
- Bismark (PJM system-wide)
- Doubs (PJM system-wide)
- Goose Creek (DOM): expansion described
- Gore (PJM system-wide)
- Kammer (PJM system-wide)
- Millville (PJM system-wide)
- Stonewall (PJM system-wide)
- Woodside (DOM)
- Woodside (PJM system-wide)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- FirstEnergy transmission line project raises questions, concerns, The Winchester Star, August 19, 2025. The Winchester Star reported that FirstEnergy presented its Gore-Doubs-Goose Creek Improvement Project at a Winchester open house as about 44 miles of existing 138-kV line rebuilt as a double circuit carrying 138-kV and 500-kV lines, 17.9 miles of it in Frederick County, with new 138-kV lines between the Stonewall substation and the proposed Woodside substation in Clear Brook, 185-foot monopoles, and construction projected to start at the end of 2027.
- Potomac Edison to seek PSC permit for Jefferson County transmission line project, The Dominion Post, August 25, 2025. The Dominion Post reported that Potomac Edison notified the West Virginia Public Service Commission that it plans to apply for a certificate for the Jefferson County section of the Gore-Doubs-Goose Creek Improvement Project, which it said will exceed $20 million, and that the company amended a filing that had described the project as part of MARL.
- A look at MARL and PJM's B3800 project series, The Dominion Post (via Yahoo News), September 13, 2025. The Dominion Post reported that Potomac Edison's Gore-Doubs-Goose Creek project and NextEra's MARL are separate projects within PJM's B3800 series, that the West Virginia PSC had received 718 letters of protest for the West Virginia segment of Potomac Edison's project, and that FirstEnergy said the companies are coordinating on connections between the projects.
Not printed
- No state or county is printed on the cited PJM pages. The press places FirstEnergy's line work in Frederick and Clarke counties, Virginia, Jefferson County, West Virginia, and Loudoun County, Virginia.
- No later cost, in-service date or status for the FE scope (b3800.101 and the other FE baselines) or the AEP scope (b3800.121) appears in the PJM materials archived here; the headline cost and date are the December 2023 FE values. Only the Dominion portion has a later update (October 2026).
- PJM prints no total for the three incumbent scopes together; the $940.85M West cluster figure includes NextEra's $512.61M scope (MARL).
- The FE slide prints the baseline range as "b3800.103 – b3200.105", apparently a typo for b3800.105; it is reproduced as printed.
- "FE" is printed as the scope owner; the PJM transmission zone for the FE work is not printed. FirstEnergy's public name for this work, "Gore-Doubs-Goose Creek Improvements Project", is not printed in these PJM documents and is used here only inside attributed news summaries.
- Not a member: b3800.100 (Cloverdale 500 kV breaker position, $11.59M) is printed as "2022W3 – Preferred Solutions: AEP Local" (proposal 2022-W3-410), PJM's separate Local cluster, not the West cluster.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.