2022 Window 3 Northern Virginia/Doubs Cluster

2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster. Presented by PJM in PJM planning materials (Dominion, APS, PEPCO zone).

$1,418.3Mcost estimate as printed p. 6
6/1/2028projected in service p. 43
Recommended (baseline)status as printed p. 8

Profile

The Northern Virginia/Doubs Cluster is one part of the solution PJM recommended for its 2022 RTEP Window 3: a portfolio of Dominion, Exelon and FirstEnergy baseline projects rather than a single line, presented at the December 5, 2023 TEAC with a cluster proposal cost of $1,418.3 million. (p. 41, p. 8, p. 1, p. 6, p. 45, p. 47, p. 48) Its largest piece, Dominion proposal 2022-W3-692 for baselines B3800.200 through B3800.227 at $1025.06 million, builds new Aspen and Golden 500/230kV substations, new double-circuit 500/230 kV lines from Aspen to Golden and from Golden to Mars, and a new 500kV line from Aspen to Goose Creek, and adds a second 1440 MVA transformer at Mars. (p. 41, p. 43) The Mars–Golden lines inside that piece (baselines B3800.210 through B3800.212) have since been revised on their own slides: an original estimate of $342.92 million rose to $439.92 million at the April 1, 2025 TEAC and fell to $431.62 million at the December 8, 2025 TEAC. (p. 5, p. 1, p. 7, p. 1, p. 134) The other pieces reconductor short 230kV sections between Golden, Sterling Park and Davis Drive ($13.50 million); under Dominion proposal 2022-W3-516 ($78.4 million), rebuild 500kV Line #514 Doubs – Goose Creek and build a new 500kV line from Doubs to Aspen; under Exelon proposal 2022-W3-344/660 ($66.38 million), rebuild 7.26 miles of 230 kV circuit from Dickerson Station H to carry the new 500 kV circuit; and under FirstEnergy proposal 2022-W3-837 ($234.96 million), cover the Doubs end of the same rebuild and new line, Doubs substation work and 230 kV lines underbuilt on the new line. (p. 44, p. 45, p. 46, p. 47, p. 48, p. 49) PJM framed the whole window around about 7,500 MW of data center load growth forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) and 11,100 MW of announced deactivations; the cluster slides do not tie a load or customer to any component. (p. 2) At the October 6, 2026 TEAC, PJM printed Pepco cost updates for two Exelon baselines: the new 500kV Doubs to Aspen work (b3800.243) from $37.20 million to $26.53 million, and the Dickerson H 23111 rebuild and relocation (b3800.244) from $18.60 million to $65.06 million; b3800.245 was unchanged, and the Exelon slide lists competition for labor and materials from data center construction among its cost drivers. (p. 1, p. 19, p. 20) The December 2023 slides print a required date of June 1, 2027 for every piece and projected dates from December 1, 2027 (proposal 2022-W3-516) to June 1, 2030 (the FirstEnergy piece); PJM has not printed an updated total for the cluster. (p. 1, p. 46, p. 45, p. 49)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Aspen – Golden lines (2022-W3-692)Proposal 2022-W3-692: new double-circuit 500/230 kV lines from Aspen to Golden; the 230kV line connects Aspen – Sycolin Creek – Goldenp. 41
Golden – Mars lines (2022-W3-692)New double-circuit 500/230 kV lines from Golden to Mars; the 230kV line connects Golden – Lockridge – Marsp. 41
Aspen – Goose Creek line, Mars transformer, new Aspen and Golden substations (2022-W3-692)New 500kV line from Aspen to Goose Creek; 2nd 500-230 kV 1440 MVA transformer at Mars; new Aspen 500/230kV substation tapping 500kV Line #558; new Golden 500/230kV substationp. 41
Golden – Paragon Park 230 kV upgrades (2022-W3-692)Upgrade double-circuit 230 kV lines #2150 and #2081 from Golden to Paragon Parkp. 41
Breaker replacements (2022-W3-692)Replace overdutied breakers at Belmont, BECO, Beaumeade, Pleasant View, Shellhorn and Discoveryp. 41
Sterling Park reconductoring (Dominion)Additional upgrades (Dominion): reconductor 1.47 miles of 230kV circuits 2081 and 2150 from Sterling Park to Golden and 0.67 miles of circuits 2194 and 9231 from Davis Drive to Sterling Parkp. 44
Line #514 Doubs – Goose Creek rebuild (2022-W3-516)Proposal 2022-W3-516 (Dominion): rebuild 500kV Line #514 Doubs – Goose Creek on double circuit 500kV/230kV towersp. 45
Doubs – Aspen 500kV line (2022-W3-516)New 500kV line between Doubs and the new Aspen substation (Dominion scope from Aspen to the Doubs interconnection point)p. 45
Exelon portion (2022-W3-344/660)Proposal 2022-W3-344/660 (Exelon): Exelon portion of the new 500 kV Doubs to Goose Creek on existing Exelon right-of-wayp. 47
Dickerson H – Ed's Ferry rebuild (Exelon)Rebuild 7.26 miles of 230 kV circuit from Dickerson Station H to the Ed's Ferry area to carry the new 500 kV circuitp. 47
Dickerson H substation (Exelon)Reconfigure Dickerson H 230 kV substation and upgrade terminal equipmentp. 47
FirstEnergy portion (2022-W3-837)Proposal 2022-W3-837 (FirstEnergy): existing Doubs to Goose Creek 500 kV rebuild and new Doubs to Aspen 500 kV linep. 48
Line #514 rebuild, FirstEnergy scopeRebuild the Doubs – Goose Creek 500 kV line with the Doubs - Dickerson 230 kV relocated and underbuilt (FE cost estimate $103.27M)p. 48
Doubs – Aspen line, FirstEnergy scopeNew Doubs to Aspen line; Aspen is not yet constructed and is a component of Dominion proposal 2022-W3-692 (FE cost estimate $68.8M)p. 48
Doubs substation (FirstEnergy)Doubs substation work: re-terminate the rebuilt Doubs – Goose Creek 500 kV line, terminate the new Doubs – Aspen 500 kV line, replace three 500 kV breakersp. 48
230 kV underbuild rebuilds (FirstEnergy)Rebuild the Doubs - Dickerson, Doubs - Aqueduct and Dickerson - Aqueduct 230 kV lines, underbuilt on the new Doubs - Aspen 500 kV line (FE cost estimate $31.19M)p. 48

Details as printed

2022 Window 3 purposePJM: unprecedented data center load growth (~7,500 MW) forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs)p. 2
2022 Window 3 purpose11,100 MW deactivation announcedp. 2
2022-W3-692 (Dominion), B3800.200 – B3800.227$1025.06M; required 6/1/2027, projected 6/1/2028p. 43
Additional upgrades (Dominion), B3800.228 – B3800.229$13.50M; required 6/1/2027, projected 6/1/2028p. 44
2022-W3-516 (Dominion), B3800.230 – B3800.242$78.4M; required 6/1/2027, projected 12/1/2027p. 46
2022-W3-344/660 (Exelon), B3800.243 – B3800.245$66.38M proposed; required 6/1/2027, projected 2028-2030p. 47
2022-W3-837 (FirstEnergy), b3800.122 – b3800.127$234.96M; required 6/1/2027, projected 6/1/2030p. 49
Projects replaced by 2022-W3-516Earlier approved EOL baseline B3247 (DOM) and supplemental S2386 (FE) will be cancelledp. 45
MeetingTEAC April 1, 2025, Reliability Analysis Updatep. 1
Cancellation of B4000.130 (April 2025)An earlier Ox breaker baseline cancelled: b3800.236 and b3800.335 from 2022 Window 3 replace the same 3 breakersp. 11
Mars – Golden lines, original solutionB3800.210 – B3800.212 (the Mars – Golden lines), part of 2022-W3-692: original estimate $342.92Mp. 5
Mars – Golden lines, revised (April 2025)Additional $97M; total proposed $439.92Mp. 7
MeetingTEAC December 8, 2025p. 1
Mars – Golden lines, revised (December 2025)Change of -$8.3M; total proposed $431.62Mp. 134
Referenced by Dominion supplemental DOM-2023-0031 (April 2026)A Dominion supplemental (Auto World Delivery) cuts Lines #2081 and #2150 (Paragon Park – Golden – Sterling Park) into a proposed Auto World 230kV substationp. 10
Auto World map labelMap label b3800.200 on the Auto World slidep. 10
MeetingTEAC October 6, 2026, Reliability Analysis Updatep. 1
Cost change, b3800.243 (October 2026)b3800.243 New 500kV Doubs to Aspen (PEPCO): $37.20M original, $26.53M updated, change -$10.67M; cost containment applicablep. 19
Cost change, b3800.244 (October 2026)b3800.244 Dickerson H 23111 rebuild and relocation (PEPCO): $18.60M original, $65.06M updated, change $46.46M; cost containment applicablep. 19
b3800.245 (October 2026)PEPCO b3800.245 has no change compared to the original cost estimatep. 19
Drivers for cost increases - Exelon (October 2026)Exelon cost drivers include competition for labor, materials, manufacturing capacity and specialized resources from rapidly expanding data center construction projectsp. 20

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster $234.96M6/1/2030
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster $1025.06 M6/1/2028
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster $13.50 M6/1/2028
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster $78.4 M12/1/2027
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster $66.38 M2028-2030

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.