2022 Window 3 Northern Virginia/Doubs Cluster
2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster. Presented by PJM in PJM planning materials (Dominion, APS, PEPCO zone).
Profile
The Northern Virginia/Doubs Cluster is one part of the solution PJM recommended for its 2022 RTEP Window 3: a portfolio of Dominion, Exelon and FirstEnergy baseline projects rather than a single line, presented at the December 5, 2023 TEAC with a cluster proposal cost of $1,418.3 million. (p. 41, p. 8, p. 1, p. 6, p. 45, p. 47, p. 48) Its largest piece, Dominion proposal 2022-W3-692 for baselines B3800.200 through B3800.227 at $1025.06 million, builds new Aspen and Golden 500/230kV substations, new double-circuit 500/230 kV lines from Aspen to Golden and from Golden to Mars, and a new 500kV line from Aspen to Goose Creek, and adds a second 1440 MVA transformer at Mars. (p. 41, p. 43) The Mars–Golden lines inside that piece (baselines B3800.210 through B3800.212) have since been revised on their own slides: an original estimate of $342.92 million rose to $439.92 million at the April 1, 2025 TEAC and fell to $431.62 million at the December 8, 2025 TEAC. (p. 5, p. 1, p. 7, p. 1, p. 134) The other pieces reconductor short 230kV sections between Golden, Sterling Park and Davis Drive ($13.50 million); under Dominion proposal 2022-W3-516 ($78.4 million), rebuild 500kV Line #514 Doubs – Goose Creek and build a new 500kV line from Doubs to Aspen; under Exelon proposal 2022-W3-344/660 ($66.38 million), rebuild 7.26 miles of 230 kV circuit from Dickerson Station H to carry the new 500 kV circuit; and under FirstEnergy proposal 2022-W3-837 ($234.96 million), cover the Doubs end of the same rebuild and new line, Doubs substation work and 230 kV lines underbuilt on the new line. (p. 44, p. 45, p. 46, p. 47, p. 48, p. 49) PJM framed the whole window around about 7,500 MW of data center load growth forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) and 11,100 MW of announced deactivations; the cluster slides do not tie a load or customer to any component. (p. 2) At the October 6, 2026 TEAC, PJM printed Pepco cost updates for two Exelon baselines: the new 500kV Doubs to Aspen work (b3800.243) from $37.20 million to $26.53 million, and the Dickerson H 23111 rebuild and relocation (b3800.244) from $18.60 million to $65.06 million; b3800.245 was unchanged, and the Exelon slide lists competition for labor and materials from data center construction among its cost drivers. (p. 1, p. 19, p. 20) The December 2023 slides print a required date of June 1, 2027 for every piece and projected dates from December 1, 2027 (proposal 2022-W3-516) to June 1, 2030 (the FirstEnergy piece); PJM has not printed an updated total for the cluster. (p. 1, p. 46, p. 45, p. 49)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Aspen – Golden lines (2022-W3-692) | Proposal 2022-W3-692: new double-circuit 500/230 kV lines from Aspen to Golden; the 230kV line connects Aspen – Sycolin Creek – Golden | p. 41 |
| Golden – Mars lines (2022-W3-692) | New double-circuit 500/230 kV lines from Golden to Mars; the 230kV line connects Golden – Lockridge – Mars | p. 41 |
| Aspen – Goose Creek line, Mars transformer, new Aspen and Golden substations (2022-W3-692) | New 500kV line from Aspen to Goose Creek; 2nd 500-230 kV 1440 MVA transformer at Mars; new Aspen 500/230kV substation tapping 500kV Line #558; new Golden 500/230kV substation | p. 41 |
| Golden – Paragon Park 230 kV upgrades (2022-W3-692) | Upgrade double-circuit 230 kV lines #2150 and #2081 from Golden to Paragon Park | p. 41 |
| Breaker replacements (2022-W3-692) | Replace overdutied breakers at Belmont, BECO, Beaumeade, Pleasant View, Shellhorn and Discovery | p. 41 |
| Sterling Park reconductoring (Dominion) | Additional upgrades (Dominion): reconductor 1.47 miles of 230kV circuits 2081 and 2150 from Sterling Park to Golden and 0.67 miles of circuits 2194 and 9231 from Davis Drive to Sterling Park | p. 44 |
| Line #514 Doubs – Goose Creek rebuild (2022-W3-516) | Proposal 2022-W3-516 (Dominion): rebuild 500kV Line #514 Doubs – Goose Creek on double circuit 500kV/230kV towers | p. 45 |
| Doubs – Aspen 500kV line (2022-W3-516) | New 500kV line between Doubs and the new Aspen substation (Dominion scope from Aspen to the Doubs interconnection point) | p. 45 |
| Exelon portion (2022-W3-344/660) | Proposal 2022-W3-344/660 (Exelon): Exelon portion of the new 500 kV Doubs to Goose Creek on existing Exelon right-of-way | p. 47 |
| Dickerson H – Ed's Ferry rebuild (Exelon) | Rebuild 7.26 miles of 230 kV circuit from Dickerson Station H to the Ed's Ferry area to carry the new 500 kV circuit | p. 47 |
| Dickerson H substation (Exelon) | Reconfigure Dickerson H 230 kV substation and upgrade terminal equipment | p. 47 |
| FirstEnergy portion (2022-W3-837) | Proposal 2022-W3-837 (FirstEnergy): existing Doubs to Goose Creek 500 kV rebuild and new Doubs to Aspen 500 kV line | p. 48 |
| Line #514 rebuild, FirstEnergy scope | Rebuild the Doubs – Goose Creek 500 kV line with the Doubs - Dickerson 230 kV relocated and underbuilt (FE cost estimate $103.27M) | p. 48 |
| Doubs – Aspen line, FirstEnergy scope | New Doubs to Aspen line; Aspen is not yet constructed and is a component of Dominion proposal 2022-W3-692 (FE cost estimate $68.8M) | p. 48 |
| Doubs substation (FirstEnergy) | Doubs substation work: re-terminate the rebuilt Doubs – Goose Creek 500 kV line, terminate the new Doubs – Aspen 500 kV line, replace three 500 kV breakers | p. 48 |
| 230 kV underbuild rebuilds (FirstEnergy) | Rebuild the Doubs - Dickerson, Doubs - Aqueduct and Dickerson - Aqueduct 230 kV lines, underbuilt on the new Doubs - Aspen 500 kV line (FE cost estimate $31.19M) | p. 48 |
Details as printed
| 2022 Window 3 purpose | PJM: unprecedented data center load growth (~7,500 MW) forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) | p. 2 |
|---|---|---|
| 2022 Window 3 purpose | 11,100 MW deactivation announced | p. 2 |
| 2022-W3-692 (Dominion), B3800.200 – B3800.227 | $1025.06M; required 6/1/2027, projected 6/1/2028 | p. 43 |
| Additional upgrades (Dominion), B3800.228 – B3800.229 | $13.50M; required 6/1/2027, projected 6/1/2028 | p. 44 |
| 2022-W3-516 (Dominion), B3800.230 – B3800.242 | $78.4M; required 6/1/2027, projected 12/1/2027 | p. 46 |
| 2022-W3-344/660 (Exelon), B3800.243 – B3800.245 | $66.38M proposed; required 6/1/2027, projected 2028-2030 | p. 47 |
| 2022-W3-837 (FirstEnergy), b3800.122 – b3800.127 | $234.96M; required 6/1/2027, projected 6/1/2030 | p. 49 |
| Projects replaced by 2022-W3-516 | Earlier approved EOL baseline B3247 (DOM) and supplemental S2386 (FE) will be cancelled | p. 45 |
| Meeting | TEAC April 1, 2025, Reliability Analysis Update | p. 1 |
| Cancellation of B4000.130 (April 2025) | An earlier Ox breaker baseline cancelled: b3800.236 and b3800.335 from 2022 Window 3 replace the same 3 breakers | p. 11 |
| Mars – Golden lines, original solution | B3800.210 – B3800.212 (the Mars – Golden lines), part of 2022-W3-692: original estimate $342.92M | p. 5 |
| Mars – Golden lines, revised (April 2025) | Additional $97M; total proposed $439.92M | p. 7 |
| Meeting | TEAC December 8, 2025 | p. 1 |
| Mars – Golden lines, revised (December 2025) | Change of -$8.3M; total proposed $431.62M | p. 134 |
| Referenced by Dominion supplemental DOM-2023-0031 (April 2026) | A Dominion supplemental (Auto World Delivery) cuts Lines #2081 and #2150 (Paragon Park – Golden – Sterling Park) into a proposed Auto World 230kV substation | p. 10 |
| Auto World map label | Map label b3800.200 on the Auto World slide | p. 10 |
| Meeting | TEAC October 6, 2026, Reliability Analysis Update | p. 1 |
| Cost change, b3800.243 (October 2026) | b3800.243 New 500kV Doubs to Aspen (PEPCO): $37.20M original, $26.53M updated, change -$10.67M; cost containment applicable | p. 19 |
| Cost change, b3800.244 (October 2026) | b3800.244 Dickerson H 23111 rebuild and relocation (PEPCO): $18.60M original, $65.06M updated, change $46.46M; cost containment applicable | p. 19 |
| b3800.245 (October 2026) | PEPCO b3800.245 has no change compared to the original cost estimate | p. 19 |
| Drivers for cost increases - Exelon (October 2026) | Exelon cost drivers include competition for labor, materials, manufacturing capacity and specialized resources from rapidly expanding data center construction projects | p. 20 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | $234.96M | 6/1/2030 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | $1025.06 M | 6/1/2028 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | $13.50 M | 6/1/2028 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | $78.4 M | 12/1/2027 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: Northern Virginia/Doubs Cluster | $66.38 M | 2028-2030 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Aspen (DOM): described as new
- Golden (DOM): described as new
- Sycolin Creek (DOM): described as new
- Aqueduct (APS)
- Aspen (APS)
- Beaumeade (DOM)
- Beco (DOM)
- Belmont (DOM)
- Breezy Knoll (DOM)
- Davis Drive (DOM)
- Dickerson (APS)
- Dickerson (DOM)
- Dickerson H (PJM system-wide)
- Dickerson Station H (PJM system-wide)
- Discovery (DOM)
- Doubs (APS)
- Doubs (DOM)
- Doubs (PJM system-wide)
- Dry Mill (DOM)
- Ed's Ferry (PJM system-wide)
- Edwards Ferry (DOM)
- Goose Creek (APS)
- Goose Creek (DOM): expansion described
- Goose Creek (PJM system-wide)
- Hamilton Substation (DOM)
- Lockridge (DOM)
- Loudoun (DOM)
- Mars (DOM)
- Paragon Park (DOM)
- Pleasant View (DOM)
- Shellhorn (DOM)
- Sterling Park (DOM)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Overhead Power Lines Project On Route 7 In Loudoun County Approved By SCC, Patch, February 10, 2025. Patch reported that the State Corporation Commission approved Dominion's Aspen-Golden project, 9.4 miles of overhead lines from the future Aspen station in Leesburg to the future Golden station in Ashburn largely along Route 7, rejecting the partial undergrounding sought by Loudoun County and the Lansdowne Conservancy; Patch put the commission's estimate for the overhead project at $700.1 million.
Not printed
- No state or county is printed on the cluster slides. The Northern Virginia/Doubs name and "south of the Potomac River" are the only location text; the press places Aspen in Leesburg and Golden in Ashburn, Loudoun County, Virginia.
- PJM has printed no updated cost or in-service date for the cluster as a whole since the December 2023 total of $1,418.3M; later changes are per baseline (Mars – Golden lines, Pepco b3800.243/.244).
- No project status (engineering, construction) is printed for any member.
- No updated cost or date is printed in the archive for the Aspen – Golden lines, the Doubs – Goose Creek rebuild (Dominion or FirstEnergy scope) or b3800.122 – b3800.127.
- The December 2023 deck prints one cost per proposal; a separate PJM informational document listing B3800 components is not in the archive, so per-baseline costs inside the $1025.06M are not shown.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.