Razzler Customer Delivery. Presented by AEP in PJM planning materials (AEP zone, OH).

$416.94 Mcost estimate as printed p. 22
11/07/2028projected in service p. 22
Scopingstatus as printed p. 22

Profile

AEP presented this program to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $416.94 million and a projected in-service date in November 2028. (p. 1, p. 17, p. 22) It combines two customer service requests: a 1000 MW peak demand at 345 kV near AEP's Hanging Rock station in Scioto County, Ohio, with a requested in-service date in May 2029, and a 20 MW request at 69 kV in Franklin Furnace, Ohio, requested by March 31, 2028. (p. 15, p. 16) AEP first presented the Hanging Rock need in August 2025 and the Franklin Furnace need in October 2026; the deck names neither customer. (p. 3, p. 7) The largest item is a new 765kV/345kV Razzler station, estimated at $376.003 million, cut into the Hanging Rock-Jefferson 765 kV line, with two ~1.25 mile 345kV double circuit extensions to the customer site, which the deck calls Dazzler. (p. 17, p. 18) The plan also includes a new Disterdick 69kV station to serve approximately 18 MW of campus load and changes to several 69kV lines that AEP describes as allowing temporary service to the customer. (p. 19, p. 18, p. 20) AEP says that, considering the size of the load, the location and the system topology, no other viable alternatives were identified, and it lists the project status as Scoping. (p. 21, p. 22)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Razzler 765/345kV stationNew 765kV/345kV station: five 765 kV breakers in a ring bus, two 2250MVA transformers, a 300 MVAR reactor, a +/- 300MVAR STATCOM, ten 345kV breakers; estimated $376.003 Mp. 17
Hanging Rock - Jefferson 765kV line workCut into the Hanging Rock-Jefferson 765 kV line and bring both terminals into Razzler; estimated $9.821 Mp. 17
Razzler 345kV double circuit extension 1~1.25 mile 345kV double circuit to the customer site (Dazzler); estimated $11.969 Mp. 18
Razzler 345kV double circuit extension 2~1.25 mile 345kV double circuit to the customer site (Dazzler); estimated $12.628 Mp. 18
Ironton - Portsmouth 69kV lineModifications to allow temporary load connection to the customer; no cost printedp. 18
Haverhill - East Haverhill 69kV lineModifications to allow temporary load connection; Bonzo Switch replaces Haverhill Switch; no cost printedp. 18
Hanging Rock stationIntra company metering removal; estimated $0.085 Mp. 19
Disterdick 69kV stationNew double box bay 69kV station to serve approximately 18 MW of campus load; estimated $2.725 Mp. 19
Disterdick 69kV line extensionsTap the Ironton - Portsmouth 69kV line and extend to the new station; estimated $0.475 Mp. 19
Bonzo SwitchReplace Haverhill Switch to facilitate customer temporary service; no cost printedp. 19
Hanging Rock - North Haverhill 69kV lineModifications for the customer's temporary service, rebuild structures 16-28; no cost printedp. 20
Althea - Franklin Furnace SW 69kV lineRebuild ~0.5 miles; estimated $3.234 Mp. 20

Details as printed

Need meeting, Hanging RockNeed first presented at the TEAC need meeting of 08/05/2025p. 3
Need meeting, Franklin FurnaceNeed first presented at the SRRTEP-W need meeting of 10/16/2026p. 7
Customer request, Hanging Rock1000 MW peak demand at 345 kV, near Hanging Rock station in Scioto County, OH; requested in service 05/01/2029p. 15
Customer request, Franklin Furnace20 MW at 69 kV in Franklin Furnace, OH; requested in service by 3/31/2028p. 16
Alternatives consideredNo other viable alternatives to serve this load were identifiedp. 21
Planning model2030 RTEPp. 22

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
August 5, 2025Item 07 - AEP Supplemental Projects PDFHanging Rock, OH not printed05/01/2029Need Meeting 08/05/2025
October 16, 2026Item 03 - AEP Supplemental Projects Presentation PDFFranklin Furnace Customer Delivery Point not printed3/31/2028Need Meeting 10/16/2026
December 1, 2026Item 03 - AEP Supplemental Projects - PresentationRazzler Customer Delivery $416.94 M11/07/2028Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.