Razzler Customer Delivery
Razzler Customer Delivery. Presented by AEP in PJM planning materials (AEP zone, OH).
Profile
AEP presented this program to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $416.94 million and a projected in-service date in November 2028. (p. 1, p. 17, p. 22) It combines two customer service requests: a 1000 MW peak demand at 345 kV near AEP's Hanging Rock station in Scioto County, Ohio, with a requested in-service date in May 2029, and a 20 MW request at 69 kV in Franklin Furnace, Ohio, requested by March 31, 2028. (p. 15, p. 16) AEP first presented the Hanging Rock need in August 2025 and the Franklin Furnace need in October 2026; the deck names neither customer. (p. 3, p. 7) The largest item is a new 765kV/345kV Razzler station, estimated at $376.003 million, cut into the Hanging Rock-Jefferson 765 kV line, with two ~1.25 mile 345kV double circuit extensions to the customer site, which the deck calls Dazzler. (p. 17, p. 18) The plan also includes a new Disterdick 69kV station to serve approximately 18 MW of campus load and changes to several 69kV lines that AEP describes as allowing temporary service to the customer. (p. 19, p. 18, p. 20) AEP says that, considering the size of the load, the location and the system topology, no other viable alternatives were identified, and it lists the project status as Scoping. (p. 21, p. 22)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Razzler 765/345kV station | New 765kV/345kV station: five 765 kV breakers in a ring bus, two 2250MVA transformers, a 300 MVAR reactor, a +/- 300MVAR STATCOM, ten 345kV breakers; estimated $376.003 M | p. 17 |
| Hanging Rock - Jefferson 765kV line work | Cut into the Hanging Rock-Jefferson 765 kV line and bring both terminals into Razzler; estimated $9.821 M | p. 17 |
| Razzler 345kV double circuit extension 1 | ~1.25 mile 345kV double circuit to the customer site (Dazzler); estimated $11.969 M | p. 18 |
| Razzler 345kV double circuit extension 2 | ~1.25 mile 345kV double circuit to the customer site (Dazzler); estimated $12.628 M | p. 18 |
| Ironton - Portsmouth 69kV line | Modifications to allow temporary load connection to the customer; no cost printed | p. 18 |
| Haverhill - East Haverhill 69kV line | Modifications to allow temporary load connection; Bonzo Switch replaces Haverhill Switch; no cost printed | p. 18 |
| Hanging Rock station | Intra company metering removal; estimated $0.085 M | p. 19 |
| Disterdick 69kV station | New double box bay 69kV station to serve approximately 18 MW of campus load; estimated $2.725 M | p. 19 |
| Disterdick 69kV line extensions | Tap the Ironton - Portsmouth 69kV line and extend to the new station; estimated $0.475 M | p. 19 |
| Bonzo Switch | Replace Haverhill Switch to facilitate customer temporary service; no cost printed | p. 19 |
| Hanging Rock - North Haverhill 69kV line | Modifications for the customer's temporary service, rebuild structures 16-28; no cost printed | p. 20 |
| Althea - Franklin Furnace SW 69kV line | Rebuild ~0.5 miles; estimated $3.234 M | p. 20 |
Details as printed
| Need meeting, Hanging Rock | Need first presented at the TEAC need meeting of 08/05/2025 | p. 3 |
|---|---|---|
| Need meeting, Franklin Furnace | Need first presented at the SRRTEP-W need meeting of 10/16/2026 | p. 7 |
| Customer request, Hanging Rock | 1000 MW peak demand at 345 kV, near Hanging Rock station in Scioto County, OH; requested in service 05/01/2029 | p. 15 |
| Customer request, Franklin Furnace | 20 MW at 69 kV in Franklin Furnace, OH; requested in service by 3/31/2028 | p. 16 |
| Alternatives considered | No other viable alternatives to serve this load were identified | p. 21 |
| Planning model | 2030 RTEP | p. 22 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| August 5, 2025 | Item 07 - AEP Supplemental Projects PDF | Hanging Rock, OH | not printed | 05/01/2029 | Need Meeting 08/05/2025 |
| October 16, 2026 | Item 03 - AEP Supplemental Projects Presentation PDF | Franklin Furnace Customer Delivery Point | not printed | 3/31/2028 | Need Meeting 10/16/2026 |
| December 1, 2026 | Item 03 - AEP Supplemental Projects - Presentation | Razzler Customer Delivery | $416.94 M | 11/07/2028 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Disterdick 69kV Station (AEP): described as new
- Razzler station (AEP): described as new
- Althea Station (AEP)
- Bonzo Switch (AEP)
- East Haverhill (AEP)
- Franklin Furnace SW (AEP)
- Hanging Rock (AEP)
- Haverhill (AEP)
- Ironton (AEP)
- Jefferson (AEP)
- North Haverhill (AEP)
- Portsmouth (AEP)
Not printed
- The deck names the customers only as Customer; it does not say what the loads are or whether the two requests are the same customer.
- No county is printed for the Razzler, Dazzler or Disterdick sites; the only county printed is Scioto County, for the Hanging Rock request.
- Four 69kV items (Ironton - Portsmouth, Haverhill - East Haverhill, Bonzo Switch, Hanging Rock - North Haverhill) print "Estimated Cost:" with no figure.
- No news article found that names the Razzler station or ties a customer to this program (searched 2026-11-27).
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.