Gordon Switchyard
Gordon, PA. Presented by PPL in PJM planning materials (PPL zone, PA).
Profile
PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in October 2025, at a transmission cost estimate of $231.65 million; its 2026 local plan submission repeats that estimate with a projected in-service date of May 30, 2028. (p. 1, p. 5, p. 6, p. 24, p. 25) The need, first presented in May 2025 under the title Gordon, PA, is a customer request to serve a facility from a 230kV source near Frackville, Pennsylvania, with a total load of approximately 600MW by 2029 and a requested in-service date of May 2027. (p. 7) PPL lists the load ramping from 290MW at initial in-service in 2027 to 300 MW in 2028 and 600 MW in 2029. (p. 7) The plan centers on a new Gordon 230kV switchyard ($45 million, four bays with an 80MVAR capacitor bank), cut into the existing Eldred - Frackville 230kV line, with three 230kV lead lines of approximately 0.1 miles to the customer facility. (p. 25) Most of the cost is in rebuilding existing 230kV lines to double circuit: Sunbury to Eldred (24.8 miles, $112.5 million), Eldred to Gordon (7.3 miles, $32.85 million) and Gordon to Frackville (4.4 miles, $19.8 million). (p. 25) PPL says there are no functional alternatives because the customer site is immediately adjacent to the Eldred - Frackville 230kV line. (p. 25) The October 2025 solution slide gave a projected in-service date of May 30, 2027; the 2026 local plan moves it to May 30, 2028 and lists the status as Conceptual. (p. 5, p. 6, p. 24, p. 25)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Gordon 230kV switchyard (s3805.1) | Four bay BAAH 230kV switchyard with an 80MVAR capacitor bank; estimated $45 M | p. 25 |
| Eldred - Frackville 230kV line bifurcation (s3805.2) | Bifurcate the Eldred - Frackville 230kV line into the new Gordon 230kV switchyard, extending lines approximately 0.4 miles; estimated $4 M | p. 25 |
| Sunbury 230kV yard (s3805.3) | Build out bay #2 in the 230kV GIS with two new breakers and re-terminate the SUNB-SUSQ #1 230kV line from bay #3 to bay #2; estimated $7 M | p. 25 |
| Eldred 230kV yard (s3805.4) | Two new terminals at Eldred Substation, building out two bays, with a total of four 230kV breakers; estimated $4.5 M | p. 25 |
| Frackville 230kV yard (s3805.5) | One new 230kV breaker, 230kV dead-end and ancillary equipment in bay #3; estimated $2 M | p. 25 |
| Sunbury - Eldred 230kV line rebuild (s3805.6) | Rebuild the existing line to double circuit 230kV from Sunbury to Eldred (24.8 miles); estimated $112.5 M | p. 25 |
| Eldred - Gordon 230kV line rebuild (s3805.7) | Rebuild the existing Eldred - Frackville line to double circuit 230kV from Eldred to Gordon (7.3 miles); estimated $32.85 M | p. 25 |
| Gordon - Frackville 230kV line rebuild (s3805.8) | Rebuild the existing Eldred - Frackville line to double circuit 230kV from Gordon to Frackville (4.4 miles); estimated $19.8 M | p. 25 |
| Gordon 230kV customer lead lines (s3805.9) | Three 230kV lead lines, approximately 0.1 miles, from the Gordon 230kV switchyard to the customer facility; estimated $4 M | p. 25 |
Details as printed
| Solution presented | Solution Meeting TEAC - 10/8/2025; previously presented at the Need Meeting 05/06/2025 | p. 5 |
|---|---|---|
| Cost at the October 2025 solution meeting | $231.65M | p. 6 |
| In-service at the October 2025 solution meeting | 5/30/2027 | p. 6 |
| Need presented | Need Meeting 05/06/2025 | p. 7 |
| Project driver | Customer Service | p. 24 |
| Customer request, near Frackville | Facility served from a 230kV source near Frackville, PA; approximately 600MW total (2029); requested in service 05/2027 | p. 7 |
| Load ramp | 290MW initial in-service 2027; 300 MW projected 2028; 600 MW projected 2029 | p. 7 |
| Alternatives considered | No functional alternatives; the customer site is immediately adjacent to the ELDR-FRAC 230kV line | p. 25 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| May 6, 2025 | Item 07 - PPL Supplemental Projects PDF | Gordon, PA | not printed | 05/2027 | Need Meeting 05/06/2025 |
| October 8, 2025 | Item 09 - PPL Supplemental Projects PDF | Gordon, PA | $231.65M | 5/30/2027 | Conceptual |
| October 6, 2026 | Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 PDF | Gordon, PA | $231.65 M | 05/30/2028 | Conceptual |
| Date not printed | PPL  PDF | Gordon, PA | $231.65 M | 05/30/2028 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Gordon (PPL): described as new
- Eldred (PPL)
- Frackville (PPL): expansion described
- Sunbury (PPL)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- PPL open house outlines pole line upgrades, new switchyard at Highridge Industrial Park, The Shenandoah Sentinel, December 17, 2025. The Shenandoah Sentinel reported that PPL plans to rebuild 37 miles of 230 kV line between Shamokin Dam and Frackville to support anticipated load growth including a large load customer, with a new switchyard in Butler Township north of the Interstate 81 interchange at Highridge Park Road on land owned by Northpoint Development, and that PPL declined to name the customer, citing confidentiality.
- PPL Plans Rebuild Of Major Regional Transmission Line, Newsradio 1070 WKOK, March 10, 2026. WKOK reported that PPL plans to rebuild about 37 miles of the Sunbury-Frackville 230-kilovolt line through Northumberland, Snyder and Schuylkill counties, that construction will begin after Pennsylvania Public Utility Commission approval, and that PPL expects the upgraded line in service by January 2029.
Not printed
- The decks name the customer only as a customer; they do not say what the facility is.
- No county is printed; near Frackville, PA is the only location given for the customer site. The Butler Township location comes from news coverage, not the decks.
- The May 2025 need meeting printed no cost or solution; the October 2025 solution and the 2026 local plan print the same $231.65 M estimate.
- The 2026 local plan prints no single supplemental ID line; the s3805.1 to s3805.9 IDs are printed beside each component.
- The news articles call the work the Sunbury-Frackville project and do not use the name Gordon or the need number; they are matched by the printed route (Sunbury - Eldred - Gordon - Frackville) and the new switchyard.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.