Gordon Switchyard

Gordon, PA. Presented by PPL in PJM planning materials (PPL zone, PA).

$231.65 Mcost estimate as printed p. 25
05/30/2028projected in service p. 25
Conceptualstatus as printed p. 25

Profile

PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in October 2025, at a transmission cost estimate of $231.65 million; its 2026 local plan submission repeats that estimate with a projected in-service date of May 30, 2028. (p. 1, p. 5, p. 6, p. 24, p. 25) The need, first presented in May 2025 under the title Gordon, PA, is a customer request to serve a facility from a 230kV source near Frackville, Pennsylvania, with a total load of approximately 600MW by 2029 and a requested in-service date of May 2027. (p. 7) PPL lists the load ramping from 290MW at initial in-service in 2027 to 300 MW in 2028 and 600 MW in 2029. (p. 7) The plan centers on a new Gordon 230kV switchyard ($45 million, four bays with an 80MVAR capacitor bank), cut into the existing Eldred - Frackville 230kV line, with three 230kV lead lines of approximately 0.1 miles to the customer facility. (p. 25) Most of the cost is in rebuilding existing 230kV lines to double circuit: Sunbury to Eldred (24.8 miles, $112.5 million), Eldred to Gordon (7.3 miles, $32.85 million) and Gordon to Frackville (4.4 miles, $19.8 million). (p. 25) PPL says there are no functional alternatives because the customer site is immediately adjacent to the Eldred - Frackville 230kV line. (p. 25) The October 2025 solution slide gave a projected in-service date of May 30, 2027; the 2026 local plan moves it to May 30, 2028 and lists the status as Conceptual. (p. 5, p. 6, p. 24, p. 25)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Gordon 230kV switchyard (s3805.1)Four bay BAAH 230kV switchyard with an 80MVAR capacitor bank; estimated $45 Mp. 25
Eldred - Frackville 230kV line bifurcation (s3805.2)Bifurcate the Eldred - Frackville 230kV line into the new Gordon 230kV switchyard, extending lines approximately 0.4 miles; estimated $4 Mp. 25
Sunbury 230kV yard (s3805.3)Build out bay #2 in the 230kV GIS with two new breakers and re-terminate the SUNB-SUSQ #1 230kV line from bay #3 to bay #2; estimated $7 Mp. 25
Eldred 230kV yard (s3805.4)Two new terminals at Eldred Substation, building out two bays, with a total of four 230kV breakers; estimated $4.5 Mp. 25
Frackville 230kV yard (s3805.5)One new 230kV breaker, 230kV dead-end and ancillary equipment in bay #3; estimated $2 Mp. 25
Sunbury - Eldred 230kV line rebuild (s3805.6)Rebuild the existing line to double circuit 230kV from Sunbury to Eldred (24.8 miles); estimated $112.5 Mp. 25
Eldred - Gordon 230kV line rebuild (s3805.7)Rebuild the existing Eldred - Frackville line to double circuit 230kV from Eldred to Gordon (7.3 miles); estimated $32.85 Mp. 25
Gordon - Frackville 230kV line rebuild (s3805.8)Rebuild the existing Eldred - Frackville line to double circuit 230kV from Gordon to Frackville (4.4 miles); estimated $19.8 Mp. 25
Gordon 230kV customer lead lines (s3805.9)Three 230kV lead lines, approximately 0.1 miles, from the Gordon 230kV switchyard to the customer facility; estimated $4 Mp. 25

Details as printed

Solution presentedSolution Meeting TEAC - 10/8/2025; previously presented at the Need Meeting 05/06/2025p. 5
Cost at the October 2025 solution meeting$231.65Mp. 6
In-service at the October 2025 solution meeting5/30/2027p. 6
Need presentedNeed Meeting 05/06/2025p. 7
Project driverCustomer Servicep. 24
Customer request, near FrackvilleFacility served from a 230kV source near Frackville, PA; approximately 600MW total (2029); requested in service 05/2027p. 7
Load ramp290MW initial in-service 2027; 300 MW projected 2028; 600 MW projected 2029p. 7
Alternatives consideredNo functional alternatives; the customer site is immediately adjacent to the ELDR-FRAC 230kV linep. 25

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
May 6, 2025Item 07 - PPL Supplemental Projects PDFGordon, PA not printed05/2027Need Meeting 05/06/2025
October 8, 2025Item 09 - PPL Supplemental Projects PDFGordon, PA $231.65M5/30/2027Conceptual
October 6, 2026Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 PDFGordon, PA $231.65 M05/30/2028Conceptual
Date not printedPPL&nbsp PDFGordon, PA $231.65 M05/30/2028Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.