MidAtlantic Resiliency Link (MARL)
NextEra MidAtlantic Resiliency Link 'MARL'. Presented by PJM in PJM planning materials (APS zone, VA (Frederick County, Woodside substation), PA, WV, MD).
Profile
PJM's January 6, 2026 update to its Transmission Expansion Advisory Committee puts NextEra's MidAtlantic Resiliency Link (MARL) at a total cost estimate of $844.80 million in 2023 dollars, up from $440.95 million. (p. 1, p. 67) MARL is NextEra's scope of proposal 2022-W3-853, which PJM listed among its preferred proposals for the West cluster on December 5, 2023: a new 500 kV line from the existing 502 Junction substation to a new Woodside substation next to the existing Stonewall 138 kV substation. (p. 1, p. 63, p. 67) At that meeting the NextEra scope carried an estimated cost of $512.61 million and a projected in-service date of June 1, 2027, and it included a Woodside - Aspen 500 kV line at $71.72 million that the 2026 summary does not list. (p. 63, p. 1) The 2026 summary follows scope changes the PJM Board approved in August 2024 and lists the line at $632.60 million, Woodside substation at $130.10 million, and Woodside reactive components and line terminations at $82.10 million. (p. 1, p. 66, p. 67) The update attributes the increase to 30% design and engineering, route refinements, substation site conditions, vendor quotes for long lead time equipment above budgetary quotes, land rights valuations and $115.4 million of added contingency. (p. 68) It states that the increases do not affect NextEra's cost containment commitment, and that the $440.95 million project cost cap and PJM's $832.52 million independent cost estimate are unchanged. (p. 68, p. 67) After Frederick County, Virginia found the Woodside substation consistent with its plans, NextEra moved the substation's in-service date from December 2031 to December 2028, and the project was on track to file applications in January 2026 with the commissions in Pennsylvania, West Virginia, Maryland and Virginia. (p. 69)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| 502 Junction - Woodside 500 kV line (NEET portion) | New 500 kV line from 502 Junction to the FE/NEET demarcation point around Gore substation, bypassing Black Oak (b3800.102); $315.65M, updated to $632.60M | p. 67 |
| Woodside substation | New substation adjacent to the existing Stonewall 138 kV substation (b3800.106 - b3800.110); $80.04M, updated to $130.10M | p. 67 |
| Woodside reactive components and Doubs - Bismark terminations | Woodside reactive components and NEET scope for terminating the Doubs - Bismark line into Woodside (b3800.113, b3800.115, b3800.117); $45.26M, updated to $82.10M | p. 67 |
| Woodside equipment (as presented December 2023) | Loop in the Bismark - Doubs 500 kV line; two 500/138 kV transformers; two 150 MVAR cap banks and one +500/-300 MVAR STATCOM | p. 63 |
Details as printed
| Cost basis | All cost estimates expressed in 2023 dollars | p. 67 |
|---|---|---|
| Developer | NextEra (NEET), under a Designated Entity Agreement with PJM | p. 66 |
| Voltage | 500 kV | p. 66 |
| Scope change | Summary follows scope changes approved by the PJM Board in August 2024 | p. 66 |
| PJM independent cost estimate | $832.52M, the basis for the security required in the DEA; unchanged | p. 67 |
| Project cost cap | $440.95M, the threshold above which NextEra earns a reduced ROE under its cost containment commitment; unchanged | p. 67 |
| Reasons for the cost increase | Estimate informed by 30% design and engineering; route refinements and substation site conditions; vendor quotes for long lead time equipment above budgetary quotes; market analyses of land rights; $115.4 million of added contingency | p. 68 |
| Cost containment | The increases do not affect NextEra's commitment to the original Project Cost Caps in the DEA | p. 68 |
| Outreach and routing | Over 1,200 survey and open-house comments and more than 300 stakeholder and landowner meetings; a proposed route and five alternative routes | p. 69 |
| Selection meeting | PJM, Reliability Analysis Update, TEAC December 5, 2023 | p. 1 |
| Preferred proposal, December 2023 | NextEra scope of proposal 2022-W3-853, listed among the preferred proposals for the West cluster | p. 63 |
| Estimate, December 2023 | Estimated cost $512.61M for the NextEra scope (b3800.102, b3800.106 - b3800.110, b3800.113, b3800.115, b3800.117 and b3800.119); required and projected in service 6/1/2027 | p. 63 |
| Woodside - Aspen line, December 2023 | The NextEra scope as first presented included a new 500kV line from Woodside to Aspen at $71.72M | p. 63 |
| Related scope: Black Oak loop-in (2024 Window 1) | b4000.14, $3.0 M NEET scope to interconnect the 502 Junction - Woodside line at Black Oak; projected in service 12/31/2031 | p. 50 |
| Related scope: designation | The future 502 Jct - Woodside line segment that loops into Black Oak is designated to NextEra | p. 50 |
| Double-circuit proposal (removed) | NextEra proposal to convert the b3800.102 line to double circuit between Fort Martin and the NEETMA/APS interconnection point in Frederick County, VA | p. 73 |
| Double-circuit proposal outcome | Proposal ID 896 removed from consideration: resolved minimal posted flowgates and provides the least benefit | p. 73 |
| Related scope: Dominion terminations (not MARL) | Dominion portion at $73.94M, up from $51.19M, including termination of the NextEra line from Woodside into Goose Creek (b3800.120); projected in service 9/30/2030 | p. 7 |
| Double-circuit proposal cost | Proposal 896 total cost $571.70M | p. 73 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Preferred Proposals to Address Clusters - West | $512.61M | 6/1/2027 | |
| January 6, 2026 | Item 09 - Reliability Analysis Update PDF | NextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary | $844.80M | December 2028 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Stonewall/Woodside (PJM system-wide): described as new
- 502 Junction (PJM system-wide)
- Aspen (PJM system-wide)
- Bismark (PJM system-wide)
- Black Oak (PJM system-wide): expansion described
- Doubs (PJM system-wide)
- Gore (PJM system-wide)
- Stonewall (PJM system-wide)
- Woodside (PJM system-wide)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- NextEra files for PSC permit for MARL project, The Dominion Post, January 30, 2026. The Dominion Post reported that NextEra Energy Transmission MidAtlantic applied to the West Virginia Public Service Commission for a certificate for the 107.5-mile MARL route from Greene County, Pa., to Frederick County, Va., about 58.9 miles of it in West Virginia, and that the application estimates the total cost at about $1.1672 billion in 2031 dollars.
- NextEra files applications for transmission line in Fayette, Greene counties, Observer-Reporter, March 9, 2026. The Observer-Reporter reported that NextEra filed applications with the Pennsylvania Public Utility Commission for the Pennsylvania portion of the line in Greene and Fayette counties, including a request to operate as a public utility, and that NextEra hopes for state approval by early 2027 and full operation by the end of 2031.
- Western Maryland residents face uncertainty over power line tied to data center demand, Technical.ly, April 1, 2026. Technical.ly reported that NextEra filed with the Maryland Public Service Commission at the end of January 2026, that the route would affect 388 properties in Garrett and Allegany counties, and that a recent NextEra update put the cost at $960 million against an original $441 million.
- Transmission Line Developer Discusses Project Ahead Of Public Hearings, West Virginia Public Broadcasting, June 10, 2026. West Virginia Public Broadcasting published a question-and-answer interview with a NextEra project executive ahead of West Virginia PSC public comment hearings, in which she described the roughly 107-mile route through Monongalia, Preston, Mineral and Hampshire counties and an estimated residential bill impact of $1 or less per month.
Not printed
- PJM does not print a transmission zone on the MARL slides. The zone shown is from the 2025 proposal slide's "NEETMA/APS interconnection point in Frederick County, VA" and the FE (APS) incumbent scope of the same proposal; Phil should confirm.
- The January 2026 update gives an in-service date only for the Woodside substation (December 2028); no in-service date for the 502 Junction - Woodside line is printed in these documents. The related Black Oak loop-in (b4000.14) is projected for 12/31/2031.
- No county is printed for 502 Junction or Gore. Frederick County, Virginia is printed only for the Woodside substation.
- PJM's materials here do not explain the difference between the $512.61M December 2023 estimate and the $440.95M figure the January 2026 summary uses as the original estimate; the 2023 scope also listed b3800.119 and a Woodside - Aspen line, which the 2026 summary does not list.
- The August 2024 Board-approved scope changes are referenced but not described in these documents.
- Not members: b3800.101 (FE incumbent scope of 2022-W3-853, $392.55M), b3800.118 (Dominion scope) and b3800.100 (AEP local) are separate tracked rows not printed as MARL; b4000.14 is a 2024 Window 1 NextEra scope at Black Oak, shown here as related work only.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.