MidAtlantic Resiliency Link (MARL)

NextEra MidAtlantic Resiliency Link 'MARL'. Presented by PJM in PJM planning materials (APS zone, VA (Frederick County, Woodside substation), PA, WV, MD).

$844.80Mcost estimate as printed p. 67
December 2028 (Woodside substation)projected in service p. 69
State applications, January 2026status as printed p. 69

Profile

PJM's January 6, 2026 update to its Transmission Expansion Advisory Committee puts NextEra's MidAtlantic Resiliency Link (MARL) at a total cost estimate of $844.80 million in 2023 dollars, up from $440.95 million. (p. 1, p. 67) MARL is NextEra's scope of proposal 2022-W3-853, which PJM listed among its preferred proposals for the West cluster on December 5, 2023: a new 500 kV line from the existing 502 Junction substation to a new Woodside substation next to the existing Stonewall 138 kV substation. (p. 1, p. 63, p. 67) At that meeting the NextEra scope carried an estimated cost of $512.61 million and a projected in-service date of June 1, 2027, and it included a Woodside - Aspen 500 kV line at $71.72 million that the 2026 summary does not list. (p. 63, p. 1) The 2026 summary follows scope changes the PJM Board approved in August 2024 and lists the line at $632.60 million, Woodside substation at $130.10 million, and Woodside reactive components and line terminations at $82.10 million. (p. 1, p. 66, p. 67) The update attributes the increase to 30% design and engineering, route refinements, substation site conditions, vendor quotes for long lead time equipment above budgetary quotes, land rights valuations and $115.4 million of added contingency. (p. 68) It states that the increases do not affect NextEra's cost containment commitment, and that the $440.95 million project cost cap and PJM's $832.52 million independent cost estimate are unchanged. (p. 68, p. 67) After Frederick County, Virginia found the Woodside substation consistent with its plans, NextEra moved the substation's in-service date from December 2031 to December 2028, and the project was on track to file applications in January 2026 with the commissions in Pennsylvania, West Virginia, Maryland and Virginia. (p. 69)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
502 Junction - Woodside 500 kV line (NEET portion)New 500 kV line from 502 Junction to the FE/NEET demarcation point around Gore substation, bypassing Black Oak (b3800.102); $315.65M, updated to $632.60Mp. 67
Woodside substationNew substation adjacent to the existing Stonewall 138 kV substation (b3800.106 - b3800.110); $80.04M, updated to $130.10Mp. 67
Woodside reactive components and Doubs - Bismark terminationsWoodside reactive components and NEET scope for terminating the Doubs - Bismark line into Woodside (b3800.113, b3800.115, b3800.117); $45.26M, updated to $82.10Mp. 67
Woodside equipment (as presented December 2023)Loop in the Bismark - Doubs 500 kV line; two 500/138 kV transformers; two 150 MVAR cap banks and one +500/-300 MVAR STATCOMp. 63

Details as printed

Cost basisAll cost estimates expressed in 2023 dollarsp. 67
DeveloperNextEra (NEET), under a Designated Entity Agreement with PJMp. 66
Voltage500 kVp. 66
Scope changeSummary follows scope changes approved by the PJM Board in August 2024p. 66
PJM independent cost estimate$832.52M, the basis for the security required in the DEA; unchangedp. 67
Project cost cap$440.95M, the threshold above which NextEra earns a reduced ROE under its cost containment commitment; unchangedp. 67
Reasons for the cost increaseEstimate informed by 30% design and engineering; route refinements and substation site conditions; vendor quotes for long lead time equipment above budgetary quotes; market analyses of land rights; $115.4 million of added contingencyp. 68
Cost containmentThe increases do not affect NextEra's commitment to the original Project Cost Caps in the DEAp. 68
Outreach and routingOver 1,200 survey and open-house comments and more than 300 stakeholder and landowner meetings; a proposed route and five alternative routesp. 69
Selection meetingPJM, Reliability Analysis Update, TEAC December 5, 2023p. 1
Preferred proposal, December 2023NextEra scope of proposal 2022-W3-853, listed among the preferred proposals for the West clusterp. 63
Estimate, December 2023Estimated cost $512.61M for the NextEra scope (b3800.102, b3800.106 - b3800.110, b3800.113, b3800.115, b3800.117 and b3800.119); required and projected in service 6/1/2027p. 63
Woodside - Aspen line, December 2023The NextEra scope as first presented included a new 500kV line from Woodside to Aspen at $71.72Mp. 63
Related scope: Black Oak loop-in (2024 Window 1)b4000.14, $3.0 M NEET scope to interconnect the 502 Junction - Woodside line at Black Oak; projected in service 12/31/2031p. 50
Related scope: designationThe future 502 Jct - Woodside line segment that loops into Black Oak is designated to NextErap. 50
Double-circuit proposal (removed)NextEra proposal to convert the b3800.102 line to double circuit between Fort Martin and the NEETMA/APS interconnection point in Frederick County, VAp. 73
Double-circuit proposal outcomeProposal ID 896 removed from consideration: resolved minimal posted flowgates and provides the least benefitp. 73
Related scope: Dominion terminations (not MARL)Dominion portion at $73.94M, up from $51.19M, including termination of the NextEra line from Woodside into Goose Creek (b3800.120); projected in service 9/30/2030p. 7
Double-circuit proposal costProposal 896 total cost $571.70Mp. 73

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 3Preferred Proposals to Address Clusters - West $512.61M6/1/2027
January 6, 2026Item 09 - Reliability Analysis Update PDFNextEra MidAtlantic Resiliency Link ‘MARL’ Project Summary $844.80MDecember 2028

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.