Mendota-Sandwich 138 kV
Mendota-Sandwich 138 kV. Presented by PJM in PJM planning materials (ComEd zone).
Profile
Mendota-Sandwich 138 kV is a ComEd zone baseline reliability project that PJM presented as a recommended solution to its PJM West subregional RTEP committee on December 12, 2025, at an estimated cost of $171.88 million. (p. 4, p. 1, p. 3) It consists of a new 28-mile 138 kV line from Mendota to Sandwich (b4025.1), conversion of the Mendota straight bus to a ring with four new 138 kV breakers (b4025.2), and a new 138 kV breaker at Sandwich substation (b4025.3). (p. 4) PJM's problem statement is a generator deliverability finding: in the 2030 light load and winter case, the Waterman-Sandwich and Steward-Haumesser 138 kV lines are overloaded for N-1 and N-2 outages. (p. 3) The slides list ancillary benefits for a network that hosts 85MW of wind generation and faces voltage regulation challenges under fluctuating wind output. (p. 4) The required and projected in-service dates are both 4/15/2030, and the cost is the same $171.88 million printed at the first read on November 14, 2025. (p. 4, p. 4, p. 1) In October 2026 ComEd presented a separate supplemental need, ComEd-2026-016, that adds two 138kV breakers to the Mendota ring bus (B4025.2) for distribution capacity, at $4.85 million. (p. 8)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Mendota - Sandwich 138 kV line (b4025.1) | New 28-mile 138 kV line | p. 4 |
| Mendota 138 kV substation (b4025.2) | Convert straight bus to a ring with four new 138 kV circuit breakers | p. 4 |
| Sandwich 138 kV substation (b4025.3) | 138 kV circuit breaker and associated equipment | p. 4 |
Details as printed
| Required in-service date | Required 4/15/2030 | p. 4 |
|---|---|---|
| First read cost, November 2025 | $171.88 M at First Read | p. 4 |
| First read meeting | November 14, 2025 | p. 1 |
| Criteria | Generator Deliverability | p. 3 |
| Model used | 2030 winter and light load base case | p. 3 |
| Proposal window exclusion | Below 200 kV exclusion | p. 3 |
| Flowgates | 2025-W1-GD-LL189, 2025-W1-GD-W61, 2025-W1-GD-W217, 2025-W1-GD-W370 | p. 3 |
| Problem statement | Waterman-Sandwich 138 kV and Steward-Haumesser 138 kV lines overloaded for N-1 and N-2 outages in the 2030 light load and winter case | p. 3 |
| Ancillary benefit (as printed) | The network hosts 85MW of wind generation | p. 4 |
| Ancillary benefit (as printed) | Voltage regulation challenges, made worse by capacitor bank controls under fluctuating wind output | p. 4 |
| Later ComEd work at the Mendota ring bus | Separate ComEd supplemental need ComEd-2026-016 (Mendota) adds two 138kV breakers to the Mendota ring bus (B4025.2); $4.85 M, projected 6/1/2030 | p. 8 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| November 14, 2025 | Item 01 - SRRTEP West - Reliability Analysis Update PDF | Mendota-Sandwich 138 kV | $171.88 M | 4/15/2030 | First Read |
| December 12, 2025 | Item 16 - SRRTEP West - Reliability Analysis Update PDF | Mendota-Sandwich 138 kV | $171.88 M | 4/15/2030 | Recommended Solution |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
Not printed
- No state or county is printed on the cited pages; Illinois is not printed.
- No project status (Conceptual, Engineering) is printed for this baseline; the status shown is the process stage.
- No later TEAC or Board approval slide for b4025 is in the archive; whether the PJM Board approved it is not shown here.
- No news article about this line was found (searched 2026-11-27); searches returned only PJM interconnection studies on the Sandwich - Plano 138 kV line.
- ComEd-2026-016 (Mendota, $4.85 M) is a separate supplemental need driven by distribution capacity for distributed energy resources; it builds on b4025.2 but is not a member.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.