Substation Scout

Mendota-Sandwich 138 kV

Mendota-Sandwich 138 kV. Presented by PJM in PJM planning materials (ComEd zone).

$171.88 Mcost estimate as printed p. 4
4/15/2030projected in service p. 4
Recommendedstatus as printed p. 3

Profile

Mendota-Sandwich 138 kV is a ComEd zone baseline reliability project that PJM presented as a recommended solution to its PJM West subregional RTEP committee on December 12, 2025, at an estimated cost of $171.88 million. (p. 4, p. 1, p. 3) It consists of a new 28-mile 138 kV line from Mendota to Sandwich (b4025.1), conversion of the Mendota straight bus to a ring with four new 138 kV breakers (b4025.2), and a new 138 kV breaker at Sandwich substation (b4025.3). (p. 4) PJM's problem statement is a generator deliverability finding: in the 2030 light load and winter case, the Waterman-Sandwich and Steward-Haumesser 138 kV lines are overloaded for N-1 and N-2 outages. (p. 3) The slides list ancillary benefits for a network that hosts 85MW of wind generation and faces voltage regulation challenges under fluctuating wind output. (p. 4) The required and projected in-service dates are both 4/15/2030, and the cost is the same $171.88 million printed at the first read on November 14, 2025. (p. 4, p. 4, p. 1) In October 2026 ComEd presented a separate supplemental need, ComEd-2026-016, that adds two 138kV breakers to the Mendota ring bus (B4025.2) for distribution capacity, at $4.85 million. (p. 8)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Mendota - Sandwich 138 kV line (b4025.1)New 28-mile 138 kV linep. 4
Mendota 138 kV substation (b4025.2)Convert straight bus to a ring with four new 138 kV circuit breakersp. 4
Sandwich 138 kV substation (b4025.3)138 kV circuit breaker and associated equipmentp. 4

Details as printed

Required in-service dateRequired 4/15/2030p. 4
First read cost, November 2025$171.88 M at First Readp. 4
First read meetingNovember 14, 2025p. 1
CriteriaGenerator Deliverabilityp. 3
Model used2030 winter and light load base casep. 3
Proposal window exclusionBelow 200 kV exclusionp. 3
Flowgates2025-W1-GD-LL189, 2025-W1-GD-W61, 2025-W1-GD-W217, 2025-W1-GD-W370p. 3
Problem statementWaterman-Sandwich 138 kV and Steward-Haumesser 138 kV lines overloaded for N-1 and N-2 outages in the 2030 light load and winter casep. 3
Ancillary benefit (as printed)The network hosts 85MW of wind generationp. 4
Ancillary benefit (as printed)Voltage regulation challenges, made worse by capacitor bank controls under fluctuating wind outputp. 4
Later ComEd work at the Mendota ring busSeparate ComEd supplemental need ComEd-2026-016 (Mendota) adds two 138kV breakers to the Mendota ring bus (B4025.2); $4.85 M, projected 6/1/2030p. 8

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 14, 2025Item 01 - SRRTEP West - Reliability Analysis Update PDFMendota-Sandwich 138 kV $171.88 M4/15/2030First Read
December 12, 2025Item 16 - SRRTEP West - Reliability Analysis Update PDFMendota-Sandwich 138 kV $171.88 M4/15/2030Recommended Solution

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.