Substation Scout

Natalie Substation

Natalie 500-230kV Substation. Presented by PPL in PJM planning materials (PPL zone, PA).

$408 Mcost estimate as printed p. 7
12/30/2029projected in service p. 7
Project Developmentstatus as printed p. 7

Profile

PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in September 2026, at a transmission cost estimate of $408 million and a projected in-service date of December 30, 2029. (p. 1, p. 3, p. 7) The need, first presented in April 2026 under the title Fisherdale, PA, is a customer request to serve a facility from a 230kV source near Mt Carmel, Pennsylvania, with a total load of approximately 2,000 MW by 2033 and a requested in-service date of June 2028. (p. 7, p. 3) PPL lists the load ramping from 290 MW at initial in-service in 2028 to 500 MW in 2029 and 1,250 MW in 2031. (p. 3) The plan centers on a new Natalie station with a 230kV switchyard ($116 million, with a STATCOM and two capacitor banks) and a 500kV yard ($88 million, two 750MVA 500-230kV transformers), cut into the Sunbury - Susquehanna (Nescopeck) 500kV line over ~10.5 miles at $92 million and into the Montour/Columbia - Frackville 230kV lines over ~6 miles at $58.5 million. (p. 4, p. 5) It also adds second circuits on the Montour - Columbia (10.6 miles) and Frackville - Columbia (26.5 miles) 230kV lines. (p. 4) PPL lists one alternative, which placed the 500-230kV substation near Catawissa, at an estimated $420 million; a separate need asks for 120MW of temporary 69kV service to the same customer. (p. 7, p. 3) PPL lists the project status as Project Development. (p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Natalie 230kV yardNine bays of new BAAH 230kV switchyard with two 144 MVAR capacitor banks and one 200+/-MVAR STATCOM; estimated $116 Mp. 4
Montour/Columbia - Frackville 230kV linesBifurcate into the new Natalie 230kV switchyard (~6 miles); estimated $58.5 Mp. 4
Montour - Columbia 230kV lineAdd the second circuit to the existing line (10.6 miles); estimated $10.5 Mp. 4
Frackville - Columbia 230kV lineAdd the second circuit to the existing line (26.5 miles); estimated $26.5 Mp. 4
Natalie 230kV customer lead linesTwo sets of three 230kV lead lines to the customer substations; estimated $10 Mp. 4
Natalie 500kV yardFour bays of a 500kV yard with two 500-230kV (750MVA) transformers; estimated $88 Mp. 5
Sunbury - Susquehanna (Nescopeck) 500kV lineBifurcate into the new Natalie 500kV yard (~10.5 miles); estimated $92 Mp. 5
Montour 230kV yard230kV line terminal for the new Montour-Natalie line; estimated $0.5 Mp. 5
Frackville 230kV yard230kV line terminal and one 230kV breaker for the new Frackville-Natalie #2 line; estimated $3.5 Mp. 5
Columbia 230kV substationUpgrade bus and bay conductor; estimated $2.5 Mp. 5

Details as printed

Need presentedNeed Meeting 04/07/2026, under the title Fisherdale, PAp. 7
Project driverCustomer Servicep. 3
Customer request, Mt CarmelFacility served from a 230kV source near Mt Carmel, PA; approximately 2,000 MW total (2033); requested in service 06/2028p. 3
Load ramp290 MW initial in-service 2028; 500 MW projected 2029; 1,250 MW projected 2031p. 3
Temporary 69kV service (PPL-2026-0048)Separate need PPL-2026-0048 (Natalie Temporary 69kV): 120MW from a temporary 69kV source near Mt Carmel, PA, requested in service 6/2028, to temporarily serve the customer of need PPL-20260029p. 3
Alternative consideredBifurcate FRAC-COLU, install Natalie 230kV yard, add a second MONT-COLU-FRAC circuit, and install the 500-230kV substation near Catawissa with double circuit 230kV lines to Natalie; estimated $420Mp. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
April 7, 2026Item 05 - PPL Supplemental Projects PDFFisherdale, PA not printed06/2028Need Meeting 04/07/2026
September 8, 2026Item 07 - PPL Supplemental Projects PDFNatalie 500-230kV Substation $408 M12/30/2029Project Development

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first