Natalie Substation
Natalie 500-230kV Substation. Presented by PPL in PJM planning materials (PPL zone, PA).
Profile
PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in September 2026, at a transmission cost estimate of $408 million and a projected in-service date of December 30, 2029. (p. 1, p. 3, p. 7) The need, first presented in April 2026 under the title Fisherdale, PA, is a customer request to serve a facility from a 230kV source near Mt Carmel, Pennsylvania, with a total load of approximately 2,000 MW by 2033 and a requested in-service date of June 2028. (p. 7, p. 3) PPL lists the load ramping from 290 MW at initial in-service in 2028 to 500 MW in 2029 and 1,250 MW in 2031. (p. 3) The plan centers on a new Natalie station with a 230kV switchyard ($116 million, with a STATCOM and two capacitor banks) and a 500kV yard ($88 million, two 750MVA 500-230kV transformers), cut into the Sunbury - Susquehanna (Nescopeck) 500kV line over ~10.5 miles at $92 million and into the Montour/Columbia - Frackville 230kV lines over ~6 miles at $58.5 million. (p. 4, p. 5) It also adds second circuits on the Montour - Columbia (10.6 miles) and Frackville - Columbia (26.5 miles) 230kV lines. (p. 4) PPL lists one alternative, which placed the 500-230kV substation near Catawissa, at an estimated $420 million; a separate need asks for 120MW of temporary 69kV service to the same customer. (p. 7, p. 3) PPL lists the project status as Project Development. (p. 7)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Natalie 230kV yard | Nine bays of new BAAH 230kV switchyard with two 144 MVAR capacitor banks and one 200+/-MVAR STATCOM; estimated $116 M | p. 4 |
| Montour/Columbia - Frackville 230kV lines | Bifurcate into the new Natalie 230kV switchyard (~6 miles); estimated $58.5 M | p. 4 |
| Montour - Columbia 230kV line | Add the second circuit to the existing line (10.6 miles); estimated $10.5 M | p. 4 |
| Frackville - Columbia 230kV line | Add the second circuit to the existing line (26.5 miles); estimated $26.5 M | p. 4 |
| Natalie 230kV customer lead lines | Two sets of three 230kV lead lines to the customer substations; estimated $10 M | p. 4 |
| Natalie 500kV yard | Four bays of a 500kV yard with two 500-230kV (750MVA) transformers; estimated $88 M | p. 5 |
| Sunbury - Susquehanna (Nescopeck) 500kV line | Bifurcate into the new Natalie 500kV yard (~10.5 miles); estimated $92 M | p. 5 |
| Montour 230kV yard | 230kV line terminal for the new Montour-Natalie line; estimated $0.5 M | p. 5 |
| Frackville 230kV yard | 230kV line terminal and one 230kV breaker for the new Frackville-Natalie #2 line; estimated $3.5 M | p. 5 |
| Columbia 230kV substation | Upgrade bus and bay conductor; estimated $2.5 M | p. 5 |
Details as printed
| Need presented | Need Meeting 04/07/2026, under the title Fisherdale, PA | p. 7 |
|---|---|---|
| Project driver | Customer Service | p. 3 |
| Customer request, Mt Carmel | Facility served from a 230kV source near Mt Carmel, PA; approximately 2,000 MW total (2033); requested in service 06/2028 | p. 3 |
| Load ramp | 290 MW initial in-service 2028; 500 MW projected 2029; 1,250 MW projected 2031 | p. 3 |
| Temporary 69kV service (PPL-2026-0048) | Separate need PPL-2026-0048 (Natalie Temporary 69kV): 120MW from a temporary 69kV source near Mt Carmel, PA, requested in service 6/2028, to temporarily serve the customer of need PPL-20260029 | p. 3 |
| Alternative considered | Bifurcate FRAC-COLU, install Natalie 230kV yard, add a second MONT-COLU-FRAC circuit, and install the 500-230kV substation near Catawissa with double circuit 230kV lines to Natalie; estimated $420M | p. 7 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| April 7, 2026 | Item 05 - PPL Supplemental Projects PDF | Fisherdale, PA | not printed | 06/2028 | Need Meeting 04/07/2026 |
| September 8, 2026 | Item 07 - PPL Supplemental Projects PDF | Natalie 500-230kV Substation | $408 M | 12/30/2029 | Project Development |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Catawissa (PPL): described as new
- Natalie 230kV Yard (PPL): described as new
- Nescopeck (PPL): described as new
- Columbia (PPL)
- Frackville (PPL): expansion described
- Montour (PPL)
- Natalie 500-230kV Substation (PPL)
- Sunbury (PPL)
- Susquehanna (PPL): expansion described
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- PPL proposes 16-mile transmission project to serve data center in Mount Carmel area, The News-Item, October 23, 2026. The News-Item reported that PPL is proposing about 16 miles of new lines, about 6 miles of double-circuit 230 kV and 10 miles of double-circuit 500 kV, plus a substation in the Mount Carmel region to serve a prospective data center customer, and that Mount Carmel Township supervisors adopted a resolution opposing the project.
- Proposed data center drives PPL transmission project in Mount Carmel, NorthcentralPa.com, October 28, 2026. NorthcentralPa.com reported that the Natalie Transmission Project would run through Franklin, Catawissa, Cleveland and Conyngham townships in Columbia County and Mount Carmel in Northumberland County, that PPL had not chosen a final route, and that construction would run from spring 2028 to early 2031 if the project moves forward as planned.
- PPL presents Natalie transmission routes as questions surround $408M in regional upgrades, The News-Item, November 4, 2026. The News-Item reported that PPL presented preliminary routes for about 16 miles of new lines at an open house in Elysburg, where residents asked about environmental impacts, costs and the project's connection to a proposed data center near Mount Carmel.
- Project Phoenix plans call for 224 megawatts; PPL confirms Natalie link, Standard-Journal (from The News-Item), November 22, 2026. The News-Item reported that the initial Project Phoenix data center in Mount Carmel Township is designed to require up to 224 megawatts, according to its conditional use application, and that PPL confirmed the proposed Natalie Transmission Project would help deliver electrical service to the development.
Not printed
- The decks name the customer only as a customer; they do not say what the facility is.
- No county is printed; Mt Carmel, PA is the only location given for the customer site.
- The April 2026 need meeting printed no cost or solution; the only cost printed is the September 2026 estimate.
- The temporary 69kV need (PPL-2026-0048) is a separate need with no printed solution or cost in the archived decks, so it is cited as a fact, not a member.
- No later deck in the archive (through December 2026) mentions Natalie or PPL-2026-0029 again.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.