Substation Scout

New Haven, Indiana

New Haven, Indiana. Presented by AEP in PJM planning materials (AEP zone, Indiana).

$169.1 Mcost estimate as printed p. 3
07/01/2029projected in service p. 4
Scopingstatus as printed p. 4

Profile

New Haven, Indiana is an AEP customer service project submitted to PJM for inclusion in AEP's 2026 local plan in January 2026, at a transmission cost estimate of $169.1 million and a projected in-service date of July 2029. (p. 2, p. 1, p. 3, p. 4) The problem statement says a customer requested a new delivery point in New Haven for up to 480 MW by November 2026, rising to 1,200 MW by July 2029; the deck does not name the customer. (p. 2) The plan builds a new 138kV breaker-and-a-half station, Zodiac ($38.1 million), with terminations to 5 customer buildings, and runs 5 double circuit 138kV radials of about 0.75 miles from it to customer-owned stations ($28.5 million). (p. 3) It also adds two 345/138kV transformers at Allen station ($58.5 million), the largest single item, and rebuilds both roughly 3.7 mile 138kV double circuit lines between Allen and Zodiac ($44 million). (p. 3) AEP says it considered serving the customer at 345kV from Allen instead, at an alternate cost of $214 million, and did not choose it because of the time a 345kV greenfield build requires, higher 345kV loadings, and the site's location next to existing 138kV lines. (p. 4) The cost estimate and in-service date printed at the November 2024 solution meeting are unchanged in the 2026 submission, which lists the project status as Scoping. (p. 8, p. 9, p. 2, p. 4)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Allen 345/138kV stationExpand with 2 additional 345/138kV transformers, 3 345kV and 3 138kV breakers; land purchase included; estimated $58.5 Mp. 3
Zodiac 138kV stationNew breaker-and-a-half station with 8 138kV AEP circuit exits and terminations to 5 customer buildings; estimated $38.1 Mp. 3
Allen - Zodiac 138kV linesCut into 2 existing double circuit 138kV lines with 0.2 mile extensions to Zodiac; rebuild both ~3.7 mile double circuit lines (~7.4 miles total); estimated $44 Mp. 3
Customer radials5 double circuit 138kV ~0.75 mile radials from Zodiac to customer-owned stations; estimated $28.5 Mp. 3

Details as printed

Previously presentedNeed Meetings 09/20/2024 and 12/15/2023; Solution Meeting 11/06/2024p. 2
Supplemental project IDs3750.1-4p. 4
DriverCustomer Servicep. 2
Customer request, New HavenNew delivery point in New Haven, Indiana for up to 480 MW by November 2026, increasing from 480MW to 1200MW by July 2029p. 2
Allen transformer need (November 2024 slide)Allen transformers added for N-1-1 overloads for loss of Robison Park Transformer #5 and Allen Transformer #2, or loss of both existing Allen transformersp. 8
Cost, November 2024 solution meeting$169.1 Mp. 8
In service, November 2024 solution meeting07/01/2029p. 9
Alternative consideredServe the customer at 345kV from Allen station instead of 138kVp. 4
Why the alternative was not chosenNot chosen due to the time required for 345kV greenfield, higher loadings on the 345kV, and the customer site being adjacent to existing 138kV; alternate cost $214Mp. 4
Process stage, November 2024Solution Meeting: 11/6/2024p. 8

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 6, 2024Item 07 - AEP Supplemental Projects PDFNew Haven, Indiana $169.1 M07/01/2029Scoping
October 6, 2026Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 PDFNew Haven, Indiana $169.1 M07/01/2029Scoping
Date not printedAEP&nbsp PDFNew Haven, Indiana $169.1 M07/01/2029Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.