New Haven, Indiana
New Haven, Indiana. Presented by AEP in PJM planning materials (AEP zone, Indiana).
Profile
New Haven, Indiana is an AEP customer service project submitted to PJM for inclusion in AEP's 2026 local plan in January 2026, at a transmission cost estimate of $169.1 million and a projected in-service date of July 2029. (p. 2, p. 1, p. 3, p. 4) The problem statement says a customer requested a new delivery point in New Haven for up to 480 MW by November 2026, rising to 1,200 MW by July 2029; the deck does not name the customer. (p. 2) The plan builds a new 138kV breaker-and-a-half station, Zodiac ($38.1 million), with terminations to 5 customer buildings, and runs 5 double circuit 138kV radials of about 0.75 miles from it to customer-owned stations ($28.5 million). (p. 3) It also adds two 345/138kV transformers at Allen station ($58.5 million), the largest single item, and rebuilds both roughly 3.7 mile 138kV double circuit lines between Allen and Zodiac ($44 million). (p. 3) AEP says it considered serving the customer at 345kV from Allen instead, at an alternate cost of $214 million, and did not choose it because of the time a 345kV greenfield build requires, higher 345kV loadings, and the site's location next to existing 138kV lines. (p. 4) The cost estimate and in-service date printed at the November 2024 solution meeting are unchanged in the 2026 submission, which lists the project status as Scoping. (p. 8, p. 9, p. 2, p. 4)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Allen 345/138kV station | Expand with 2 additional 345/138kV transformers, 3 345kV and 3 138kV breakers; land purchase included; estimated $58.5 M | p. 3 |
| Zodiac 138kV station | New breaker-and-a-half station with 8 138kV AEP circuit exits and terminations to 5 customer buildings; estimated $38.1 M | p. 3 |
| Allen - Zodiac 138kV lines | Cut into 2 existing double circuit 138kV lines with 0.2 mile extensions to Zodiac; rebuild both ~3.7 mile double circuit lines (~7.4 miles total); estimated $44 M | p. 3 |
| Customer radials | 5 double circuit 138kV ~0.75 mile radials from Zodiac to customer-owned stations; estimated $28.5 M | p. 3 |
Details as printed
| Previously presented | Need Meetings 09/20/2024 and 12/15/2023; Solution Meeting 11/06/2024 | p. 2 |
|---|---|---|
| Supplemental project ID | s3750.1-4 | p. 4 |
| Driver | Customer Service | p. 2 |
| Customer request, New Haven | New delivery point in New Haven, Indiana for up to 480 MW by November 2026, increasing from 480MW to 1200MW by July 2029 | p. 2 |
| Allen transformer need (November 2024 slide) | Allen transformers added for N-1-1 overloads for loss of Robison Park Transformer #5 and Allen Transformer #2, or loss of both existing Allen transformers | p. 8 |
| Cost, November 2024 solution meeting | $169.1 M | p. 8 |
| In service, November 2024 solution meeting | 07/01/2029 | p. 9 |
| Alternative considered | Serve the customer at 345kV from Allen station instead of 138kV | p. 4 |
| Why the alternative was not chosen | Not chosen due to the time required for 345kV greenfield, higher loadings on the 345kV, and the customer site being adjacent to existing 138kV; alternate cost $214M | p. 4 |
| Process stage, November 2024 | Solution Meeting: 11/6/2024 | p. 8 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| November 6, 2024 | Item 07 - AEP Supplemental Projects PDF | New Haven, Indiana | $169.1 M | 07/01/2029 | Scoping |
| October 6, 2026 | Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 PDF | New Haven, Indiana | $169.1 M | 07/01/2029 | Scoping |
| Date not printed | AEP  PDF | New Haven, Indiana | $169.1 M | 07/01/2029 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Zodiac (AEP): described as new
- Allen (AEP): expansion described
- Robison Park (AEP)
Not printed
- The deck names the customer only as a customer; it does not say what the load is.
- No county or street location is printed for Zodiac station.
- No news article about this transmission program could be found and opened; coverage found was about the customer's campus, not the Allen - Zodiac work.
- The December 2023 and September 2024 need meeting decks are not in the archive.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.