Customer in Grayslake (ComEd-2025-005)
Customer in Grayslake. Presented by ComEd in PJM planning materials (ComEd zone).
Profile
ComEd presented Customer in Grayslake (need ComEd-2025-005) to PJM's TEAC on July 7, 2026 at a total estimated transmission cost of $248.8 million, with the status Conceptual. (p. 8, p. 1, p. 12) The deck describes a new customer looking for transmission service in the Grayslake area, with initial loading of 320 MW in June 2028, 600 MW in 2029 and an ultimate load of 1,550 MW in 2031. (p. 8) The solution builds a new Grayslake 345 kV substation in three phases, cut into the Silver Lake - Libertyville line and later the Tollway - Libertyville line, at $113 million, $15 million and $44 million. (p. 9) System reinforcements add $72.8 million on the 345 kV system, including 14.4 miles of reconductoring from Silver Lake to Grayslake and a new 420 MVA transformer at Tollway, plus $3.0 million and $1.0 million of 138 kV work near Spaulding and Hanover Tap. (p. 10, p. 11, p. 12) Projected in-service dates run from June 1, 2027 for Phase 1 to June 1, 2031 for the Tollway - Grayslake 345 kV work. (p. 12) At the March 10, 2026 solutions meeting the same three phases totaled $174.8 million with only $2.8 million of system reinforcement, and Phase 3 cut into the Beverly Road - Libertyville line instead. (p. 8, p. 7, p. 8) ComEd first presented the need on April 1, 2025 with initial loading of 300 MW in June 2028 and an ultimate load of 1,550 MW; the July 2026 deck also lists ComEd-2025-005 among the eight needs behind its 345KV STATCOMS solution. (p. 3, p. 13)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Silver Lake - Libertyville 345kV cut-in (Phase 1) | Cut into existing line; extend 2 lines 0.1 miles each to a new Grayslake substation | p. 9 |
| Grayslake 345kV substation (new, Phase 1) | Initially 7 345 kV circuit breakers in a breaker and a half configuration | p. 9 |
| Grayslake capacitor bank (Phase 1) | 1-150 MVAR, 345kV capacitor bank | p. 9 |
| Grayslake breakers (Phase 2) | Install 5 new 345 kV circuit breakers | p. 9 |
| Tollway - Libertyville 345kV cut-in (Phase 3) | Cut into existing line; extend 2 lines 0.1 miles each to Grayslake | p. 9 |
| Grayslake breakers and capacitor bank (Phase 3) | Install 7 new 345 kV circuit breakers and 1-150 MVAR, 345kV capacitor bank | p. 9 |
| Silver Lake - Grayslake 345kV reconductor | Reconductor 14.4 miles with 2-1113 Twisted Bluejay ($28.8M) | p. 10 |
| Wayne - Tollway 345kV reconductor and Tollway breaker | Reconductor 5.5 miles with 2156 ACSR Bluebird and add one 345kV SF6 breaker at Tollway ($15.0M) | p. 10 |
| Tollway - Grayslake towers | Resag/raise 6 towers ($8.0M) | p. 10 |
| Tollway 345/138 kV transformer TR84 | One new 420MVA 345KV/138KV transformer with one 345kV and one 138kV breaker ($21.0M) | p. 10 |
| Spaulding 138kV breaker | Replace one 138kV oil circuit breaker for Spaulding - Hanover - Tollway Blue | p. 11 |
| Hanover Tap 138kV reconductors (Blue) | Reconductor 0.1 mile Spaulding - Hanover Tap Blue and 0.2 mile Tollway - Hanover Tap Blue | p. 11 |
| Hanover Tap 138kV reconductors (Red) | Reconductor 0.2 mile Spaulding - Hanover Tap Red and 0.2 mile Tollway - Hanover Tap Red | p. 12 |
Details as printed
| Project driver | Customer Service | p. 8 |
|---|---|---|
| Customer request, Grayslake | 320 MW in June 2028, 600 MW in 2029, ultimate 1,550 MW in 2031 | p. 8 |
| Previously presented | Solutions Meeting 3/10/2026, Needs Meeting 4/1/2025 | p. 8 |
| Phase 1 cost | $113M | p. 9 |
| Phase 2 cost | $15M | p. 9 |
| Phase 3 cost | $44M | p. 9 |
| 345 kV system reinforcements cost | $72.8M | p. 10 |
| 138 kV reinforcements cost (Blue lines) | $3.0M | p. 11 |
| 138 kV reinforcements cost (Red lines) | $1.0M | p. 12 |
| Model | 2029 RTEP | p. 12 |
| Cost, March 10, 2026 solution | $174.8M | p. 8 |
| In-service, March 10, 2026 solution | 6/30/2027 (Phase 1), 6/30/2029 (Phase 2), 6/30/2030 (Phase 3), 6/1/2029 (System Reinforcement) | p. 8 |
| Reinforcement cost, March 10, 2026 solution | System reinforcement: $2.8M | p. 8 |
| Phase 3 cut-in, March 10, 2026 solution | Cut into the Beverly Road - Libertyville 345kV line; extend 2 lines 0.1 miles each to Grayslake | p. 7 |
| Customer request, April 1, 2025 need meeting | 300 MW in June 2028, 600 MW in 2029, ultimate 1,550 MW | p. 3 |
| Also listed under 345KV STATCOMS (same deck) | ComEd-2025-005 is one of eight need numbers on the 345KV STATCOMS solution, Solution Meeting 7/7/2026 | p. 13 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| April 1, 2025 | Item 08 - ComEd Supplemental Projects PDF | Customer in Grayslake | not printed | not printed | Need Meeting 4/1/2025 |
| March 10, 2026 | Item 08 - ComEd Supplemental Projects PDF | Customer in Grayslake | $174.8M | 6/30/2027 (Phase 1), 6/30/2029 (Phase 2), 6/30/2030 (Phase 3), 6/1/2029 (System Reinforcement) | Conceptual |
| July 7, 2026 | Item 12 - ComEd Supplemental Projects PDF | Customer in Grayslake | $248.8M | 6/1/2027 (Phase 1), 6/1/2029 (Phase 2), 6/1/2030 (Phase 3), 6/1/2029 (138KV System Reinforcement), 6/1/2030 (345KV Auto, 345KV Silverlake-Grayslake, 345KV Wayne-Tollway), 6/1/2031 (345KV Tollway-Grayslake) | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Beverly Road (COMED): described as new
- Grayslake (COMED): described as new
- Hanover Tap (COMED)
- Hanover Tap Blue (COMED)
- Hanover Tap Red (COMED)
- Libertyville (COMED)
- Silver Lake (COMED)
- Spaulding (COMED)
- Tollway (COMED)
- Wayne (COMED)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- ‘A place of innovation and opportunity’: Work underway for data center campus in Grayslake, Daily Herald, October 11, 2025. The Daily Herald reported that site work had begun on T5 Data Centers' campus at the Cornerstone business park in Grayslake, which it said would be supported by an on-site primary ComEd transmission substation, with first power in June 2027; the article gives both 1.2 and 1.5 gigawatts for the power and does not cite a PJM need number.
- CEO defends controversial proposed Grayslake data center, NBC Chicago, September 28, 2026. NBC Chicago reported that T5's chief executive defended the proposed Grayslake data center, which the station said could consume up to 1.2 gigawatts once all phases are complete, and that T5 says it has a separate rate agreement with ComEd; the article does not mention a substation or this PJM need.
Not printed
- No state or county is printed on the cited pages; Illinois is not printed.
- The decks name the customer only as a new customer; they do not say what the load is.
- Neither news article cites ComEd-2025-005 or PJM; the link between T5's Grayslake campus and this need is not printed by ComEd, PJM or the outlets. The outlets' power figures (1.2 and 1.5 gigawatts) differ from the 1,550 MW in the deck.
- The April 1, 2025 need meeting row carries no cost, date or status; the first printed cost is the March 10, 2026 figure.
- The July 2026 deck does not say why system reinforcement rose from $2.8M to $72.8M between the two solutions meetings.
- The 2026 RTEP Window 1 proposal list (TEAC, November 3, 2026) includes several proposals that name Grayslake (Plano - Grayslake, Tollway - Grayslake); nothing printed ties them to this need, so they are not members.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.