Valley Link

Valley Link Transmission Project. Presented by PJM in PJM planning materials (AEP, APS/FE, DVP zone, WV, VA, MD (state affiliate VLT-MD)).

$5,115M (2026 dollars)cost estimate as printed p. 13
5/31/2031projected in service p. 14
Selected, 2024 Open Window #1status as printed p. 13

Profile

PJM's November 3, 2026 update to its Transmission Expansion Advisory Committee puts the Valley Link Transmission Project at $5,115 million in 2026 dollars, up from an original estimate of $2,995 million in 2024 dollars. (p. 1, p. 13) The project combines three proposals selected through PJM's 2024 Open Window #1 (2024-W1-967, 2024-W1-820 and 2024-W1-708), built around new 765 kV lines from Amos to Welton Spring (175 miles), Welton Spring to Rocky Point (86 miles) and Joshua Falls to Yeat (115 miles). (p. 13, p. 14) When PJM recommended proposal 2024-W1-708, the Amos - Welton Spring - Rocky Point portion, it listed an estimated cost of $1,945.05 million and a projected in-service date of December 1, 2029. (p. 65) The original proposals assumed a June 1, 2029 in-service date for every component; the revised dates are May 31, 2031 for the Amos - Welton Spring - Rocky Point components, January 17, 2031 for the Joshua Falls - Yeat line and Yeat substation, and January 18, 2030 for Thornburg substation. (p. 13, p. 14) The update attributes the cost increase primarily to construction labor and outside services, right-of-way and land costs, and material and equipment costs, and attributes the later dates to more detailed routing analysis, expanded stakeholder and regulatory engagement, and permitting. (p. 13) The largest single line in the updated table is the 145-mile APS/FE section of the Amos - Welton Spring line, at $1,356.28 million, up from $725.00 million. (p. 14) PJM lists the work as designated to Valley Link Transmission, split between state affiliates VLT-MD, VLT-VA and VLT-WV, and Valley Link has evaluated options for relocating the Yeat substation further south. (p. 51, p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Amos - Welton Spring 765 kV line (AEP section)175-mile line, AEP section 30 miles; $150.00M original, $277.79M updatedp. 14
Amos - Welton Spring 765 kV line (APS/FE section)APS/FE section 145 miles; $725.00M original, $1,356.28M updatedp. 14
Welton Spring 765 kV switchyardNew switchyard; $92.28M original, $145.68M updatedp. 14
Welton Spring capacitors and STATCOMFour 250 MVAR shunt capacitors and a +/-500 MVAR STATCOM; $121.54M original, $193.11M updatedp. 14
Welton Spring - Rocky Point 765 kV line (WV portion)Roughly 50 miles in WV; $248.50M original, $478.58M updatedp. 14
Welton Spring - Rocky Point 765 kV line (VA portion)Roughly 21 miles in VA; $105.00M original, $293.00M updatedp. 14
Welton Spring - Rocky Point 765 kV line (Millville to Lovettsville section)Roughly 10.5 miles; $52.50M original, $144.31M updatedp. 14
Welton Spring - Rocky Point 765 kV line (to Rocky Point)Roughly 4.8 miles, entity VLT MD; $24.00M original, $59.61M updatedp. 14
Rocky Point 765/500 kV substationNew substation with a 765 kV and a 500 kV yard, loop-ins of 500 kV lines, two 765/500 kV transformersp. 14
Rocky Point 765/500 kV substation cost$254.70M original, $316.32M updatedp. 14
Rocky Point capacitors and STATCOMFour 250 MVAR cap banks and a +/-500 MVAR STATCOM; $121.00M original, $148.86M updatedp. 14
Thornburg 500/230kV substationNew 500/230kV substation with two 1400MVA 500/230 kV transformersp. 14
Thornburg substation cost$84.41M original, $142.80M updatedp. 14
Joshua Falls - Yeat 765kV line (AEP section)115-mile line, roughly 1 mile in AEP section; $341.17M original, $11.88M updatedp. 14
Joshua Falls - Yeat 765kV line (Dominion section)Roughly 114 miles in Dominion section; $426.83M original, $1,176.44M updatedp. 14
Yeat 765/500 kV substationNew substation with two 765/500 kV transformers, Spotsylvania - Morrisville 500kV cut-in; $197.10M original, $370.34M updatedp. 14

Details as printed

Voltage765 kVp. 51
DeveloperValley Link Transmission (VLT), split between state affiliates VLT-MD, VLT-VA and VLT-WVp. 51
Cost table totalTable total: $2,944.03 M original, $5,115.00 M updatedp. 14
Cost footnoteb4000.346 ($5.00M) re-designated to Dominion/Vepco and b4000.358 ($45.60M) cancelled; the 2024 proposal including them was $2,994.63Mp. 14
Cost driversIncrease driven primarily by construction labor / outside services, right-of-way and land costs, and material and equipment costsp. 13
In service originalOriginal proposals assumed June 1, 2029 for all componentsp. 13
Schedule reasonRevised dates reflect post-award development: more detailed routing analysis, expanded stakeholder and regulatory engagement, permitting and other approvalsp. 13
In service yeat1/17/2031 revised in-service date for the Joshua Falls - Yeat line and Yeat substation (originally 6/1/2029)p. 14
In service thornburg1/18/2030 revised in-service date for the Thornburg substation (originally 6/1/2029)p. 14
Cost preferred 2024 12Preferred solution estimate: $1,944.98 Mp. 78
Cost recommended 2025 01Recommended solution 2024-W1-708: estimated cost $1,945.05 M, projected in service 12/1/2029p. 65
W1 820 cost 2026 08Proposal estimate (all entities) printed as $1,055.3 M, then $1,109.89M, then $978.76 Mp. 34
B4000 6 splitOriginal b4000.6 (roughly 70.7 miles, $353.5M) split into b4000.6 (Virginia, roughly 21 miles, $105M) and b4000.15 (West Virginia, roughly 50 miles, $248.5M)p. 51
Yeat relocationValley Link evaluating options to relocate the Yeat substation further south, including to reduce new 765kV line mileage and residential, environmental, cultural and historical impactsp. 7
Thornburg new idsNew baseline IDs b4000.364 and b4000.365 ($2.5M each) for terminating line 568 into Thornburg designated to Valley Link Transmissionp. 8
Cost preferred is 2024 12Projected IS Date: 12/1/2029 (required 6/1/2029)p. 78

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 3, 2024Item 11 - Reliability Analysis Update PDF2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 $1,944.98 M12/1/2029
January 7, 2025Item 12 - Reliability Analysis Update PDFRecommended Solution: 2024-W1-708 $1,945.05 M12/1/2029
January 7, 2025Item 12 - Reliability Analysis Update PDFRecommended Solution: 2024-W1-820 $1,109.89M6/1/2029
June 5, 2025Item 09 - Reliability Analysis Update PDF2024 W1 Regional Cluster: Baseline b4000.6 Project Update $353.5 M6/1/2029
February 3, 2026Item 13 - Reliability Analysis Update PDFYeat Substation Relocation Update not printednot printed
April 7, 2026Item 11 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation $1,109.89M6/1/2029First Read
May 8, 2026Item 10 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation $1,109.89M6/1/2029First Read
August 4, 2026Item 13 - Reliability Analysis Update PDF2024W1 – Regional Cluster Recommended Solution: 2024-W1-820 $978.76 M6/1/2029
November 3, 2026Item 09 - Reliability Analysis UpdateValley Link Transmission Project Schedule & Cost Estimate Update $5,115M5/31/2031

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.