Valley Link
Valley Link Transmission Project. Presented by PJM in PJM planning materials (AEP, APS/FE, DVP zone, WV, VA, MD (state affiliate VLT-MD)).
Profile
PJM's November 3, 2026 update to its Transmission Expansion Advisory Committee puts the Valley Link Transmission Project at $5,115 million in 2026 dollars, up from an original estimate of $2,995 million in 2024 dollars. (p. 1, p. 13) The project combines three proposals selected through PJM's 2024 Open Window #1 (2024-W1-967, 2024-W1-820 and 2024-W1-708), built around new 765 kV lines from Amos to Welton Spring (175 miles), Welton Spring to Rocky Point (86 miles) and Joshua Falls to Yeat (115 miles). (p. 13, p. 14) When PJM recommended proposal 2024-W1-708, the Amos - Welton Spring - Rocky Point portion, it listed an estimated cost of $1,945.05 million and a projected in-service date of December 1, 2029. (p. 65) The original proposals assumed a June 1, 2029 in-service date for every component; the revised dates are May 31, 2031 for the Amos - Welton Spring - Rocky Point components, January 17, 2031 for the Joshua Falls - Yeat line and Yeat substation, and January 18, 2030 for Thornburg substation. (p. 13, p. 14) The update attributes the cost increase primarily to construction labor and outside services, right-of-way and land costs, and material and equipment costs, and attributes the later dates to more detailed routing analysis, expanded stakeholder and regulatory engagement, and permitting. (p. 13) The largest single line in the updated table is the 145-mile APS/FE section of the Amos - Welton Spring line, at $1,356.28 million, up from $725.00 million. (p. 14) PJM lists the work as designated to Valley Link Transmission, split between state affiliates VLT-MD, VLT-VA and VLT-WV, and Valley Link has evaluated options for relocating the Yeat substation further south. (p. 51, p. 7)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Amos - Welton Spring 765 kV line (AEP section) | 175-mile line, AEP section 30 miles; $150.00M original, $277.79M updated | p. 14 |
| Amos - Welton Spring 765 kV line (APS/FE section) | APS/FE section 145 miles; $725.00M original, $1,356.28M updated | p. 14 |
| Welton Spring 765 kV switchyard | New switchyard; $92.28M original, $145.68M updated | p. 14 |
| Welton Spring capacitors and STATCOM | Four 250 MVAR shunt capacitors and a +/-500 MVAR STATCOM; $121.54M original, $193.11M updated | p. 14 |
| Welton Spring - Rocky Point 765 kV line (WV portion) | Roughly 50 miles in WV; $248.50M original, $478.58M updated | p. 14 |
| Welton Spring - Rocky Point 765 kV line (VA portion) | Roughly 21 miles in VA; $105.00M original, $293.00M updated | p. 14 |
| Welton Spring - Rocky Point 765 kV line (Millville to Lovettsville section) | Roughly 10.5 miles; $52.50M original, $144.31M updated | p. 14 |
| Welton Spring - Rocky Point 765 kV line (to Rocky Point) | Roughly 4.8 miles, entity VLT MD; $24.00M original, $59.61M updated | p. 14 |
| Rocky Point 765/500 kV substation | New substation with a 765 kV and a 500 kV yard, loop-ins of 500 kV lines, two 765/500 kV transformers | p. 14 |
| Rocky Point 765/500 kV substation cost | $254.70M original, $316.32M updated | p. 14 |
| Rocky Point capacitors and STATCOM | Four 250 MVAR cap banks and a +/-500 MVAR STATCOM; $121.00M original, $148.86M updated | p. 14 |
| Thornburg 500/230kV substation | New 500/230kV substation with two 1400MVA 500/230 kV transformers | p. 14 |
| Thornburg substation cost | $84.41M original, $142.80M updated | p. 14 |
| Joshua Falls - Yeat 765kV line (AEP section) | 115-mile line, roughly 1 mile in AEP section; $341.17M original, $11.88M updated | p. 14 |
| Joshua Falls - Yeat 765kV line (Dominion section) | Roughly 114 miles in Dominion section; $426.83M original, $1,176.44M updated | p. 14 |
| Yeat 765/500 kV substation | New substation with two 765/500 kV transformers, Spotsylvania - Morrisville 500kV cut-in; $197.10M original, $370.34M updated | p. 14 |
Details as printed
| Voltage | 765 kV | p. 51 |
|---|---|---|
| Developer | Valley Link Transmission (VLT), split between state affiliates VLT-MD, VLT-VA and VLT-WV | p. 51 |
| Cost table total | Table total: $2,944.03 M original, $5,115.00 M updated | p. 14 |
| Cost footnote | b4000.346 ($5.00M) re-designated to Dominion/Vepco and b4000.358 ($45.60M) cancelled; the 2024 proposal including them was $2,994.63M | p. 14 |
| Cost drivers | Increase driven primarily by construction labor / outside services, right-of-way and land costs, and material and equipment costs | p. 13 |
| In service original | Original proposals assumed June 1, 2029 for all components | p. 13 |
| Schedule reason | Revised dates reflect post-award development: more detailed routing analysis, expanded stakeholder and regulatory engagement, permitting and other approvals | p. 13 |
| In service yeat | 1/17/2031 revised in-service date for the Joshua Falls - Yeat line and Yeat substation (originally 6/1/2029) | p. 14 |
| In service thornburg | 1/18/2030 revised in-service date for the Thornburg substation (originally 6/1/2029) | p. 14 |
| Cost preferred 2024 12 | Preferred solution estimate: $1,944.98 M | p. 78 |
| Cost recommended 2025 01 | Recommended solution 2024-W1-708: estimated cost $1,945.05 M, projected in service 12/1/2029 | p. 65 |
| W1 820 cost 2026 08 | Proposal estimate (all entities) printed as $1,055.3 M, then $1,109.89M, then $978.76 M | p. 34 |
| B4000 6 split | Original b4000.6 (roughly 70.7 miles, $353.5M) split into b4000.6 (Virginia, roughly 21 miles, $105M) and b4000.15 (West Virginia, roughly 50 miles, $248.5M) | p. 51 |
| Yeat relocation | Valley Link evaluating options to relocate the Yeat substation further south, including to reduce new 765kV line mileage and residential, environmental, cultural and historical impacts | p. 7 |
| Thornburg new ids | New baseline IDs b4000.364 and b4000.365 ($2.5M each) for terminating line 568 into Thornburg designated to Valley Link Transmission | p. 8 |
| Cost preferred is 2024 12 | Projected IS Date: 12/1/2029 (required 6/1/2029) | p. 78 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 3, 2024 | Item 11 - Reliability Analysis Update PDF | 2024W1 – Regional Cluster Preferred Solution: 2024-W1-708 | $1,944.98 M | 12/1/2029 | |
| January 7, 2025 | Item 12 - Reliability Analysis Update PDF | Recommended Solution: 2024-W1-708 | $1,945.05 M | 12/1/2029 | |
| January 7, 2025 | Item 12 - Reliability Analysis Update PDF | Recommended Solution: 2024-W1-820 | $1,109.89M | 6/1/2029 | |
| June 5, 2025 | Item 09 - Reliability Analysis Update PDF | 2024 W1 Regional Cluster: Baseline b4000.6 Project Update | $353.5 M | 6/1/2029 | |
| February 3, 2026 | Item 13 - Reliability Analysis Update PDF | Yeat Substation Relocation Update | not printed | not printed | |
| April 7, 2026 | Item 11 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation | $1,109.89M | 6/1/2029 | First Read |
| May 8, 2026 | Item 10 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation | $1,109.89M | 6/1/2029 | First Read |
| August 4, 2026 | Item 13 - Reliability Analysis Update PDF | 2024W1 – Regional Cluster Recommended Solution: 2024-W1-820 | $978.76 M | 6/1/2029 | |
| November 3, 2026 | Item 09 - Reliability Analysis Update | Valley Link Transmission Project Schedule & Cost Estimate Update | $5,115M | 5/31/2031 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Rocky Point (PJM system-wide): described as new
- Thornburg (DOM): described as new
- Thornburg (PJM system-wide): described as new
- Vontay (DOM): described as new
- Welton Spring (PJM system-wide): described as new
- Welton Springs (PJM system-wide): described as new
- Wishing Star (DOM): described as new
- Yeat (DOM): described as new
- Yeat (PJM system-wide): described as new
- 502 Jct (PJM system-wide)
- Amos (PJM system-wide)
- Anderson Branch (DOM)
- Aspen (PJM system-wide)
- Black Oak (PJM system-wide): expansion described
- Bristers (DOM)
- Bristers (PJM system-wide)
- Cloverdale (PJM system-wide)
- Cunningham (DOM)
- Doubs (PJM system-wide)
- Elk Run (DOM)
- Elk Run (PJM system-wide)
- Elmont (DOM)
- Goose Creek (PJM system-wide)
- Joshua Falls (DOM)
- Joshua Falls (PJM system-wide)
- Meadowbrook (DOM)
- Meadowbrook (PJM system-wide)
- Midlothian (DOM)
- Morrisville (DOM)
- Morrisville (PJM system-wide)
- Mosby (DOM)
- Nokesville (DOM): expansion described
- North Anna (DOM): expansion described
- North Anna (PJM system-wide)
- Possum Pt (DOM)
- Spotsylvania (DOM)
- Spotsylvania (PJM system-wide)
- Vint Hill (DOM): expansion described
- Vint Hill (PJM system-wide)
- Woodside (PJM system-wide)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- FERC urged to reject proposed ROE, incentives for $3B Valley Link transmission project, Utility Dive, April 7, 2025. Utility Dive reported that the Maryland Office of People's Counsel and a Virginia resident asked FERC to reject or set for hearing Valley Link Transmission's request for a 10.9% base return on equity and other incentives, and that the joint venture is owned by Transource (36%), FirstEnergy (34%) and Dominion (30%).
- Why Northern Virginians will help pay for controversial rural transmission line project, WTOP, July 20, 2026. WTOP reported that Valley Link's roughly 115-mile Virginia line from Campbell County to Culpeper County faces opposition from residents along the route, that Culpeper officials have opposed the proposed Yeat substation, and that the company planned to file its preferred route with the State Corporation Commission in the fall.
- Valley Link aims to meet growing energy demand, but farmers fear losing family land, WSET, October 29, 2026. WSET reported that an Appomattox County family whose 190-acre beef cattle farm is crossed by three of the routes under consideration said the line could force them to sell their herd, while utility representatives cited data center and other demand growth.
- Researcher: Valley Link is now $5.1 billion and 2031. PJM's own rules give the counties a question to ask., Cardinal News (opinion), November 6, 2026. In an opinion column in Cardinal News, independent researcher Tommy Turner wrote that PJM's November figures put Valley Link at $5.1 billion in 2026 dollars with later in-service dates, and argued that PJM's operating agreement gives counties grounds to ask whether the delay triggers a re-evaluation of the project's need.
Not printed
- PJM's materials do not print a project status such as Engineering or Construction for the Valley Link components; the status given is the window selection.
- No county is printed for Welton Spring, Rocky Point, Yeat or Thornburg in these documents.
- The November 2026 table does not list b4000.1 (Amos breakers), b4000.11 (Black Oak) or b4000.12 (Doubs), which were part of the 2024-W1-708 recommended solution; these documents do not name their designated entities.
- The November 2026 update gives no reason for the drop in the b4000.355 estimate from $341.17M to $11.88M.
- Proposal 2024-W1-967 (North Anna - Thornburg - Bristers) is named as a Valley Link proposal, but its tracked row is not a member here: its printed costs cover Dominion work, and only b4000.348 (Thornburg) is listed under Valley Link.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.