Substation Scout

ComEd 345kV STATCOMs

345KV STATCOMS. Presented by ComEd in PJM planning materials (ComEd zone).

$472.0Mcost estimate as printed p. 14
06/01/2031projected in service p. 14
Conceptualstatus as printed p. 14

Profile

ComEd presented the 345kV STATCOMs as a proposed solution to PJM's Transmission Expansion Advisory Committee on July 7, 2026, at an estimated transmission cost of $472.0 million and a projected in-service date of June 2031. (p. 13, p. 1, p. 14) ComEd describes the work as system reinforcements required to serve the load and meet applicable transmission planning criteria, and lists eight need numbers, from ComEd-2024-014 to ComEd-2025-020, previously presented at need meetings between August 2024 and March 2026. (p. 13) The plan adds a +/-350 MVAR STATCOM at four 345kV substations: Hiawatha ($88.0 million), Itasca ($108.0 million), Silver Lake ($112.0 million), and a new Charter Grove substation cut into the existing Byron - Wayne line ($164.0 million); the last three also get a 150 MVAR capacitor bank. (p. 13, p. 14) Charter Grove would start as a four-breaker 345kV ring bus, expandable to a breaker-and-a-half layout; a new Charter Grove substation on the same line was also part of the solution ComEd presented for a Customer in DeKalb need (ComEd-2025-009) in February 2026. (p. 14, p. 5) The tracked row for need ComEd-2024-014 first appeared as Customer in Plano, an ultimate 480 MW request, with a $35.3 million connection solution presented on September 9, 2025; that earlier cost is for the Plano connection, not for the STATCOMs. (p. 16, p. 15) The same July 2026 deck lists another of the eight needs, Customer in Grayslake (ComEd-2025-005), with an ultimate load of 1,550 MW in 2031. (p. 8) ComEd lists the project status as Conceptual and says no feasible alternatives were available. (p. 14)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Hiawatha 345kV substation+/-350 MVAR STATCOM and two circuit breakers; $88.0Mp. 13
Itasca 345kV substation+/-350 MVAR STATCOM, 1-150 MVAR capacitor bank, three circuit breakers; $108.0Mp. 13
Silver Lake 345kV substation+/-350 MVAR STATCOM, 1-150 MVAR capacitor bank, four circuit breakers; $112.0Mp. 13
Byron - Wayne 345kV line cut-in (printed "Bryon")Cut into the existing line to a new Charter Grove substation; $164.0Mp. 14
Charter Grove 345kV substation (new)Four-breaker 345kV ring bus at first, expandable to breaker and a halfp. 14
Charter Grove STATCOM+/-350 MVAR STATCOM, 1-150 MVAR capacitor bank, three circuit breakers; no separate cost printedp. 14

Details as printed

Need numbers listedEight need numbers: ComEd-2024-014, ComEd-2024-022, ComEd-2025-005, ComEd-2025-011, ComEd-2025-013, ComEd-2025-015, ComEd-2025-016, ComEd-2025-020p. 13
Previously presentedNeed meetings 8/6/2024, 4/1/2025, 9/9/2025, 9/19/2025, 3/10/2026p. 13
Purpose as printedSystem reinforcements required to serve the load and meet applicable transmission planning criteriap. 13
Alternatives consideredNo feasible alternatives availablep. 14
Customer request, Grayslake (ComEd-2025-005)320 MW in June 2028, 600 MW in 2029, ultimate 1,550 MW in 2031p. 8
Grayslake need, same deckCustomer in Grayslake, ComEd-2025-005p. 8
Earlier slide for ComEd-2024-014Customer in Plano, ComEd-2024-014, Solution Meeting 9/9/2025p. 16
Customer request, Plano (ComEd-2024-014)216 MW in June 2028, 270 MW in June 2029, ultimate 480 MW in 2032p. 15
Plano connection solution, September 2025Plano customer connection: $35.3 M, in service 5/1/2028p. 16
Charter Grove, February 2026 deckNew Charter Grove substation on the Byron - Wayne 345kV line, in the Customer in DeKalb solution (ComEd-2025-009)p. 5

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 12 - ComEd Supplemental Projects PDFCustomer in Plano $35.3 M5/1/2028Conceptual
July 7, 2026Item 12 - ComEd Supplemental Projects PDF345KV STATCOMS $472.0M06/01/2031Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first