Substation Scout

Orefield Substation

Orefield, PA. Presented by PPL in PJM planning materials (PPL zone, PA).

$194 Mcost estimate as printed p. 17
05/31/2028projected in service p. 17
Conceptualstatus as printed p. 17

Profile

PPL included this customer service project in its 2026 Local Plan submission (stage date March 13, 2026), shown to PJM's Transmission Expansion Advisory Committee in October 2026, at a transmission cost estimate of $194 million and a projected in-service date of May 31, 2028. (p. 17, p. 16) The need, presented in May 2025 under the title Orefield, PA, is a customer request to serve a facility from a 138kV source in Allentown, Pennsylvania, with a total load of approximately 1000 MW by 2031 and a requested in-service date of October 2026. (p. 5, p. 16) PPL lists the load ramping from 75 MW at initial in-service in 2026 to 450 MW in 2028 and 920 MW in 2030. (p. 16) The plan centers on a new Orefield 500-138kV substation: a three-bay 500kV yard with two 500-138kV transformers ($71 million) and an eight-bay 138kV yard ($40 million), cut into the Susquehanna - Wescosville 500kV line over approximately 1.2 miles at $17.2 million and into the Siegfried - Wescosville and Wescosville - Allentown #1 & #2 138kV lines. (p. 17) Six 138kV lead lines of approximately 0.75 miles run to the customer facility ($9 million), and PPL also connects a spare 500-138kV transformer at Wescosville ($5 million) and rebuilds the Wescosville 138kV yard ($35 million). (p. 17) At the first solution meeting in June 2025 the estimate was $159 million with in-service on May 30, 2028; the Wescosville 138kV yard rebuild first appears at a second solution meeting in November 2025, where the estimate is $194 million and in-service May 31, 2028. (p. 6, p. 4, p. 17) PPL lists one alternative, which added a new 500kV line of about 20 miles from Alburtis, at an estimated $359 million, and lists the project status as Conceptual. (p. 17)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Orefield 500-138kV substationNew three bay BAAH 500kV yard with two 500-138kV transformers and one 144MVAR capacitor bank; estimated $71 M (s3801.1)p. 17
Orefield 138kV yardEight bay BAAH 138kV yard with two 44MVAR capacitor banks; estimated $40 M (s3801.2)p. 17
Susquehanna - Wescosville 500kV lineBifurcate and terminate at the new Orefield substation; extend lines approximately 1.2 miles on separate pole lines; estimated $17.2 M (s3801.3)p. 17
Siegfried - Wescosville #1 & #2 138kV linesBifurcate and terminate at Orefield; extend lines approximately 1.8 miles on separate double circuit pole lines; estimated $14.4 M (s3801.4)p. 17
Wescosville - Allentown #1 & #2 138kV linesBifurcate and terminate at Orefield; extend lines approximately 0.3 miles; estimated $2.4 M (s3801.5)p. 17
Orefield customer 138kV lead linesSix 138kV lead lines for approximately 0.75 miles to the customer facility; estimated $9 M (s3801.6)p. 17
Wescosville 500-138kV transformer #2Connect the on-site spare 500-138kV transformer into a new GIS bay and tie to the 138kV bus; estimated $5 M (s3801.7)p. 17
Wescosville 138kV yardRebuild the 138kV yard in a BAAH configuration and re-terminate the 138kV lines and transformer connections; estimated $35 M (s3801.8)p. 17

Details as printed

Need presentedNeed Meeting 05/06/2025, under the title Orefield, PAp. 5
Project driverCustomer Servicep. 16
Customer request, AllentownFacility served from a 138kV source in Allentown, PA; approximately 1000 MW total (2031); requested in service 10/2026p. 16
Load ramp75 MW initial in-service 2026; 450 MW projected 2028; 920 MW projected 2030p. 16
First solutionSolution Meeting TEAC 06/05/2025p. 6
Cost, June 2025$159 Mp. 6
In-service, June 202505/30/2028p. 6
Revised solutionSolution Meeting TEAC 11/04/2025p. 4
Added, November 2025Wescosville 138kV yard rebuild in a BAAH configuration, estimated $35 Mp. 4
Cost, November 2025$194 Mp. 4
Alternative consideredBreak the Susquehanna - Wescosville 500kV and install a 500kV-138kV substation with four 500-138kV transformers, extend a new 500kV line from the Alburtis 500kV yard to the new Orefield substation (~20 miles), and extend six 138kV lines to the new customer substation; estimated $359 Millionp. 17

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
May 6, 2025Item 07 - PPL Supplemental Projects PDFOrefield, PA not printed10/2026Need Meeting 05/06/2025
June 5, 2025Item 05 - PPL Supplemental Projects PDFOrefield, PA $159 M05/30/2028Conceptual
November 4, 2025Item 08 - PPL Supplemental Projects PDFPPL Transmission Zone: Supplemental Orefield, PA $194 M05/31/2028Conceptual
October 6, 2026Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 PDFOrefield, PA $194 M05/31/2028Conceptual
Date not printedPPL&nbsp PDFOrefield, PA $194 M05/31/2028Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.