Orefield, PA. Presented by PPL in PJM planning materials (PPL zone, PA).
Profile
PPL included this customer service project in its 2026 Local Plan submission (stage date March 13, 2026), shown to PJM's Transmission Expansion Advisory Committee in October 2026, at a transmission cost estimate of $194 million and a projected in-service date of May 31, 2028. (p. 17, p. 16) The need, presented in May 2025 under the title Orefield, PA, is a customer request to serve a facility from a 138kV source in Allentown, Pennsylvania, with a total load of approximately 1000 MW by 2031 and a requested in-service date of October 2026. (p. 5, p. 16) PPL lists the load ramping from 75 MW at initial in-service in 2026 to 450 MW in 2028 and 920 MW in 2030. (p. 16) The plan centers on a new Orefield 500-138kV substation: a three-bay 500kV yard with two 500-138kV transformers ($71 million) and an eight-bay 138kV yard ($40 million), cut into the Susquehanna - Wescosville 500kV line over approximately 1.2 miles at $17.2 million and into the Siegfried - Wescosville and Wescosville - Allentown #1 & #2 138kV lines. (p. 17) Six 138kV lead lines of approximately 0.75 miles run to the customer facility ($9 million), and PPL also connects a spare 500-138kV transformer at Wescosville ($5 million) and rebuilds the Wescosville 138kV yard ($35 million). (p. 17) At the first solution meeting in June 2025 the estimate was $159 million with in-service on May 30, 2028; the Wescosville 138kV yard rebuild first appears at a second solution meeting in November 2025, where the estimate is $194 million and in-service May 31, 2028. (p. 6, p. 4, p. 17) PPL lists one alternative, which added a new 500kV line of about 20 miles from Alburtis, at an estimated $359 million, and lists the project status as Conceptual. (p. 17)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Orefield 500-138kV substation | New three bay BAAH 500kV yard with two 500-138kV transformers and one 144MVAR capacitor bank; estimated $71 M (s3801.1) | p. 17 |
| Orefield 138kV yard | Eight bay BAAH 138kV yard with two 44MVAR capacitor banks; estimated $40 M (s3801.2) | p. 17 |
| Susquehanna - Wescosville 500kV line | Bifurcate and terminate at the new Orefield substation; extend lines approximately 1.2 miles on separate pole lines; estimated $17.2 M (s3801.3) | p. 17 |
| Siegfried - Wescosville #1 & #2 138kV lines | Bifurcate and terminate at Orefield; extend lines approximately 1.8 miles on separate double circuit pole lines; estimated $14.4 M (s3801.4) | p. 17 |
| Wescosville - Allentown #1 & #2 138kV lines | Bifurcate and terminate at Orefield; extend lines approximately 0.3 miles; estimated $2.4 M (s3801.5) | p. 17 |
| Orefield customer 138kV lead lines | Six 138kV lead lines for approximately 0.75 miles to the customer facility; estimated $9 M (s3801.6) | p. 17 |
| Wescosville 500-138kV transformer #2 | Connect the on-site spare 500-138kV transformer into a new GIS bay and tie to the 138kV bus; estimated $5 M (s3801.7) | p. 17 |
| Wescosville 138kV yard | Rebuild the 138kV yard in a BAAH configuration and re-terminate the 138kV lines and transformer connections; estimated $35 M (s3801.8) | p. 17 |
Details as printed
| Need presented | Need Meeting 05/06/2025, under the title Orefield, PA | p. 5 |
|---|---|---|
| Project driver | Customer Service | p. 16 |
| Customer request, Allentown | Facility served from a 138kV source in Allentown, PA; approximately 1000 MW total (2031); requested in service 10/2026 | p. 16 |
| Load ramp | 75 MW initial in-service 2026; 450 MW projected 2028; 920 MW projected 2030 | p. 16 |
| First solution | Solution Meeting TEAC 06/05/2025 | p. 6 |
| Cost, June 2025 | $159 M | p. 6 |
| In-service, June 2025 | 05/30/2028 | p. 6 |
| Revised solution | Solution Meeting TEAC 11/04/2025 | p. 4 |
| Added, November 2025 | Wescosville 138kV yard rebuild in a BAAH configuration, estimated $35 M | p. 4 |
| Cost, November 2025 | $194 M | p. 4 |
| Alternative considered | Break the Susquehanna - Wescosville 500kV and install a 500kV-138kV substation with four 500-138kV transformers, extend a new 500kV line from the Alburtis 500kV yard to the new Orefield substation (~20 miles), and extend six 138kV lines to the new customer substation; estimated $359 Million | p. 17 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| May 6, 2025 | Item 07 - PPL Supplemental Projects PDF | Orefield, PA | not printed | 10/2026 | Need Meeting 05/06/2025 |
| June 5, 2025 | Item 05 - PPL Supplemental Projects PDF | Orefield, PA | $159 M | 05/30/2028 | Conceptual |
| November 4, 2025 | Item 08 - PPL Supplemental Projects PDF | PPL Transmission Zone: Supplemental Orefield, PA | $194 M | 05/31/2028 | Conceptual |
| October 6, 2026 | Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 PDF | Orefield, PA | $194 M | 05/31/2028 | Conceptual |
| Date not printed | PPL  PDF | Orefield, PA | $194 M | 05/31/2028 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Orefield (PPL): described as new
- Alburtis (PPL)
- Allentown (PPL)
- Siegfried (PPL)
- Susquehanna (PPL): expansion described
- Wescosville (PPL)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- PPL plans new lines and substation, Switchgear Magazine, February 18, 2026. Switchgear Magazine, citing WFMZ, reported that PPL plans a new substation north of Huckleberry Road in South Whitehall Township, Lehigh County, beside its Susquehanna-Wescosville line, with three new lines running about 1.5 miles east to a new customer facility PPL did not name.
Not printed
- The decks name the customer only as a customer; they do not say what the facility is or who it is.
- No county or township is printed; Allentown, PA is the only location given for the customer site. South Whitehall Township comes only from the press.
- The May 2025 need meeting printed no cost or solution.
- The 2026 SRRTEP local plan PDF (0353c263...) prints the same Orefield slides as the cited October 2026 TEAC copy, so it is not cited separately.
- PPL-2026-0056 (Tamarack) bifurcates the Susquehanna - Wescosville (Orefield) 500kV line into a new Sandy Run switchyard; it is a separate, already-recorded program and not a member.
- No news article from a primary local outlet (WFMZ, Lehigh Valley News, The Morning Call) could be opened; only the Switchgear Magazine rewrite is listed.