ATSI Cluster 2

Cluster 2 (ATSI). Presented by PJM in PJM planning materials (ATSI zone, Ohio).

$217.32Mcost estimate as printed p. 52
6/1/2029projected in service p. 52
Second Readstatus as printed p. 49

Profile

Cluster 2 (ATSI) is a set of overloads in the ATSI zone that PJM put out for proposals in its 2024 RTEP Window 1: in the 2029 summer case, multiple 138 kV lines and two 345 kV lines are overloaded for N-2 contingency pairs. (p. 32, p. 49) Six proposals were submitted, and five of them were new 345 kV lines ending at Lake Ave, including ATSI's approximately 88-mile Lemoyne - Lake Avenue line and a 79-mile Fostoria Central - Lake Ave double circuit line proposed by TRNSRC. (p. 91, p. 32) PJM short-listed three options: ATSI's 138 kV rebuild (proposal 605, $265.1 million), ATSI's Lemoyne - Lake Ave 345 kV line (proposal 843, $455.0 million) and NEETMH's Lemoyne - Lake Ave line (proposal 533, $202.0 million). (p. 59, p. 91) PJM recommended proposal 605 in revised form, which rebuilds the Avery - Shinrock, Greenfield - Lakeview and Avery - Hayes 138 kV lines and the 32-mile Greenfield - Beaver 138 kV corridor, at a total estimated cost of $217.32 million and a projected in-service date of June 1, 2029. (p. 51, p. 52) The largest component is the Greenfield - Beaver corridor at $131.43 million, which PJM says carries multiple 138 kV lines on common towers. (p. 51) PJM presented a modified version of proposal 605 at First Read and the revised version at Second Read in January 2025, and lists the rebuild as upgrading lines built 70-100 years ago. (p. 72, p. 49, p. 1, p. 52)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Avery - Shinrock 138 kV line (b3925.1)Rebuild 7.46 miles; $15.2Mp. 51
Greenfield - Lakeview 138 kV line (b3925.2)Rebuild 13.45 miles; $59.68Mp. 51
Avery - Hayes 138 kV line (b3925.3)Rebuild 6.5 miles; $11.01Mp. 51
Greenfield - Beaver 138 kV corridor (b3925.4)Rebuild 32 miles of corridor carrying multiple 138 kV lines on common towers; $131.43Mp. 51

Details as printed

Recommended solutionProposal #605 (Revised)p. 51
Earlier stageFirst Read, with Proposal #605 (Modified) as the proposed solutionp. 72
Problem statement2029 RTEP summer case: multiple 138 kV lines and two 345 kV lines overloaded for N-2 contingency pairsp. 49
WindowProposals submitted in the 2024 RTEP Window 1p. 32
Short listOption 1: proposal 605 ($265.1M); Option 2: proposal 843 ($455.0M); Option 3: proposal 533 ($202.0M)p. 59
Proposal 605 (ATSI)ATSI 138kV Rebuild; proposal estimate $265,156,487.00, independent estimate $266,273,438.00p. 91
Proposal 843 (ATSI)Lemoyne - Lake Ave 345 kV Line; proposal estimate $455,038,571.00, independent estimate $468,122,679.45p. 91
Proposal 843 scopeA new approximately 88 mile Lemoyne - Lake Avenue 345 kV linep. 32
Proposal 694 (TRNSRC)Fostoria Central - Lake Ave. 345 kV DC; proposal estimate $328,369,046.00, independent estimate $448,294,086.49p. 91
Proposal 694 scopeA new 79 mile 345kV double circuit line from Fostoria Central to Lake Avenuep. 32
Proposal 533 (NEETMH)Lemoyne - Lake Ave 345kV; proposal estimate $202,084,415.75, independent estimate $344,156,240.59p. 91
Proposal 294 (NEETMH)Bay Shore - Davis-Besse - Lake Ave; proposal estimate $257,300,886.58, independent estimate $369,256,820.42p. 91
Proposal 357 (NEETMH)Bay Shore - Davis-Besse - Lake Ave + Lemoyne - Lake Ave 345kV; proposal estimate $344,117,143.00, independent estimate $451,938,163.29p. 91
Additional benefits citedUpgrades lines built 70-100 years agop. 52

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 6, 2024Item 13 - Reliability Analysis Update PDFCluster 2 (ATSI) not printednot printedShort List
November 19, 2024Item 1 - Reliability Analysis Update PDFRebuild/Reconductor existing 138 kV lines/Terminal upgrades at 345 kV substations 265.1not printed
January 7, 2025Item 12 - Reliability Analysis Update PDFCluster 2 (ATSI) $217.32M6/1/2029Second Read

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.