Ohio Seven Year Solution (765 kV)

Ohio Seven Year Solution. Presented by PJM in PJM planning materials (AEP/ATSI/DAYTON/DEOK zone).

$2,768.0Mcost estimate as printed p. 47
Listed per componentprojected in service p. 47
Recommended (2nd read)status as printed p. 44

Profile

PJM staff presented this selection to the Transmission Expansion Advisory Committee as a second read on January 6, 2026, at an estimated cost of $2,768.0 million, with a required in-service date of June 1, 2030. (p. 1, p. 44, p. 47) It is a modified version of Transource/FE proposal 2025-W1-570, which the proposer titled the Ohio Seven Year Solution, chosen from 29 proposals to address load increases in the Columbus and Melissa areas. (p. 60, p. 79, p. 91, p. 44) PJM's independent cost estimate for the selected portfolio is $3,410.66 million, and PJM described it as about $600 million less than the runner-up, proposal 152, on independent cost. (p. 60, p. 111) The largest piece is a 137-mile 765 kV line from the existing Greentown substation to a new Teddy 765/345 kV substation, at a proposed cost of $633.79 million. (p. 48, p. 60) From Teddy, a 35.4-mile 765 kV line runs to the existing Marysville substation; a second chain of 765 kV lines links Guernsey, Conesville, a new West Millersport yard and Adkins. (p. 49, p. 51, p. 52, p. 54) As submitted, the proposal listed 291.5 miles of new 765 kV line and 35 miles of new 345 kV line, 277.4 miles of it greenfield. (p. 79, p. 48) Projected in-service dates are listed per component, the latest being October 1, 2032 for a transformer at Marysville. (p. 47, p. 49)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Greentown 765 kV stationNew 765 kV line position, three 100 Mvar reactors, two 765 kV breakers; $45,294,123, projected 10/31/2031p. 48
Greentown - Teddy 765 kV lineProposed cost $633.79 M; independent estimate $863.10 Mp. 60
Teddy 765/345 kV station (new)New greenfield substation: nine 765 kV breakers, two 765/345 kV 2250 MVA transformers, nine 345 kV breakers; $222,773,008, projected 10/31/2030p. 48
Teddy - Marysville 765 kV lineProposed cost $176.46 M; independent estimate $223.02 Mp. 60
Marysville 765 kV stationStation upgrade; proposed cost $281.83 M; independent estimate $309.52 Mp. 60
Teddy - Beatty 345 kV double circuitProposed cost $175.19 M; independent estimate $246.46 Mp. 60
Guernsey - Conesville 765 kV lineNew 32-mile single circuit 765 kV line; $166,168,865p. 51
West Millersport 765 kV yard (new)New 765 kV yard, four breakers, one 765/345 kV 2250 MVA transformer; $118,108,319p. 51
West Millersport - Adkins 765 kV lineNew 38-mile single circuit 765 kV line; $201,833,315, projected 10/31/2031p. 52
Conesville 765 kV stationStation expansion; proposed cost $140.97 M; independent estimate $150.86 Mp. 60
Conesville - West Millersport 765 kV lineNew 49.1-mile single circuit 765 kV line; $243,654,861p. 54
Adkins 765 kV yard765 kV yard, seven 765 kV breakers, three 100 MVar reactors on each 765 kV line; $102,977,072, projected 10/31/2031p. 54

Details as printed

DeveloperTransource/FEp. 60
Independent cost$3,410.66 M independent cost estimate, against $2,768.00 M proposedp. 60
Required in service6/1/2030p. 47
First readProposed solutions, first readp. 87
First read cost$2,768.00 M proposed, $3,410.66 M independent estimatep. 127
SubmittedAs submitted: $2,775.19 M proposed, $3,418.68 M independent estimate, proposed in service 10/1/2031; new line miles 291.5 and 35 by voltage column, 326.5 total, 277.4 greenfieldp. 79
ShortlistRanked first of three on the November shortlist, ahead of proposals 152 and 239p. 113
Proposals29 proposals from five proposing entitiesp. 91
Selection reasonAbout $600M less than proposal 152 based on independent costp. 111
Selection riskLower constructability and regulatory risk and higher use of existing rights of wayp. 111
DriversLoad increase in the Columbus area and at the Melissa areap. 44
ViolationsThermal overloads in AEP/Dayton/ATSI; widespread voltage issues in AEP/Dayton/ATSI/DEOKp. 44
Greentown teddy length137 miles totalp. 48
Greentown teddy aep60 miles (AEP portion)p. 48
Greentown teddy dayton49.92 miles (DAYTON portion)p. 48
Greentown teddy atsi27.08 miles (ATSI portion)p. 48
Teddy marysville length35.4 milesp. 49
Latest component isdMarysville 765/345 kV transformer, projected in service 10/1/2032p. 49

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 16 - Reliability Analysis Update PDF2025-W1-570 not printednot printed
December 8, 2025Item 11 - Reliability Analysis Update PDFWest Regional Cluster Solution - Transource/FE Proposal 2025-W1-570 (Modified) not printed10/31/2031
January 6, 2026Item 09 - Reliability Analysis Update PDFWest Cluster Recommended Selection (2nd Read) $2,768.0M10/1/2032Recommended Solution

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.