Ohio Seven Year Solution (765 kV)
Ohio Seven Year Solution. Presented by PJM in PJM planning materials (AEP/ATSI/DAYTON/DEOK zone).
Profile
PJM staff presented this selection to the Transmission Expansion Advisory Committee as a second read on January 6, 2026, at an estimated cost of $2,768.0 million, with a required in-service date of June 1, 2030. (p. 1, p. 44, p. 47) It is a modified version of Transource/FE proposal 2025-W1-570, which the proposer titled the Ohio Seven Year Solution, chosen from 29 proposals to address load increases in the Columbus and Melissa areas. (p. 60, p. 79, p. 91, p. 44) PJM's independent cost estimate for the selected portfolio is $3,410.66 million, and PJM described it as about $600 million less than the runner-up, proposal 152, on independent cost. (p. 60, p. 111) The largest piece is a 137-mile 765 kV line from the existing Greentown substation to a new Teddy 765/345 kV substation, at a proposed cost of $633.79 million. (p. 48, p. 60) From Teddy, a 35.4-mile 765 kV line runs to the existing Marysville substation; a second chain of 765 kV lines links Guernsey, Conesville, a new West Millersport yard and Adkins. (p. 49, p. 51, p. 52, p. 54) As submitted, the proposal listed 291.5 miles of new 765 kV line and 35 miles of new 345 kV line, 277.4 miles of it greenfield. (p. 79, p. 48) Projected in-service dates are listed per component, the latest being October 1, 2032 for a transformer at Marysville. (p. 47, p. 49)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Greentown 765 kV station | New 765 kV line position, three 100 Mvar reactors, two 765 kV breakers; $45,294,123, projected 10/31/2031 | p. 48 |
| Greentown - Teddy 765 kV line | Proposed cost $633.79 M; independent estimate $863.10 M | p. 60 |
| Teddy 765/345 kV station (new) | New greenfield substation: nine 765 kV breakers, two 765/345 kV 2250 MVA transformers, nine 345 kV breakers; $222,773,008, projected 10/31/2030 | p. 48 |
| Teddy - Marysville 765 kV line | Proposed cost $176.46 M; independent estimate $223.02 M | p. 60 |
| Marysville 765 kV station | Station upgrade; proposed cost $281.83 M; independent estimate $309.52 M | p. 60 |
| Teddy - Beatty 345 kV double circuit | Proposed cost $175.19 M; independent estimate $246.46 M | p. 60 |
| Guernsey - Conesville 765 kV line | New 32-mile single circuit 765 kV line; $166,168,865 | p. 51 |
| West Millersport 765 kV yard (new) | New 765 kV yard, four breakers, one 765/345 kV 2250 MVA transformer; $118,108,319 | p. 51 |
| West Millersport - Adkins 765 kV line | New 38-mile single circuit 765 kV line; $201,833,315, projected 10/31/2031 | p. 52 |
| Conesville 765 kV station | Station expansion; proposed cost $140.97 M; independent estimate $150.86 M | p. 60 |
| Conesville - West Millersport 765 kV line | New 49.1-mile single circuit 765 kV line; $243,654,861 | p. 54 |
| Adkins 765 kV yard | 765 kV yard, seven 765 kV breakers, three 100 MVar reactors on each 765 kV line; $102,977,072, projected 10/31/2031 | p. 54 |
Details as printed
| Developer | Transource/FE | p. 60 |
|---|---|---|
| Independent cost | $3,410.66 M independent cost estimate, against $2,768.00 M proposed | p. 60 |
| Required in service | 6/1/2030 | p. 47 |
| First read | Proposed solutions, first read | p. 87 |
| First read cost | $2,768.00 M proposed, $3,410.66 M independent estimate | p. 127 |
| Submitted | As submitted: $2,775.19 M proposed, $3,418.68 M independent estimate, proposed in service 10/1/2031; new line miles 291.5 and 35 by voltage column, 326.5 total, 277.4 greenfield | p. 79 |
| Shortlist | Ranked first of three on the November shortlist, ahead of proposals 152 and 239 | p. 113 |
| Proposals | 29 proposals from five proposing entities | p. 91 |
| Selection reason | About $600M less than proposal 152 based on independent cost | p. 111 |
| Selection risk | Lower constructability and regulatory risk and higher use of existing rights of way | p. 111 |
| Drivers | Load increase in the Columbus area and at the Melissa area | p. 44 |
| Violations | Thermal overloads in AEP/Dayton/ATSI; widespread voltage issues in AEP/Dayton/ATSI/DEOK | p. 44 |
| Greentown teddy length | 137 miles total | p. 48 |
| Greentown teddy aep | 60 miles (AEP portion) | p. 48 |
| Greentown teddy dayton | 49.92 miles (DAYTON portion) | p. 48 |
| Greentown teddy atsi | 27.08 miles (ATSI portion) | p. 48 |
| Teddy marysville length | 35.4 miles | p. 49 |
| Latest component isd | Marysville 765/345 kV transformer, projected in service 10/1/2032 | p. 49 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 16 - Reliability Analysis Update PDF | 2025-W1-570 | not printed | not printed | |
| December 8, 2025 | Item 11 - Reliability Analysis Update PDF | West Regional Cluster Solution - Transource/FE Proposal 2025-W1-570 (Modified) | not printed | 10/31/2031 | |
| January 6, 2026 | Item 09 - Reliability Analysis Update PDF | West Cluster Recommended Selection (2nd Read) | $2,768.0M | 10/1/2032 | Recommended Solution |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Teddy (AEP): described as new
- Teddy (PJM system-wide): described as new
- West Millersport (AEP): described as new
- Adkins (AEP): expansion described
- Adkins (PJM system-wide): expansion described
- Allen (AEP): expansion described
- Allen (PJM system-wide)
- Beatty (AEP)
- Beatty (PJM system-wide)
- Bethel (AEP)
- Bethel (PJM system-wide)
- Bixby (AEP)
- Bixby (PJM system-wide)
- Cole (AEP)
- Cole (PJM system-wide)
- Conesville (AEP): expansion described
- Conesville (PJM system-wide): expansion described
- Fifth Avenue (PJM system-wide)
- Greentown (AEP)
- Greentown (PJM system-wide)
- Guernsey (AEP)
- Guernsey (PJM system-wide)
- Hayden (AEP)
- Hayden (PJM system-wide)
- Hess (AEP)
- Hess (PJM system-wide)
- Hyatt (AEP)
- Hyatt (PJM system-wide)
- Kenny (PJM system-wide)
- Kirk (AEP)
- Kirk (PJM system-wide)
- Maliszewski (AEP): expansion described
- Maliszewski (PJM system-wide)
- Marysville (AEP)
- Marysville (PJM system-wide)
- Meadow Lake (AEP)
- Meadow Lake (PJM system-wide)
- Newark Center (AEP)
- Newark Center (PJM system-wide)
- Ohio Central (AEP)
- Ohio Central (PJM system-wide)
- OSU (AEP)
- OSU (PJM system-wide)
- Roberts (PJM system-wide)
- South Kenton (AEP)
- South Kenton (PJM system-wide)
- West Millersport (PJM system-wide): expansion described
- Wilson (PJM system-wide)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- PJM board approves $11.8B transmission expansion plan, Utility Dive, February 17, 2026. Utility Dive reported that the PJM board approved the 2025 transmission plan, including what it described as a $1.1 billion central Ohio project with 300 miles of 765-kV lines proposed by Grid Growth Ventures, a joint venture of Transource Energy and FirstEnergy Transmission.
- FirstEnergy Transmission and Transource Energy Joint Venture Receives Approval for Transmission Project in Central Ohio, T&D World, February 17, 2026. T&D World reported that the PJM Board of Managers approved the joint FirstEnergy Transmission and Transource proposal on Feb. 12, 2026, describing more than 300 miles of new 765-kV lines and substation upgrades to be developed through Grid Growth Ventures.
- Miami County board fights 190-mile transmission line proposal, WHIO, August 20, 2026. WHIO reported that the Miami County Board of Commissioners formally opposed routing Grid Growth Ventures' proposed 765-kilovolt line, which it described as about 190 miles across western and central Ohio, through the county, while the developer was still finalizing a route.
- Union County landowners worry proposed transmission line could cut through farms and woods, WSYX ABC6, October 20, 2026. ABC6 reported on Union County landowners' concerns about Grid Growth Ventures' proposed Thistlewood-Marysville 765-kV line, described as about 35 miles through Union and Clark counties, and said the Ohio Power Siting Board application was not expected until spring.
Not printed
- No state is printed for any station or line in the West cluster slides; Ohio appears only in the proposal name.
- No county is printed for Teddy, West Millersport, Adkins or Conesville.
- The slides do not say what the Columbus-area or Melissa-area load is.
- Within the January 6, 2026 deck, Conesville - West Millersport 765 kV is $243,654,861 on the component slide (p. 54) and $248.98 M on the cost summary (p. 60); both are printed.
- No PJM Board approval is in the archived documents.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.