Dominion 2025 Window 1 Portfolio (2025-W1-275)
Regional Solution: 2025-W1-275 Portfolio. Presented by PJM in PJM planning materials (Dominion zone, VA (Chesterfield and Dinwiddie County, for the Carson - Midlothian rebuild)).
Profile
This is a portfolio, not a single line: Dominion's proposal 2025-W1-275, which PJM presented to its Transmission Expansion Advisory Committee on January 6, 2026 as a recommended regional solution at a total of $4,832.45 million, with a projected in-service date of June 1, 2032. (p. 1, p. 59, p. 27, p. 38) Its largest component is a new bipolar +/- 525kV HVDC link between Heritage and Mosby substations with a capability of 3000MW, listed at $3790.85 million including converter stations at both ends. (p. 38, p. 28) The rest is 500 kV work in Virginia: a new 765/500kV Vontay switching station, a new Elmont - Kraken 500kV line of approximately 31 miles, rebuilds of lines 576, 539, 563 and 560, and terminal and breaker upgrades. (p. 34, p. 28, p. 36, p. 41) PJM's problem statement is generator deliverability: various Dominion 500kV lines overloaded in the 2032 RTEP cases, and PJM called the HVDC proposal the technically superior solution while noting it was approximately $2Bn more expensive than Transource proposal #331. (p. 27, p. 72) The portfolio total was printed as $4819.51 million on the November 2025 short-list and $4817.73 million at the December 2025 first read; the second-read table in January added $13.0 million of breaker upgrades. (p. 82, p. 74, p. 28) Valley Link's relocation of Yeat substation, presented after the selection, reached into this portfolio: the 765 kV loop into Vontay (b4053.16) and the Kraken line terminal (b4053.10) were cancelled, the Vontay estimate was printed as $217.76 million followed by $80.0 million, and new IDs b4053.34 and b4053.35 were added. (p. 20, p. 21) PJM's later 2025W1 references describe the HVDC link (b4053.3) as awarded, with operational measures used until it goes into service in 2032. (p. 7)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Line 576 rebuild, Vontay - Midlothian (500 kV) | Partial rebuild of line 576, Vontay to Midlothian; $104.86M | p. 28 |
| Line 539 rebuild, Yeat - Ox (500 kV) | Rebuild of line 539, Yeat to Ox; $125.25M | p. 28 |
| Line 567 terminal upgrades, Chickahominy and Surry | $2.49M | p. 28 |
| Line 563 rebuild, Carson - Midlothian (500 kV) | Rebuild of line 563, Carson to Midlothian; $237.06M | p. 28 |
| Carson 500kV substation equipment | $12.44M | p. 28 |
| Vontay switching station, component total | $248.69M | p. 28 |
| Vontay 765/500kV switching station (new) | New 765/500kV Vontay switching station with one 765/500kV transformer; $217.759 for this item (b4053.13) | p. 34 |
| Line 5008 cut-in to Mosby | $16.25M | p. 28 |
| Elmont - Kraken 500 kV line (new) | New 500kV line, Elmont to Kraken; $162.50M | p. 28 |
| Line 576 rebuild, North Anna - Vontay (500 kV) | $104.86M | p. 28 |
| Heritage - Mosby HVDC link (new) | Bipolar +/- 525kV HVDC link, capability 3000MW; $2271.696M for the link | p. 38 |
| Heritage HVDC converter station (new) | Voltage Source Converter station at Heritage; $773.733M | p. 38 |
| Mosby HVDC converter station (new) | Voltage Source Converter station at Mosby; $745.422M | p. 38 |
| HVDC link, component total | $3790.85M | p. 28 |
| Line 560 rebuild, Possum Point - Burches Hill | Rebuild of line 560, Possum Point to Burches Hill; $14.21M | p. 28 |
| Breaker upgrades, Clifton, Elmont, Celestial | Breaker replacements at Clifton, Elmont and Celestial; $13.0M | p. 41 |
Details as printed
| Proposing entity | Dominion Portfolio Proposal 2025-W1-275, South Regional Cluster | p. 59 |
|---|---|---|
| Problem statement | Generator deliverability: various Dominion 500kV lines overloaded under single and common mode contingencies in the 2032 RTEP summer, winter and light load cases | p. 27 |
| Why PJM chose it | PJM recommended HVDC-based Proposal #275 as the technically superior solution, offering 500 ~ 1000 MWs higher South - North transfer capability and lower area impact than a 765 kV overhead solution | p. 72 |
| Cost against the runner-up | About $2Bn more than Transource proposal #331; preliminary cost allocation shows the Dominion Zone carrying about 50% of the cost | p. 72 |
| Short-list, November 2025 | Portfolio 1A, 2025-W1-275: $4819.51 M | p. 82 |
| First read, December 2025 | Portfolio component table total: $4817.73M | p. 74 |
| Vontay, December 2025 | New 765/500kV Switching Station - Vontay: $239.49M at first read | p. 74 |
| Elmont - Kraken, December 2025 | New 500kV Line - Elmont to Kraken: $180.30M at first read | p. 74 |
| Breaker upgrades added at second read | Breaker Upgrades line ($13.0M) in the component table, which totals $4832.45M | p. 28 |
| HVDC link in later planning | PJM's 2031 RTEP analysis included Dominion's HVDC link (b4053.3) awarded from 2025W1, which resolved all 230kV thermal overloads; operational measures until it goes into service in 2032 | p. 7 |
| Additional HVDC benefits | PJM lists additional benefits including 1000 MVAR of reactive support at each end and headroom on existing lines raised from under 10% to 35% | p. 42 |
| Yeat relocation: Vontay rescoped, May 2026 | Vontay (b4053.13) rescoped to sit at the crossing of line No. 553 and line No. 576; estimate printed as $217.76 M followed by $80.0M | p. 20 |
| Yeat relocation: 765 kV line no longer passes Vontay | Yeat relocated about 15 miles south; the Joshua Falls - Yeat 765kV line will no longer pass by Vontay | p. 18 |
| Yeat relocation: 2025 Window 1 items cancelled | Cancelled: the Joshua Falls - Yeat 765 kV loop into Vontay (b4053.16, $8.36M) and the Kraken 500kV line terminal (b4053.10, $8.609M) | p. 20 |
| Yeat relocation: new b4053 IDs | New baseline projects b4053.34 (Kraken bypass, $1M) and b4053.35 (rebuild about 11 miles of Line #594 Spotsylvania to Culpeper Yeat, $67.03M) | p. 21 |
| Yeat relocation: Yeat - Ox rebuild becomes Bristers - Ox | Line No. 539 rebuild (b4053.23) changed from Yeat - Ox to Bristers - Ox, about 23 miles, no cost change ($122.66M) | p. 20 |
| Thornburg bypass re-designated, October 2026 | b4053.34 (bypass at Thornburg, $1M) moved from Dominion to Valley Link Transmission as designated entity | p. 9 |
| Elmont - Kraken length | New 500kV line from Elmont to Kraken, approximately 31 miles | p. 36 |
| Burches Hill work (PEPCO scope) | Burches Hill terminal uprate, $10.315M, listed as PEPCO scope | p. 39 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 16 - Reliability Analysis Update PDF | 2025-W1-275 | not printed | not printed | |
| December 8, 2025 | Item 11 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio | not printed | 6/1/2032 | First Read |
| January 6, 2026 | Item 09 - Reliability Analysis Update PDF | Regional Solution: 2025-W1-275 Portfolio | $4832.45 | 6/1/2032 | Recommended Solution |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Thornburg (DOM): described as new
- Vontay (DOM): described as new
- Wishing Star (DOM): described as new
- Yeat (DOM): described as new
- Burches Hill (DOM)
- Carson (DOM)
- Celestial (DOM)
- Chickahominy (DOM)
- Clifton (DOM)
- Cunningham (DOM)
- Elmont (DOM)
- Heritage (DOM): expansion described
- Midlothian (DOM)
- Mosby (DOM)
- North Anna (DOM): expansion described
- Possum Point (DOM)
- Surry (DOM)
- Vint Hill (DOM): expansion described
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- PJM board approves $11.8B transmission expansion plan, Utility Dive, February 17, 2026. Utility Dive reported that PJM's board approved an $11.8 billion transmission plan in which Dominion's Virginia utility will build about $4.8 billion of projects, including a $2.3 billion, 185-mile underground 525-kV line and two converter stations of about $1.5 billion, set to be online by June 2032 and designed to deliver 3,000 MW into Loudoun County.
Not printed
- PJM's materials print no program name beyond "2025-W1-275 Portfolio"; Dominion's own name for the HVDC line (Commonwealth Energy Express, on its project pages) does not appear in any archived PJM document.
- No board approval date is printed in the PJM documents cited here; later slides describe the HVDC link as "awarded from 2025W1". Utility Dive reported the board approval.
- No updated portfolio total is printed after January 2026; the May 2026 Yeat relocation slides print component changes (the Vontay estimate printed as $217.76M followed by $80.0M, two cancellations, two new IDs) and a total cost savings for the whole relocation package, not a new 2025-W1-275 total.
- No county is printed for Heritage, Mosby, Vontay or Kraken; the only county printed on these pages is Chesterfield and Dinwiddie County, VA (Carson - Midlothian). Burches Hill work is labeled PEPCO scope, but no state is printed for it.
- No project status such as Engineering or Construction is printed for the portfolio components.
- Tracked row id:b4053.34 (Thornburg bypass, October 2026) is not a member: it is printed under Proposal 2024-W1-820 (Valley Link) and was re-designated to Valley Link Transmission. Valley Link's own members (b4000.x rows) are not included here.
- The breaker-upgrade slide lists Clifton in its bullets but "Clinton" in its rating table; the record follows the bullets.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.