Dominion 2025 Window 1 Portfolio (2025-W1-275)

Regional Solution: 2025-W1-275 Portfolio. Presented by PJM in PJM planning materials (Dominion zone, VA (Chesterfield and Dinwiddie County, for the Carson - Midlothian rebuild)).

$4,832.45Mcost estimate as printed p. 59
6/1/2032projected in service p. 38
Recommended Solutionstatus as printed p. 27

Profile

This is a portfolio, not a single line: Dominion's proposal 2025-W1-275, which PJM presented to its Transmission Expansion Advisory Committee on January 6, 2026 as a recommended regional solution at a total of $4,832.45 million, with a projected in-service date of June 1, 2032. (p. 1, p. 59, p. 27, p. 38) Its largest component is a new bipolar +/- 525kV HVDC link between Heritage and Mosby substations with a capability of 3000MW, listed at $3790.85 million including converter stations at both ends. (p. 38, p. 28) The rest is 500 kV work in Virginia: a new 765/500kV Vontay switching station, a new Elmont - Kraken 500kV line of approximately 31 miles, rebuilds of lines 576, 539, 563 and 560, and terminal and breaker upgrades. (p. 34, p. 28, p. 36, p. 41) PJM's problem statement is generator deliverability: various Dominion 500kV lines overloaded in the 2032 RTEP cases, and PJM called the HVDC proposal the technically superior solution while noting it was approximately $2Bn more expensive than Transource proposal #331. (p. 27, p. 72) The portfolio total was printed as $4819.51 million on the November 2025 short-list and $4817.73 million at the December 2025 first read; the second-read table in January added $13.0 million of breaker upgrades. (p. 82, p. 74, p. 28) Valley Link's relocation of Yeat substation, presented after the selection, reached into this portfolio: the 765 kV loop into Vontay (b4053.16) and the Kraken line terminal (b4053.10) were cancelled, the Vontay estimate was printed as $217.76 million followed by $80.0 million, and new IDs b4053.34 and b4053.35 were added. (p. 20, p. 21) PJM's later 2025W1 references describe the HVDC link (b4053.3) as awarded, with operational measures used until it goes into service in 2032. (p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Line 576 rebuild, Vontay - Midlothian (500 kV)Partial rebuild of line 576, Vontay to Midlothian; $104.86Mp. 28
Line 539 rebuild, Yeat - Ox (500 kV)Rebuild of line 539, Yeat to Ox; $125.25Mp. 28
Line 567 terminal upgrades, Chickahominy and Surry$2.49Mp. 28
Line 563 rebuild, Carson - Midlothian (500 kV)Rebuild of line 563, Carson to Midlothian; $237.06Mp. 28
Carson 500kV substation equipment$12.44Mp. 28
Vontay switching station, component total$248.69Mp. 28
Vontay 765/500kV switching station (new)New 765/500kV Vontay switching station with one 765/500kV transformer; $217.759 for this item (b4053.13)p. 34
Line 5008 cut-in to Mosby$16.25Mp. 28
Elmont - Kraken 500 kV line (new)New 500kV line, Elmont to Kraken; $162.50Mp. 28
Line 576 rebuild, North Anna - Vontay (500 kV)$104.86Mp. 28
Heritage - Mosby HVDC link (new)Bipolar +/- 525kV HVDC link, capability 3000MW; $2271.696M for the linkp. 38
Heritage HVDC converter station (new)Voltage Source Converter station at Heritage; $773.733Mp. 38
Mosby HVDC converter station (new)Voltage Source Converter station at Mosby; $745.422Mp. 38
HVDC link, component total$3790.85Mp. 28
Line 560 rebuild, Possum Point - Burches HillRebuild of line 560, Possum Point to Burches Hill; $14.21Mp. 28
Breaker upgrades, Clifton, Elmont, CelestialBreaker replacements at Clifton, Elmont and Celestial; $13.0Mp. 41

Details as printed

Proposing entityDominion Portfolio Proposal 2025-W1-275, South Regional Clusterp. 59
Problem statementGenerator deliverability: various Dominion 500kV lines overloaded under single and common mode contingencies in the 2032 RTEP summer, winter and light load casesp. 27
Why PJM chose itPJM recommended HVDC-based Proposal #275 as the technically superior solution, offering 500 ~ 1000 MWs higher South - North transfer capability and lower area impact than a 765 kV overhead solutionp. 72
Cost against the runner-upAbout $2Bn more than Transource proposal #331; preliminary cost allocation shows the Dominion Zone carrying about 50% of the costp. 72
Short-list, November 2025Portfolio 1A, 2025-W1-275: $4819.51 Mp. 82
First read, December 2025Portfolio component table total: $4817.73Mp. 74
Vontay, December 2025New 765/500kV Switching Station - Vontay: $239.49M at first readp. 74
Elmont - Kraken, December 2025New 500kV Line - Elmont to Kraken: $180.30M at first readp. 74
Breaker upgrades added at second readBreaker Upgrades line ($13.0M) in the component table, which totals $4832.45Mp. 28
HVDC link in later planningPJM's 2031 RTEP analysis included Dominion's HVDC link (b4053.3) awarded from 2025W1, which resolved all 230kV thermal overloads; operational measures until it goes into service in 2032p. 7
Additional HVDC benefitsPJM lists additional benefits including 1000 MVAR of reactive support at each end and headroom on existing lines raised from under 10% to 35%p. 42
Yeat relocation: Vontay rescoped, May 2026Vontay (b4053.13) rescoped to sit at the crossing of line No. 553 and line No. 576; estimate printed as $217.76 M followed by $80.0Mp. 20
Yeat relocation: 765 kV line no longer passes VontayYeat relocated about 15 miles south; the Joshua Falls - Yeat 765kV line will no longer pass by Vontayp. 18
Yeat relocation: 2025 Window 1 items cancelledCancelled: the Joshua Falls - Yeat 765 kV loop into Vontay (b4053.16, $8.36M) and the Kraken 500kV line terminal (b4053.10, $8.609M)p. 20
Yeat relocation: new b4053 IDsNew baseline projects b4053.34 (Kraken bypass, $1M) and b4053.35 (rebuild about 11 miles of Line #594 Spotsylvania to Culpeper Yeat, $67.03M)p. 21
Yeat relocation: Yeat - Ox rebuild becomes Bristers - OxLine No. 539 rebuild (b4053.23) changed from Yeat - Ox to Bristers - Ox, about 23 miles, no cost change ($122.66M)p. 20
Thornburg bypass re-designated, October 2026b4053.34 (bypass at Thornburg, $1M) moved from Dominion to Valley Link Transmission as designated entityp. 9
Elmont - Kraken lengthNew 500kV line from Elmont to Kraken, approximately 31 milesp. 36
Burches Hill work (PEPCO scope)Burches Hill terminal uprate, $10.315M, listed as PEPCO scopep. 39

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 16 - Reliability Analysis Update PDF2025-W1-275 not printednot printed
December 8, 2025Item 11 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio not printed6/1/2032First Read
January 6, 2026Item 09 - Reliability Analysis Update PDFRegional Solution: 2025-W1-275 Portfolio $4832.456/1/2032Recommended Solution

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.