Tanners Creek - Hanna 345 kV

Tanners Creek - Hanna 345 kV line rebuild. Presented by AEP in PJM planning materials (AEP zone, IN).

$520 Mcost estimate as printed p. 74
10/15/2031projected in service p. 74
Scopingstatus as printed p. 74

Profile

AEP's local plan submission for 2026 lists a rebuild of the Tanners Creek - Hanna 345 kV circuit in Indiana at a transmission cost estimate of $520 million, with a projected in-service date of October 15, 2031 and a status of Scoping. (p. 1, p. 7, p. 72, p. 74) AEP presented the need to PJM's Transmission Expansion Advisory Committee in November 2025 and the solution in June 2026, then submitted it for inclusion in the Local Plan on September 25, 2026; the June 2026 and 2026 local plan slides both print $520 million and October 15, 2031. (p. 72, p. 74) The driver AEP lists is equipment condition: the Tanners Creek - Junction Tower section is 74.07 miles long, was originally installed in 1961, and carried 69 structure open conditions. (p. 3) AEP reports 313 structures, 311 of them from the original installation, and says a drone assessment of 30 structures found worn insulator attachment hardware on 87% of them. (p. 4) The proposed solution rebuilds about 73.9 miles from Tanners Creek to Junction Tower as single circuit and about 5.65 miles from Hanna to Junction Tower as double circuit. (p. 7) AEP says retiring the line is not an option because the MISO Tranche 2.1 project will loop Duke's Gwynneville and Batesville stations into it. (p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Tanners Creek - Junction Tower 345 kVRebuild ~73.9 miles as 345 kV single circuit, 2-bundle 954 ACSR 54/7 Cardinalp. 7
Hanna - Junction Tower 345 kVRebuild ~5.65 miles as double circuit, 2-bundle 954 ACSR 54/7 Cardinalp. 7

Details as printed

Previously presentedNeed Meeting 11/04/2025, Solution Meeting TEAC - 06/02/2026p. 72
Supplemental IDs3956.1p. 74
Project driverEquipment Condition/Performance/Riskp. 3
Line condition, Tanners Creek - Junction Tower74.07 miles, originally installed in 1961p. 3
Open conditions, Tanners Creek - Junction Tower69 structure open conditions; structures do not meet AEP and ASCE structural strength requirementsp. 3
Structure count313 structures, 311 from the original installationp. 4
Drone assessmentOvalization of insulator attachment hardware on 87% of 30 assessed structuresp. 4
Line condition, Hanna - Junction Tower5.63 miles, originally installed in 1962p. 4
Outage history (last 5 years)7 total outages: 5 momentary, 2 permanentp. 4
Alternatives consideredRetirement is not an option because the MISO Tranche 2.1 project will loop Duke stations Gwynneville and Batesville into the linep. 7
Ancillary benefitRebuilding the line now will help reduce future outages on the 345 kV outlets for the new 765 kV connectionsp. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 4, 2025Item 07 - AEP Supplemental Projects PDFHanna, IN/Tanners Creek, IN not printednot printedNeed Meeting 11/04/2025
June 2, 2026Item 06 - AEP Supplemental Projects PDFHanna, IN/Tanners Creek, IN $520 M10/15/2031Scoping
October 6, 2026Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 PDFHanna, IN/Tanners Creek, IN $520 M10/15/2031Scoping
Date not printedAEP&nbsp PDFHanna, IN/Tanners Creek, IN $520 M10/15/2031Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.