Mars–Golden
New Mars – Lockridge – Golden 230kV Lines; New Mars – Golden 500kV Line. Presented by PJM in PJM planning materials (Dominion zone).
Profile
This Dominion zone baseline project builds a new 500kV line and a new 230kV line between Mars and Golden substations, as part of the solution PJM recommended for 2022 Window 3 (2022-W3-692). (p. 134, p. 130) PJM first presented it in December 2023 inside the Northern Virginia/Doubs Cluster solution, a $1025.06 million package of baselines B3800.200 through B3800.227 that also lists a new Golden 500/230kV substation. (p. 130, p. 43, p. 41) The original scope was an 8.3-mile 500kV line and 230kV lines of 5.2 and 2.9 miles through Lockridge, all on shared double circuit structures, at an estimated $342.92 million. (p. 130, p. 5) In April 2025 the estimate rose by $97 million to $439.92 million, because the new lines would cross an existing transmission corridor where spatial and FAA constraints ruled out the alternative routes, so two existing lines at Mars are to be rerouted with about 2 miles of new conductor. (p. 132, p. 7) At the December 8, 2025 TEAC the 230kV line was moved to end at Prentice Drive substation instead of Lockridge, which PJM's slide says needs less right-of-way and avoids a full Lockridge outage, lowering the estimate by $8.3 million to $431.62 million. (p. 1, p. 134) The required and projected in-service dates printed in 2025 are both June 1, 2027; the December 2023 package showed a projected date of June 1, 2028 for the cluster as a whole. (p. 130, p. 1, p. 43)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Mars - Lockridge 230kV line (B3800.210) | New line, approximately 5.2 miles on 500/230kV double circuit structures, 1573 MVA summer rating; $57.95M in the original solution | p. 130 |
| Lockridge - Golden 230kV line (B3800.211) | New line, approximately 2.9 miles on 500/230kV double circuit structures, 1573 MVA summer rating; $56.93M in the original solution | p. 130 |
| Mars - Golden 500kV line (B3800.212) | New line, approximately 8.3 miles on 500/230kV double circuit structures, 4357 MVA summer normal rating; $228.04M in the original solution | p. 130 |
| Reroute of lines #2095 and #2292 at Mars | Remove and re-route 230kV lines #2095 Mars - Shellhorn and #2292 Mars - Sojourner to the south side of Mars, adding approximately 2 miles of new conductor | p. 132 |
| Sojourner 230kV cut-in | Cut line #2095 into Sojourner, creating line #2427 (Mars - Sojourner) and line #2095 (Sojourner - Shellhorn) | p. 132 |
| Sojourner 230kV breakers | Upgrade 4 230kV breakers from 63kA to 80kA | p. 132 |
| Prentice Drive 230kV termination | Terminate the 230kV Golden to Mars line at Prentice Drive instead of Lockridge; move two 230kV 80kA breakers from Lockridge to Prentice Drive | p. 134 |
Details as printed
| Required in service | Required 6/1/2027 | p. 130 |
|---|---|---|
| Solution | Part of the recommended solution for 2022 Window 3 (2022-W3-692) | p. 130 |
| Previously presented | Previously presented 12/5/2023 | p. 130 |
| Portfolio 2023 | Northern Virginia/Doubs Cluster recommended solution: Baseline B3800.200 – B3800.227, $1025.06 M, projected in service 6/1/2028 | p. 43 |
| Portfolio lines 2023 | New double-circuit 500/230 kV lines from Golden to Mars; the 230kV line connects Golden – Lockridge – Mars | p. 41 |
| Golden substation 2023 | The same recommended solution lists a new Golden 500/230kV substation | p. 41 |
| Cost original | $342.92M (original solution) | p. 5 |
| Cost 2025 04 | $439.92M after an additional $97M (B3800.210 $49M + B3800.212 $48M) | p. 7 |
| Revision 2025 04 | Revised solution presented at the 4/1/2025 TEAC | p. 132 |
| Reason 2025 04 | The new lines intersect an existing transmission corridor just east of the Old Ox/Carters School Road intersection; spatial and FAA constraints rule out the alternative routes | p. 7 |
| Reason cost 2025 04 | Cost increase due to an additional 2 miles of line and real estate for the reroutes | p. 7 |
| Cost 2025 12 | $431.62M after a change of -$8.3M (B3800.210 -$4.15M + B3800.211 -$4.15M) | p. 134 |
| Reason 2025 12 | Prentice Drive termination requires less right-of-way and reduces line material costs | p. 134 |
| Reason outages 2025 12 | Prentice allows alternating outages; Lockridge would require a full substation outage or temporary configurations | p. 134 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| April 1, 2025 | Item 14 - Reliability Analysis Update PDF | New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line | $439.92M | 6/1/2027 | |
| December 8, 2025 | Item 11 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line | $431.62M | 6/1/2027 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Loudoun residents take fight against high-voltage power lines for Data Center Alley to SCC, Virginia Mercury (via Yahoo News), December 16, 2025. The Virginia Mercury reported that residents of the Loudoun Valley Estates neighborhoods in Ashburn testified at the State Corporation Commission against the proposed Golden to Mars routes, that the Board of Supervisors supports burying segments within 500 feet of homes and schools, and that Dominion said a feasibility study found burial difficult.
- Loudoun homeowners appear to lose battle with Dominion’s data center transmission lines, WJLA 7News, July 3, 2026. WJLA reported that the State Corporation Commission issued a final order approving the Golden to Mars project on Route 3A past homes in Loudoun Valley Estates, after rejecting the county-backed Route 4 because the school board had not consented to the use of school property.
- Dominion’s ‘Golden to Mars’ project in Loudoun could reach Va. Supreme Court, WTOP News, July 21, 2026. WTOP reported that the State Corporation Commission declined a request from the school board, the Board of Supervisors and Dominion to postpone the route decision, a ruling that WTOP said opens the way for opponents to appeal to the Supreme Court of Virginia.
Not printed
- No project status (such as engineering or construction) is printed on the PJM slides; the latest slide is a scope change and cost update.
- No state or county is printed on the cited pages; the only location given is the Old Ox/Carters School Road intersection.
- The 2023 deck prints one cost for the whole B3800.200 – B3800.227 package, not a separate cost for the Mars–Golden lines.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.