Mars–Golden

New Mars – Lockridge – Golden 230kV Lines; New Mars – Golden 500kV Line. Presented by PJM in PJM planning materials (Dominion zone).

$431.62Mcost estimate as printed p. 134
6/1/2027projected in service p. 130
Baseline; revised solutionstatus as printed p. 134

Profile

This Dominion zone baseline project builds a new 500kV line and a new 230kV line between Mars and Golden substations, as part of the solution PJM recommended for 2022 Window 3 (2022-W3-692). (p. 134, p. 130) PJM first presented it in December 2023 inside the Northern Virginia/Doubs Cluster solution, a $1025.06 million package of baselines B3800.200 through B3800.227 that also lists a new Golden 500/230kV substation. (p. 130, p. 43, p. 41) The original scope was an 8.3-mile 500kV line and 230kV lines of 5.2 and 2.9 miles through Lockridge, all on shared double circuit structures, at an estimated $342.92 million. (p. 130, p. 5) In April 2025 the estimate rose by $97 million to $439.92 million, because the new lines would cross an existing transmission corridor where spatial and FAA constraints ruled out the alternative routes, so two existing lines at Mars are to be rerouted with about 2 miles of new conductor. (p. 132, p. 7) At the December 8, 2025 TEAC the 230kV line was moved to end at Prentice Drive substation instead of Lockridge, which PJM's slide says needs less right-of-way and avoids a full Lockridge outage, lowering the estimate by $8.3 million to $431.62 million. (p. 1, p. 134) The required and projected in-service dates printed in 2025 are both June 1, 2027; the December 2023 package showed a projected date of June 1, 2028 for the cluster as a whole. (p. 130, p. 1, p. 43)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Mars - Lockridge 230kV line (B3800.210)New line, approximately 5.2 miles on 500/230kV double circuit structures, 1573 MVA summer rating; $57.95M in the original solutionp. 130
Lockridge - Golden 230kV line (B3800.211)New line, approximately 2.9 miles on 500/230kV double circuit structures, 1573 MVA summer rating; $56.93M in the original solutionp. 130
Mars - Golden 500kV line (B3800.212)New line, approximately 8.3 miles on 500/230kV double circuit structures, 4357 MVA summer normal rating; $228.04M in the original solutionp. 130
Reroute of lines #2095 and #2292 at MarsRemove and re-route 230kV lines #2095 Mars - Shellhorn and #2292 Mars - Sojourner to the south side of Mars, adding approximately 2 miles of new conductorp. 132
Sojourner 230kV cut-inCut line #2095 into Sojourner, creating line #2427 (Mars - Sojourner) and line #2095 (Sojourner - Shellhorn)p. 132
Sojourner 230kV breakersUpgrade 4 230kV breakers from 63kA to 80kAp. 132
Prentice Drive 230kV terminationTerminate the 230kV Golden to Mars line at Prentice Drive instead of Lockridge; move two 230kV 80kA breakers from Lockridge to Prentice Drivep. 134

Details as printed

Required in serviceRequired 6/1/2027p. 130
SolutionPart of the recommended solution for 2022 Window 3 (2022-W3-692)p. 130
Previously presentedPreviously presented 12/5/2023p. 130
Portfolio 2023Northern Virginia/Doubs Cluster recommended solution: Baseline B3800.200 – B3800.227, $1025.06 M, projected in service 6/1/2028p. 43
Portfolio lines 2023New double-circuit 500/230 kV lines from Golden to Mars; the 230kV line connects Golden – Lockridge – Marsp. 41
Golden substation 2023The same recommended solution lists a new Golden 500/230kV substationp. 41
Cost original$342.92M (original solution)p. 5
Cost 2025 04$439.92M after an additional $97M (B3800.210 $49M + B3800.212 $48M)p. 7
Revision 2025 04Revised solution presented at the 4/1/2025 TEACp. 132
Reason 2025 04The new lines intersect an existing transmission corridor just east of the Old Ox/Carters School Road intersection; spatial and FAA constraints rule out the alternative routesp. 7
Reason cost 2025 04Cost increase due to an additional 2 miles of line and real estate for the reroutesp. 7
Cost 2025 12$431.62M after a change of -$8.3M (B3800.210 -$4.15M + B3800.211 -$4.15M)p. 134
Reason 2025 12Prentice Drive termination requires less right-of-way and reduces line material costsp. 134
Reason outages 2025 12Prentice allows alternating outages; Lockridge would require a full substation outage or temporary configurationsp. 134

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
April 1, 2025Item 14 - Reliability Analysis Update PDFNew Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line $439.92M6/1/2027
December 8, 2025Item 11 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline New Mars – Lockridge – Golden 230kV Lines New Mars – Golden 500kV Line $431.62M6/1/2027

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.