AEP Central/NW Ohio, Indiana portfolio
Central/NW OH, Indiana.. Presented by AEP in PJM planning materials (AEP zone, OH, IN).
Profile
This page covers a portfolio, not a single project: in its 2024 Local Plan submission to PJM, AEP groups fourteen customer-service need numbers in the New Albany and Columbus, Ohio area under one solution titled "Central/NW OH, Indiana.", with supplemental project IDs s3442.1-.30. (p. 1, p. 154, p. 156, p. 137) AEP lists a total estimated transmission cost of $378.3 million (direct connection $309.77 million and system upgrades $68.53 million), a projected in-service date of October 13, 2027, and a status of Scoping. (p. 155, p. 156) The next slide lists a separate $199.2 million of reinforcements that AEP says it identified and PJM later confirmed through its DNH analysis, including two new 345 kV lines of about 12.5 miles each from Vassell to Green Chapel and from Vassell to Curleys; the deck does not print a figure combining the two subtotals. (p. 156, p. 156) Thirteen of the needs are customer requests and one (Souder) is an AEP Ohio request for a new delivery point, mostly at sites near AEP's Jug Street and Anguin stations; the largest is an initial 226 MW rising to up to 968 MW at the site served by the new Curleys 345 kV station. (p. 137, p. 139, p. 127, p. 138) New stations in the plan include Badger, Horizon, Jorden, Macy, Souder, Fiesta, Tasjan and Kiber at 138 kV and Bermuda and Curleys at 345 kV, plus a new 345 kV ring bus at Innovation; Kiber is to carry a STATCOM to support what AEP calls the significant amount of load added to the area. (p. 126, p. 132, p. 134, p. 136, p. 140, p. 144, p. 148, p. 154, p. 142, p. 138, p. 130) The needs were first presented at need meetings from February 2022 to April 2023 and at solution meetings on May 9 and December 5, 2023; the 2024 submission prints two costs each for Curleys ($55.2 million and $57.2 million) and Bermuda ($60.3 million and $58.3 million), explaining that a capacitor bank planned for Bermuda moved to Curleys. (p. 125, p. 151, p. 138, p. 142, p. 138, p. 1) A later, undated copy of the same plan gives the submission date as September 16, 2024, where the October 2024 TEAC posting printed TBD. (p. 156, p. 156, p. 1)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Badger 138 kV station (s3442.1) | New breaker-and-a-half station, 10 breakers and a capacitor bank, cut into the Green Chapel - Jug 138 kV circuit; $18.43 M | p. 126 |
| QTS North 138 kV tie lines (s3442.2) | ~0.3 miles of 138 kV tie lines from Anguin station to the QTS customer's site; $1.8 M | p. 128 |
| Innovation 345/138 kV station (s3442.3) | New 345 kV ring bus at Innovation cut into the Corridor - Conesville 345 kV circuit, two 675 MVA transformers, 15 138 kV breakers; $53.7 M | p. 130 |
| Horizon 138 kV station (s3442.4) | New station, 8 breakers in breaker-and-a-half; $10.81 M | p. 132 |
| Jorden 138 kV station (s3442.5) | New 4-breaker ring bus station cut into the Innovation - Kirk 138 kV circuit; $12.5 M | p. 134 |
| QTS South / Macy 138 kV station (s3442.6) | New Macy station, 4-breaker ring bus, cut into an Anguin - Brie 138 kV circuit; $9.54 M | p. 136 |
| Brie - Innovation 138 kV tie (s3442.7) | New ~1.75 mile double circuit line; addresses an N-1-1 load drop of more than 300 MW at Anguin and Brie; $10.8 M | p. 136 |
| Curleys 345 kV station (s3442.8) | New station, 14 breakers, cut into the rerouted Corridor - Innovation 345 kV circuit; cost printed as $55.2 M and $57.2 M | p. 138 |
| Souder 138 kV station (s3442.9) | New 5-breaker ring bus station, ~1.0 mile of new double circuit line; $14.31 M | p. 140 |
| Bermuda 345 kV station (s3442.10) | New station, 11 breakers, Corridor - Innovation 345 kV circuit rerouted across the customer's site; cost printed as $60.3 M and $58.3 M | p. 142 |
| Fiesta 138 kV station (s3442.11) | New station, 10 breakers in breaker-and-a-half, ~0.75 miles of new double circuit line; $22.3 M | p. 144 |
| Anguin - Rockhopper 138 kV (s3442.12) | Reconfigure Anguin, 10 breakers, new ~0.6 mile line to the customer's Rockhopper station; $13.2 M | p. 146 |
| Tasjan 138 kV station (s3442.13) | New 4-breaker ring bus station, ~0.75 miles of new double circuit line; $18.95 M | p. 148 |
| Anguin - Chinstrap 138 kV (s3442.14) | Extend the line to Rockhopper by ~0.22 miles to the new Chinstrap (customer) station; $1.01 M | p. 150 |
| Anguin - NBY-6A 138 kV (s3442.15) | 3 breakers and a new ~0.9 mile line to the customer's NBY-6A station; $6.92 M | p. 152 |
| Corridor - Vassell 345 kV sag re-rate (s3442.16) | Replace two structures on the #1 and #2 circuits; $1.88 M | p. 154 |
| Kiber 138 kV station (s3442.17) | New station on the Green Chapel - Corridor 138 kV circuit with a STATCOM; $35 M | p. 154 |
| Green Chapel 138 kV capacitor banks (s3442.18) | Upgrade two proposed cap banks from 69.1 MVAR to 115.2 MVAR; $3.6 M | p. 154 |
| Corridor 138 kV breakers (s3442.19) | Replace 12 63 kA breakers with 80 kA breakers; $12.6 M | p. 154 |
| Babbitt 138 kV breakers (s3442.20) | Replace 2 bus-tie breakers with 80 kA breakers; $2.15 M | p. 154 |
| Jug Street 138 kV breaker (s3442.21) | Replace a 40 kA breaker with an 80kA breaker; $0.8 M | p. 154 |
| Anchor Hocking - Lancaster 69 kV rebuild (s3442.22) | Rebuild ~1.16 miles of 69 kV line; $2.5 M | p. 155 |
| Newark Center 138 kV (s3442.23) | High and low side sectionalizing on the 138/69 kV transformer; $2.5 M | p. 155 |
| Fremont - West Fremont 138 kV sag re-rate (s3442.24) | Sag re-rate and 1200 A switch upgrade for a generation deliverability violation; $2.0 M | p. 155 |
| Fremont - Fremont Center 138 kV sag re-rate (s3442.25) | Sag re-rate for a generation deliverability violation; $1.5 M | p. 155 |
| Dumont 765 kV breaker (s3442.26) | Replace a 3000 A breaker for a deliverability violation on the Dumont - Sorenson 765 kV branch; $4.0 M | p. 155 |
| Vassell - Green Chapel 345 kV line (s3442.27) | New ~12.5-mile 345 kV line; $75.0 M | p. 156 |
| Vassell - Curleys 345 kV line (s3442.28) | New ~12.5-mile 345 kV line; $75.0 M | p. 156 |
| Vassell 765 & 345 kV stations (s3442.29) | 345 kV breakers to connect the new lines to Curleys and Green Chapel; $10 M | p. 156 |
| Green Chapel 345/138 kV station (s3442.30) | Two 675 MVA 345/138 kV transformers; $39.2 M | p. 156 |
Details as printed
| Cost breakdown printed with the total | Direct connection $309.77M plus system upgrades $68.53M = $378.3M | p. 155 |
|---|---|---|
| Reinforcements confirmed by PJM (separate subtotal) | Further system reinforcements initially identified by AEP and later confirmed by PJM through its DNH analysis, listed after the total | p. 156 |
| Subtotal for those reinforcements | System Upgrades: $199.2 M | p. 156 |
| Process stage (TEAC 10/8/2024 posting) | Submission of Supplemental Project for inclusion in the Local Plan TBD | p. 156 |
| Need numbers in the portfolio | Fourteen need numbers, AEP-2022-OH023 through AEP-2023-OH063 | p. 154 |
| Supplemental project IDs | s3442.1-.30 | p. 156 |
| Why the reinforcements | System reinforcements required to serve the load and meet TPL-001, PJM and AEP planning criteria | p. 154 |
| Direct connection work | Station work described as direct connect, to physically connect demand to the grid | p. 126 |
| Earliest need meeting (Badger) | Need Meeting 2/18/2022; Solutions Meetings 5/9/2023 and 12/5/2023 (Badger) | p. 125 |
| Latest need meeting (Penguin NBY-6A) | Needs Meeting 4/21/2023; Solutions Meetings 5/9/2023 and 12/5/2023 (last of the fourteen) | p. 151 |
| Reason for update, Curleys and Bermuda | Capacitor bank moved from Bermuda to Curleys after engineering review | p. 138 |
| Reason for update, Kiber | 8 138 kV breakers needed initially at Kiber to fit the line exits and two STATCOM feeds | p. 154 |
| Customer request, Badger (AEP-2022-OH023) | 125 MW initial, up to 290 MW, north of Jugg Street station in Columbus, OH; requested June 1, 2024 | p. 125 |
| Customer request, QTS North (AEP-2022-OH034) | 216 MW east of Anguin station in New Albany, OH; requested 5/31/2023 | p. 127 |
| Customer request, Innovation build out (AEP-2022-OH036) | 247 MW additional service at an existing site in New Albany, OH; requested 4/1/2024 | p. 129 |
| Customer request, Horizon (AEP-2022-OH045) | 50 MW initial, 200 MW ultimate, north of Jug Street station in New Albany, OH; requested 4/30/2024 | p. 131 |
| Customer request, Jorden (AEP-2022-OH046) | 50 MW initial, up to 270 MW, east of Jug Street station in New Albany, OH; requested 6/28/2024 | p. 133 |
| Customer request, QTS South (AEP-2022-OH075) | 125 MW southeast of Anguin station in New Albany, OH; requested 8/1/2024 | p. 135 |
| Customer request, Curleys (AEP-2022-OH077) | 226 MW initial, up to 968 MW, north of Jug Street station in New Albany, OH; requested 5/1/2026 | p. 137 |
| AEP Ohio request, Souder (AEP-2023-OH016) | New 138kV delivery point near the Corridor - Jug circuit by June 2025; ~24.0 MVA initial, ~100 MVA future | p. 139 |
| Customer request, Bermuda (AEP-2023-OH019) | 337 MW initial and ultimate, north of Jug Street station in New Albany, OH; requested 12/15/2025 | p. 141 |
| Customer request, Fiesta (AEP-2023-OH032) | 50 MW initial, up to 300 MW, north of Jug Street station in Columbus, OH; requested January 1, 2026 | p. 143 |
| Customer request, Rockhopper (AEP-2023-OH040) | 100 MW addition for an existing Anguin customer, site total 350 MW, up to 720 MW; requested 5/31/2023 | p. 145 |
| Customer request, Tasjan (AEP-2023-OH044) | 54 MW, up to 150 MW, east of Jug Street station in New Albany; requested 12/19/2025 | p. 147 |
| Customer request, Penguin NBY-5A (AEP-2023-OH052) | 100 MW addition, site total 450 MW, up to 720 MW; requested 3/31/2024 | p. 149 |
| Customer request, Penguin NBY-6A (AEP-2023-OH063) | 100 MW addition, site total 550 MW, up to 720 MW; requested 7/31/2024 | p. 151 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| October 8, 2024 | Informational Only - AEP Local Plan submission of supplemental projects 2024 PDF | Central/NW OH, Indiana. | $378.3M | 10/13/2027 | Scoping |
| Date not printed | AEP  PDF | Central/NW OH, Indiana. | $378.3M | 10/13/2027 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Badger (AEP): described as new
- Bermuda (AEP): described as new
- Chinstrap (AEP): described as new
- Curleys (AEP): described as new
- Fiesta (AEP): described as new
- Green Chapel (AEP): described as new
- Horizon (AEP): described as new
- Jorden (AEP): described as new
- Kiber station (AEP): described as new
- Macy (AEP): described as new
- Souder (AEP): described as new
- Tasjan (AEP): described as new
- Anguin (AEP)
- Babbitt (AEP)
- Brie (AEP)
- Conesville (AEP): expansion described
- Corridor (AEP)
- Dumont (AEP)
- Fremont (AEP)
- Innovation (AEP): expansion described
- Jug (AEP)
- Jug Street (AEP)
- Kirk (AEP)
- Lancaster (AEP)
- Newark Center (AEP)
- QTS North (AEP)
- Vassell (AEP)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- AEP Ohio To Build Two 345 kV Electric Transmission Lines In Delaware And Licking Counties, T&D World, December 11, 2023. T&D World reported that AEP Ohio planned two 345 kV lines from Vassell Substation in Sunbury to two new substations near Green Chapel Road in New Albany, with construction of the first line expected from summer 2024 to spring 2026 and the second from spring 2026 to spring 2027.
- AEP Ohio picks routes for massive new transmission lines near Licking County Intel plant, The Columbus Dispatch (via AOL), January 31, 2024. The Columbus Dispatch reported that AEP Ohio chose routes for two roughly 13-mile 345 kV lines from Vassell Substation, one to a new substation on Green Chapel Road near Intel's planned plants and one to a new substation near land bought by Amazon, and that the Ohio Power Siting Board must approve them.
- AEP Ohio gives notice for new high voltage transmission lines to meet growing energy demands, WOSU Public Media, March 28, 2024. WOSU reported that AEP Ohio gave notice of two 345 kV lines from Vassell Substation to new substations off Green Chapel Road and near Tippet and Johnstown Utica roads, and quoted a Licking County commissioner saying data centers in the region need power.
Not printed
- The deck names no customer except in the station and tie-line labels QTS North and QTS South; it does not say what the loads are.
- No county is printed for any station in this portfolio. Indiana appears only in the solution title; no Indiana location is printed on the cited pages.
- The deck does not print a single total that includes both the $378.3M figure and the $199.2 M subtotal for the Vassell lines and Green Chapel transformers.
- The need and solution decks of 2022-2023 (need meetings 2/18/2022 to 4/21/2023; solution meetings 5/9/2023 and 12/5/2023) are not in the archive, so earlier cost estimates could not be checked.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.