Substation Scout

AEP Central/NW Ohio, Indiana portfolio

Central/NW OH, Indiana.. Presented by AEP in PJM planning materials (AEP zone, OH, IN).

$378.3Mcost estimate as printed p. 155
10/13/2027projected in service p. 156
Scopingstatus as printed p. 156

Profile

This page covers a portfolio, not a single project: in its 2024 Local Plan submission to PJM, AEP groups fourteen customer-service need numbers in the New Albany and Columbus, Ohio area under one solution titled "Central/NW OH, Indiana.", with supplemental project IDs s3442.1-.30. (p. 1, p. 154, p. 156, p. 137) AEP lists a total estimated transmission cost of $378.3 million (direct connection $309.77 million and system upgrades $68.53 million), a projected in-service date of October 13, 2027, and a status of Scoping. (p. 155, p. 156) The next slide lists a separate $199.2 million of reinforcements that AEP says it identified and PJM later confirmed through its DNH analysis, including two new 345 kV lines of about 12.5 miles each from Vassell to Green Chapel and from Vassell to Curleys; the deck does not print a figure combining the two subtotals. (p. 156, p. 156) Thirteen of the needs are customer requests and one (Souder) is an AEP Ohio request for a new delivery point, mostly at sites near AEP's Jug Street and Anguin stations; the largest is an initial 226 MW rising to up to 968 MW at the site served by the new Curleys 345 kV station. (p. 137, p. 139, p. 127, p. 138) New stations in the plan include Badger, Horizon, Jorden, Macy, Souder, Fiesta, Tasjan and Kiber at 138 kV and Bermuda and Curleys at 345 kV, plus a new 345 kV ring bus at Innovation; Kiber is to carry a STATCOM to support what AEP calls the significant amount of load added to the area. (p. 126, p. 132, p. 134, p. 136, p. 140, p. 144, p. 148, p. 154, p. 142, p. 138, p. 130) The needs were first presented at need meetings from February 2022 to April 2023 and at solution meetings on May 9 and December 5, 2023; the 2024 submission prints two costs each for Curleys ($55.2 million and $57.2 million) and Bermuda ($60.3 million and $58.3 million), explaining that a capacitor bank planned for Bermuda moved to Curleys. (p. 125, p. 151, p. 138, p. 142, p. 138, p. 1) A later, undated copy of the same plan gives the submission date as September 16, 2024, where the October 2024 TEAC posting printed TBD. (p. 156, p. 156, p. 1)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Badger 138 kV station (s3442.1)New breaker-and-a-half station, 10 breakers and a capacitor bank, cut into the Green Chapel - Jug 138 kV circuit; $18.43 Mp. 126
QTS North 138 kV tie lines (s3442.2)~0.3 miles of 138 kV tie lines from Anguin station to the QTS customer's site; $1.8 Mp. 128
Innovation 345/138 kV station (s3442.3)New 345 kV ring bus at Innovation cut into the Corridor - Conesville 345 kV circuit, two 675 MVA transformers, 15 138 kV breakers; $53.7 Mp. 130
Horizon 138 kV station (s3442.4)New station, 8 breakers in breaker-and-a-half; $10.81 Mp. 132
Jorden 138 kV station (s3442.5)New 4-breaker ring bus station cut into the Innovation - Kirk 138 kV circuit; $12.5 Mp. 134
QTS South / Macy 138 kV station (s3442.6)New Macy station, 4-breaker ring bus, cut into an Anguin - Brie 138 kV circuit; $9.54 Mp. 136
Brie - Innovation 138 kV tie (s3442.7)New ~1.75 mile double circuit line; addresses an N-1-1 load drop of more than 300 MW at Anguin and Brie; $10.8 Mp. 136
Curleys 345 kV station (s3442.8)New station, 14 breakers, cut into the rerouted Corridor - Innovation 345 kV circuit; cost printed as $55.2 M and $57.2 Mp. 138
Souder 138 kV station (s3442.9)New 5-breaker ring bus station, ~1.0 mile of new double circuit line; $14.31 Mp. 140
Bermuda 345 kV station (s3442.10)New station, 11 breakers, Corridor - Innovation 345 kV circuit rerouted across the customer's site; cost printed as $60.3 M and $58.3 Mp. 142
Fiesta 138 kV station (s3442.11)New station, 10 breakers in breaker-and-a-half, ~0.75 miles of new double circuit line; $22.3 Mp. 144
Anguin - Rockhopper 138 kV (s3442.12)Reconfigure Anguin, 10 breakers, new ~0.6 mile line to the customer's Rockhopper station; $13.2 Mp. 146
Tasjan 138 kV station (s3442.13)New 4-breaker ring bus station, ~0.75 miles of new double circuit line; $18.95 Mp. 148
Anguin - Chinstrap 138 kV (s3442.14)Extend the line to Rockhopper by ~0.22 miles to the new Chinstrap (customer) station; $1.01 Mp. 150
Anguin - NBY-6A 138 kV (s3442.15)3 breakers and a new ~0.9 mile line to the customer's NBY-6A station; $6.92 Mp. 152
Corridor - Vassell 345 kV sag re-rate (s3442.16)Replace two structures on the #1 and #2 circuits; $1.88 Mp. 154
Kiber 138 kV station (s3442.17)New station on the Green Chapel - Corridor 138 kV circuit with a STATCOM; $35 Mp. 154
Green Chapel 138 kV capacitor banks (s3442.18)Upgrade two proposed cap banks from 69.1 MVAR to 115.2 MVAR; $3.6 Mp. 154
Corridor 138 kV breakers (s3442.19)Replace 12 63 kA breakers with 80 kA breakers; $12.6 Mp. 154
Babbitt 138 kV breakers (s3442.20)Replace 2 bus-tie breakers with 80 kA breakers; $2.15 Mp. 154
Jug Street 138 kV breaker (s3442.21)Replace a 40 kA breaker with an 80kA breaker; $0.8 Mp. 154
Anchor Hocking - Lancaster 69 kV rebuild (s3442.22)Rebuild ~1.16 miles of 69 kV line; $2.5 Mp. 155
Newark Center 138 kV (s3442.23)High and low side sectionalizing on the 138/69 kV transformer; $2.5 Mp. 155
Fremont - West Fremont 138 kV sag re-rate (s3442.24)Sag re-rate and 1200 A switch upgrade for a generation deliverability violation; $2.0 Mp. 155
Fremont - Fremont Center 138 kV sag re-rate (s3442.25)Sag re-rate for a generation deliverability violation; $1.5 Mp. 155
Dumont 765 kV breaker (s3442.26)Replace a 3000 A breaker for a deliverability violation on the Dumont - Sorenson 765 kV branch; $4.0 Mp. 155
Vassell - Green Chapel 345 kV line (s3442.27)New ~12.5-mile 345 kV line; $75.0 Mp. 156
Vassell - Curleys 345 kV line (s3442.28)New ~12.5-mile 345 kV line; $75.0 Mp. 156
Vassell 765 & 345 kV stations (s3442.29)345 kV breakers to connect the new lines to Curleys and Green Chapel; $10 Mp. 156
Green Chapel 345/138 kV station (s3442.30)Two 675 MVA 345/138 kV transformers; $39.2 Mp. 156

Details as printed

Cost breakdown printed with the totalDirect connection $309.77M plus system upgrades $68.53M = $378.3Mp. 155
Reinforcements confirmed by PJM (separate subtotal)Further system reinforcements initially identified by AEP and later confirmed by PJM through its DNH analysis, listed after the totalp. 156
Subtotal for those reinforcementsSystem Upgrades: $199.2 Mp. 156
Process stage (TEAC 10/8/2024 posting)Submission of Supplemental Project for inclusion in the Local Plan TBDp. 156
Need numbers in the portfolioFourteen need numbers, AEP-2022-OH023 through AEP-2023-OH063p. 154
Supplemental project IDss3442.1-.30p. 156
Why the reinforcementsSystem reinforcements required to serve the load and meet TPL-001, PJM and AEP planning criteriap. 154
Direct connection workStation work described as direct connect, to physically connect demand to the gridp. 126
Earliest need meeting (Badger)Need Meeting 2/18/2022; Solutions Meetings 5/9/2023 and 12/5/2023 (Badger)p. 125
Latest need meeting (Penguin NBY-6A)Needs Meeting 4/21/2023; Solutions Meetings 5/9/2023 and 12/5/2023 (last of the fourteen)p. 151
Reason for update, Curleys and BermudaCapacitor bank moved from Bermuda to Curleys after engineering reviewp. 138
Reason for update, Kiber8 138 kV breakers needed initially at Kiber to fit the line exits and two STATCOM feedsp. 154
Customer request, Badger (AEP-2022-OH023)125 MW initial, up to 290 MW, north of Jugg Street station in Columbus, OH; requested June 1, 2024p. 125
Customer request, QTS North (AEP-2022-OH034)216 MW east of Anguin station in New Albany, OH; requested 5/31/2023p. 127
Customer request, Innovation build out (AEP-2022-OH036)247 MW additional service at an existing site in New Albany, OH; requested 4/1/2024p. 129
Customer request, Horizon (AEP-2022-OH045)50 MW initial, 200 MW ultimate, north of Jug Street station in New Albany, OH; requested 4/30/2024p. 131
Customer request, Jorden (AEP-2022-OH046)50 MW initial, up to 270 MW, east of Jug Street station in New Albany, OH; requested 6/28/2024p. 133
Customer request, QTS South (AEP-2022-OH075)125 MW southeast of Anguin station in New Albany, OH; requested 8/1/2024p. 135
Customer request, Curleys (AEP-2022-OH077)226 MW initial, up to 968 MW, north of Jug Street station in New Albany, OH; requested 5/1/2026p. 137
AEP Ohio request, Souder (AEP-2023-OH016)New 138kV delivery point near the Corridor - Jug circuit by June 2025; ~24.0 MVA initial, ~100 MVA futurep. 139
Customer request, Bermuda (AEP-2023-OH019)337 MW initial and ultimate, north of Jug Street station in New Albany, OH; requested 12/15/2025p. 141
Customer request, Fiesta (AEP-2023-OH032)50 MW initial, up to 300 MW, north of Jug Street station in Columbus, OH; requested January 1, 2026p. 143
Customer request, Rockhopper (AEP-2023-OH040)100 MW addition for an existing Anguin customer, site total 350 MW, up to 720 MW; requested 5/31/2023p. 145
Customer request, Tasjan (AEP-2023-OH044)54 MW, up to 150 MW, east of Jug Street station in New Albany; requested 12/19/2025p. 147
Customer request, Penguin NBY-5A (AEP-2023-OH052)100 MW addition, site total 450 MW, up to 720 MW; requested 3/31/2024p. 149
Customer request, Penguin NBY-6A (AEP-2023-OH063)100 MW addition, site total 550 MW, up to 720 MW; requested 7/31/2024p. 151

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
October 8, 2024Informational Only - AEP Local Plan submission of supplemental projects 2024 PDFCentral/NW OH, Indiana. $378.3M10/13/2027Scoping
Date not printedAEP&nbsp PDFCentral/NW OH, Indiana. $378.3M10/13/2027Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first