2022 Window 3 South Cluster
2022W3 – Recommended Solutions: South Cluster. Presented by PJM in PJM planning materials (Dominion zone).
Profile
The South Cluster is one part of the solution PJM recommended for its 2022 RTEP Window 3: a portfolio of Dominion zone baseline projects rather than a single line, presented at the December 5, 2023 TEAC with a cluster proposal cost of $1,265.85 million. (p. 25, p. 8, p. 1, p. 6, p. 37) Its largest piece, proposal 2022-W3-711 (Partial) for baselines B3800.311 through B3800.357 at $842.19 million, builds a new 500kV line of about 36.3 miles from Morrisville through Vint Hill to Wishing Star, largely in existing right-of-way, and rebuilds the existing lines and upgrades substations along that corridor. (p. 27, p. 28, p. 30) The other pieces rebuild 230kV lines around Charlottesville ($183.49 million), between Hollymeade and Gordonsville ($54.85 million) and between Ladysmith CT and Summit D.P. ($36.50 million), replace a Locks 230/115 kV transformer ($7.14 million), add capacitor banks and STATCOMs at Morrisville, Wishing Star, Mars and Beaumeade ($103.79 million), and uprate 12.44 miles of line 256 from St. Johns to Ladysmith CT ($37.89 million). (p. 31, p. 32, p. 33, p. 35, p. 34, p. 36, p. 37) PJM framed the whole window around about 7,500 MW of data center load growth forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) and 11,100 MW of announced deactivations; the cluster slides do not tie a load or customer to any South Cluster component. (p. 2) In April 2025 PJM cancelled two earlier baselines because 2022 Window 3 projects cover the same work, and in May 2025 Dominion switched the Charlottesville – Hollymeade Junction and Hollymeade – Gordonsville rebuilds to double-circuit 230/230kV structures for right-of-way reasons, lowering one estimate from $70.14 million to $46.53 million and the other from $53.96 million to $32.0 million, with the first moving to a projected date of December 1, 2028. (p. 1, p. 10, p. 1, p. 5, p. 6) At the May 8, 2026 TEAC, on slides for the new Yeat substation, the 500kV line baseline b3800.357 is printed to Vint Hill from Yeat, with its length marked from 19.71 to 27.21 miles and its estimate from $101.89 million to $150.64 million; the same slides withdraw a December 2025 scope change to b3800.313. (p. 1, p. 19, p. 20, p. 1, p. 86) The December 2023 slides print required dates of June 1, 2027 for most pieces and projected dates from December 1, 2027 to June 1, 2028; PJM has not printed an updated total for the cluster. (p. 1, p. 30, p. 35)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| New 500kV line, Morrisville – Vint Hill – Wishing Star (2022-W3-711) | Proposal 2022-W3-711 (Partial): build a new 500kV line from Morrisville – Vint Hill – Wishing Star (approximately 36.3 miles), maximizing use of existing right-of-way in the corridor | p. 27 |
| 500kV corridor rebuilds (2022-W3-711) | Rebuild 500kV lines #545 Bristers - Morrisville, #569 Loudoun to Morrisville, #535 Meadowbrook - Loudoun, #546 and #590 Mosby - Wishing Star | p. 27 |
| 230kV corridor rebuilds (2022-W3-711) | Rebuild 230kV lines #2030, #2045, #2094 & 2227, #2101 and #2114 | p. 27 |
| More corridor rebuilds (2022-W3-711) | Rebuild 230kV lines #2140, #2151, #2163, #2176, #2222 and 115kV line #183 Bristers - Ox | p. 28 |
| Substation upgrades (2022-W3-711) | Substation upgrades at Bristers, Brambleton, Dawkins Branch, Gainesville, Heathcote, Loudoun, Mint Springs, Morrisville, Mosby, North Star, Racefield, Railroad, Vint Hill, Wishing Star and Youngs Branch | p. 28 |
| Line #2054 rebuild (2022-W3-967) | Proposal 2022-W3-967: rebuild 230kV Line #2054 Charlottesville – Proffit DP on double-circuit capable 500/230 kV poles | p. 31 |
| Lines #233 and #291 rebuilds (2022-W3-967) | Rebuild 230kV Lines #233 and #291 between Charlottesville and Dooms | p. 31 |
| Line #2135 rebuild (2022-W3-211) | Proposal 2022-W3-211: rebuild 230kV Line #2135 Hollymeade – Gordonsville on double-circuit capable 500/230 kV poles | p. 33 |
| Locks transformer (2022-W3-731) | Proposal 2022-W3-731: replace Locks 230/115 kV 168MVA transformer #7 with a 224 MVA unit | p. 34 |
| Line #2090 rebuild (2022-W3-74) | Proposal 2022-W3-74 (Partial): wreck and rebuild Line #2090 Ladysmith CT – Summit D.P. as a double circuit 230kV line, one circuit wired | p. 35 |
| Reactive support (2022-W3-231) | Proposal 2022-W3-231 (Partial): install 230kV and 500kV shunt capacitor banks and STATCOMs for reactive power needs | p. 36 |
| Reactive support stations (2022-W3-231) | Beaumeade Substation: (1) 230kV, 300 MVAr STATCOM; the slide also lists Morrisville, Wishing Star and Mars | p. 36 |
| Line 256 uprate (Dominion) | Additional 230kV upgrades (Dominion): uprate 12.44 miles of 230kV circuit 256 from St. Johns to Ladysmith CT | p. 37 |
Details as printed
| 2022 Window 3 purpose | PJM: unprecedented data center load growth (~7,500 MW) forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) | p. 2 |
|---|---|---|
| 2022 Window 3 purpose | 11,100 MW deactivation announced | p. 2 |
| First presented | Selected proposals were previously presented at the Oct 31st TEAC | p. 14 |
| 2022-W3-711 (Partial), B3800.311 – B3800.357 | $842.19M; required 6/1/2027, projected 6/1/2028 | p. 30 |
| 2022-W3-967, B3800.360 – B3800.372 | $183.49M; required 6/1/2027, projected 6/1/2028 | p. 32 |
| 2022-W3-211, B3800.300 – B3800.304 | $54.85M; required 6/1/2027, projected 6/1/2028 | p. 33 |
| 2022-W3-731, B3800.358 | $7.14M; required 6/1/2027, projected 6/1/2028 | p. 34 |
| 2022-W3-74 (Partial), B3800.359 | $36.50M; required 6/1/2027, projected 12/1/2027 | p. 35 |
| 2022-W3-231 (Partial), B3800.305 – B3800.310 | $103.79M; required 6/1/2027, projected 12/1/2027 | p. 36 |
| Additional 230kV upgrades (Dominion), B3800.373 – B3800.374 | $37.89M; required and projected 6/1/2028 | p. 37 |
| Meeting | TEAC April 1, 2025, Reliability Analysis Update | p. 1 |
| Cancellation of B3211 (April 2025) | An earlier 1.3 mile Line #569 rebuild ($4.5M) cancelled: b3800.312 from 2022 Window 3 will rebuild the entire portion of line #569 Loudoun – Morrisville | p. 10 |
| Cancellation of B4000.130 (April 2025) | Earlier Ox breaker replacements cancelled: b3800.236 and b3800.335 from 2022 Window 3 replace the same 3 breakers | p. 11 |
| B4000.130 cost | $3.045M | p. 11 |
| Meeting | TEAC May 6, 2025, Reliability Analysis Update (scope change and cost updates) | p. 1 |
| Scope change, b3800.360 (May 2025) | Revised cost estimate $70.14M to $46.53M; projected in service 6/1/2028 to 12/1/2028 | p. 5 |
| Reason, b3800.360 | Due to right-of-way considerations, Dominion proposes double-circuit 230/230kV structures | p. 5 |
| Scope change, b3800.300/b3800.301 (May 2025) | Scope change for b3800.300 & b3800.301, previously presented 12/5/2023 | p. 6 |
| Revised cost, b3800.300/b3800.301 | b3800.300 $19.4M and b3800.301 $12.6M on double-circuit capable 230 kV poles; $53.96M revised to $32.0M; projected in service 6/1/2028 | p. 6 |
| Scope change, b3800.304 (May 2025) | Revised scope: Charlottesville substation switch 205415 and line leads to 4000A for 230 kV line No. 2054, instead of a Hollymeade switch | p. 7 |
| b3800.304 cost and date | $0.3M; projected 6/1/2028 changed to 12/30/2028 | p. 7 |
| Referenced by Dominion supplemental DOM-2024-0051 (June 2025) | A Dominion supplemental need slide lists B3800.373-374 and B3800.359 as existing reliability projects in the Elmont to Fredericksburg corridor | p. 10 |
| Meeting | TEAC December 8, 2025, Reliability Analysis Update | p. 1 |
| Scope change, b3800.313 (December 2025) | Scope change to 2022W3 b3800.313: reconductor the existing 500kV Yeat – Vint Hill line to 6000A | p. 86 |
| b3800.313 scope change cost | Total estimated cost $0M; required and projected in service 6/1/2032 | p. 86 |
| Meeting | TEAC May 8, 2026, Reliability Analysis Update | p. 1 |
| Scope change, b3800.357 (May 2026) | On the new Yeat substation slide, b3800.357: new 500kV line printed as Morrisville / Culpeper / Yeat to Vint Hill, length 19.71 then 27.21 miles, cost $101.89M then $150.64M | p. 19 |
| Cost change, b3800.346 (May 2026) | b3800.346 Morrisville terminal equipment: $17.54 then $12.54 | p. 19 |
| b3800.313 scope change withdrawn (May 2026) | The b3800.313 scope change from 2025W1 is no longer required; B3800.313 remains as originally specified | p. 20 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $54.85 M | 6/1/2028 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $103.79 M | 12/1/2027 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $842.19 M | 6/1/2028 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $7.14 M | 6/1/2028 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $36.50 M | 12/1/2027 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $183.49 M | 6/1/2028 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | 2022W3 – Recommended Solutions: South Cluster | $37.89 M | 6/1/2028 | |
| May 6, 2025 | Item 10 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline 230kV Line #2135 Hollymeade – Gordonsville | $32.0 M | 6/1/2028 | |
| May 6, 2025 | Item 10 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline Hollymeade/Charlottesville Switch Upgrades | $0.3 M | 12/30/2028 | |
| May 6, 2025 | Item 10 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline 230kV Line #2054 Charlottesville-Proffit | $46.53 M | 12/1/2028 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Burrell Substation (DOM): described as new
- Dawkins Branch (DOM): described as new
- Wishing Star (DOM): described as new
- Barracks Road (DOM)
- Beaumeade (DOM)
- Brambleton (DOM)
- Bristers (DOM)
- Cash’s Corner (DOM)
- Charlottesville (DOM)
- Crozet (DOM)
- Dooms (DOM)
- Gainesville (DOM)
- Gordonsville (DOM)
- Heathcote (DOM)
- Hollymeade (DOM)
- Hollymeade Junction (DOM)
- Hydraulic Rd (DOM)
- Ladysmith CT (DOM)
- Liberty (DOM)
- Locks (DOM)
- Loudoun (DOM)
- Mars (DOM)
- Meadowbrook (DOM)
- Morrisville (DOM)
- Mosby (DOM)
- North Star (DOM)
- Proffit (DOM)
- Proffit DP (DOM)
- Racefield (DOM)
- Railroad (DOM)
- Railroad DP (DOM)
- Remington CT (DOM)
- Rollins Ford (DOM)
- St. Johns (DOM)
- Summit D.P. (DOM)
- Vint Hill (DOM): expansion described
- Youngs Branch (DOM)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Power crunch prompts planning for new, high-voltage lines, Prince William Times, August 30, 2023. The Prince William Times reported, before PJM made its selection, that Dominion proposal 711 in the PJM window included a new 500-kilovolt line through Fauquier County to Morrisville and Vint Hill, among competing proposals from Dominion and Transource.
- SCC Adds Time For Public Comment, Testimony In Morrisville To Wishing Star Power Line Case, Patch, July 6, 2026. Patch reported that the State Corporation Commission extended the schedule in the case on Dominion's proposed 36.5-mile, 500-kilovolt Morrisville to Wishing Star line along an existing route, moving the public comment deadline to October 30 and the evidentiary hearing to November 16, and that conservation groups sought a full environmental review over Manassas National Battlefield Park.
- Data center demand questioned in Dominion line case, The Center Square (via WarrenCountyVa.com), September 30, 2026. The Center Square reported that at a State Corporation Commission public hearing on the Morrisville-Wishing Star project a Loudoun County supervisor, testifying as an individual, questioned whether data center demand forecasts support the line, and that landowners near Manassas National Battlefield Park and Heritage Hunt residents disagreed over routing; the commission adjourned the case to November 16.
Not printed
- No developer or designated entity is printed in text for the South Cluster proposals; the "by Designated Entity" map (2023-12 deck p.26) has no readable text. Only the line 256 uprate is labeled "(Dominion)"; the 2025 and 2026 slides head these items "Dominion Transmission Zone: Baseline".
- No state or county is printed on the cited pages. The press places the Morrisville – Wishing Star line in Fauquier, Prince William and Loudoun counties, Virginia.
- PJM has printed no updated cost or in-service date for the cluster as a whole since the December 2023 total of $1,265.85M; later changes are per baseline.
- No project status (engineering, construction) is printed for any member.
- The December 2023 deck points to a separate informational document for per-baseline components (B3800.312, .313, .346, .357 and others inside B3800.311 – B3800.357); that document is not in the archive, so per-baseline costs inside the $842.19M are not shown.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.