2022 Window 3 South Cluster

2022W3 – Recommended Solutions: South Cluster. Presented by PJM in PJM planning materials (Dominion zone).

$1,265.85Mcost estimate as printed p. 6
6/1/2028projected in service p. 30
Recommended (baseline)status as printed p. 8

Profile

The South Cluster is one part of the solution PJM recommended for its 2022 RTEP Window 3: a portfolio of Dominion zone baseline projects rather than a single line, presented at the December 5, 2023 TEAC with a cluster proposal cost of $1,265.85 million. (p. 25, p. 8, p. 1, p. 6, p. 37) Its largest piece, proposal 2022-W3-711 (Partial) for baselines B3800.311 through B3800.357 at $842.19 million, builds a new 500kV line of about 36.3 miles from Morrisville through Vint Hill to Wishing Star, largely in existing right-of-way, and rebuilds the existing lines and upgrades substations along that corridor. (p. 27, p. 28, p. 30) The other pieces rebuild 230kV lines around Charlottesville ($183.49 million), between Hollymeade and Gordonsville ($54.85 million) and between Ladysmith CT and Summit D.P. ($36.50 million), replace a Locks 230/115 kV transformer ($7.14 million), add capacitor banks and STATCOMs at Morrisville, Wishing Star, Mars and Beaumeade ($103.79 million), and uprate 12.44 miles of line 256 from St. Johns to Ladysmith CT ($37.89 million). (p. 31, p. 32, p. 33, p. 35, p. 34, p. 36, p. 37) PJM framed the whole window around about 7,500 MW of data center load growth forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs) and 11,100 MW of announced deactivations; the cluster slides do not tie a load or customer to any South Cluster component. (p. 2) In April 2025 PJM cancelled two earlier baselines because 2022 Window 3 projects cover the same work, and in May 2025 Dominion switched the Charlottesville – Hollymeade Junction and Hollymeade – Gordonsville rebuilds to double-circuit 230/230kV structures for right-of-way reasons, lowering one estimate from $70.14 million to $46.53 million and the other from $53.96 million to $32.0 million, with the first moving to a projected date of December 1, 2028. (p. 1, p. 10, p. 1, p. 5, p. 6) At the May 8, 2026 TEAC, on slides for the new Yeat substation, the 500kV line baseline b3800.357 is printed to Vint Hill from Yeat, with its length marked from 19.71 to 27.21 miles and its estimate from $101.89 million to $150.64 million; the same slides withdraw a December 2025 scope change to b3800.313. (p. 1, p. 19, p. 20, p. 1, p. 86) The December 2023 slides print required dates of June 1, 2027 for most pieces and projected dates from December 1, 2027 to June 1, 2028; PJM has not printed an updated total for the cluster. (p. 1, p. 30, p. 35)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
New 500kV line, Morrisville – Vint Hill – Wishing Star (2022-W3-711)Proposal 2022-W3-711 (Partial): build a new 500kV line from Morrisville – Vint Hill – Wishing Star (approximately 36.3 miles), maximizing use of existing right-of-way in the corridorp. 27
500kV corridor rebuilds (2022-W3-711)Rebuild 500kV lines #545 Bristers - Morrisville, #569 Loudoun to Morrisville, #535 Meadowbrook - Loudoun, #546 and #590 Mosby - Wishing Starp. 27
230kV corridor rebuilds (2022-W3-711)Rebuild 230kV lines #2030, #2045, #2094 & 2227, #2101 and #2114p. 27
More corridor rebuilds (2022-W3-711)Rebuild 230kV lines #2140, #2151, #2163, #2176, #2222 and 115kV line #183 Bristers - Oxp. 28
Substation upgrades (2022-W3-711)Substation upgrades at Bristers, Brambleton, Dawkins Branch, Gainesville, Heathcote, Loudoun, Mint Springs, Morrisville, Mosby, North Star, Racefield, Railroad, Vint Hill, Wishing Star and Youngs Branchp. 28
Line #2054 rebuild (2022-W3-967)Proposal 2022-W3-967: rebuild 230kV Line #2054 Charlottesville – Proffit DP on double-circuit capable 500/230 kV polesp. 31
Lines #233 and #291 rebuilds (2022-W3-967)Rebuild 230kV Lines #233 and #291 between Charlottesville and Doomsp. 31
Line #2135 rebuild (2022-W3-211)Proposal 2022-W3-211: rebuild 230kV Line #2135 Hollymeade – Gordonsville on double-circuit capable 500/230 kV polesp. 33
Locks transformer (2022-W3-731)Proposal 2022-W3-731: replace Locks 230/115 kV 168MVA transformer #7 with a 224 MVA unitp. 34
Line #2090 rebuild (2022-W3-74)Proposal 2022-W3-74 (Partial): wreck and rebuild Line #2090 Ladysmith CT – Summit D.P. as a double circuit 230kV line, one circuit wiredp. 35
Reactive support (2022-W3-231)Proposal 2022-W3-231 (Partial): install 230kV and 500kV shunt capacitor banks and STATCOMs for reactive power needsp. 36
Reactive support stations (2022-W3-231)Beaumeade Substation: (1) 230kV, 300 MVAr STATCOM; the slide also lists Morrisville, Wishing Star and Marsp. 36
Line 256 uprate (Dominion)Additional 230kV upgrades (Dominion): uprate 12.44 miles of 230kV circuit 256 from St. Johns to Ladysmith CTp. 37

Details as printed

2022 Window 3 purposePJM: unprecedented data center load growth (~7,500 MW) forecast by 2027-28 in Dominion (Northern Virginia) and APS (Doubs)p. 2
2022 Window 3 purpose11,100 MW deactivation announcedp. 2
First presentedSelected proposals were previously presented at the Oct 31st TEACp. 14
2022-W3-711 (Partial), B3800.311 – B3800.357$842.19M; required 6/1/2027, projected 6/1/2028p. 30
2022-W3-967, B3800.360 – B3800.372$183.49M; required 6/1/2027, projected 6/1/2028p. 32
2022-W3-211, B3800.300 – B3800.304$54.85M; required 6/1/2027, projected 6/1/2028p. 33
2022-W3-731, B3800.358$7.14M; required 6/1/2027, projected 6/1/2028p. 34
2022-W3-74 (Partial), B3800.359$36.50M; required 6/1/2027, projected 12/1/2027p. 35
2022-W3-231 (Partial), B3800.305 – B3800.310$103.79M; required 6/1/2027, projected 12/1/2027p. 36
Additional 230kV upgrades (Dominion), B3800.373 – B3800.374$37.89M; required and projected 6/1/2028p. 37
MeetingTEAC April 1, 2025, Reliability Analysis Updatep. 1
Cancellation of B3211 (April 2025)An earlier 1.3 mile Line #569 rebuild ($4.5M) cancelled: b3800.312 from 2022 Window 3 will rebuild the entire portion of line #569 Loudoun – Morrisvillep. 10
Cancellation of B4000.130 (April 2025)Earlier Ox breaker replacements cancelled: b3800.236 and b3800.335 from 2022 Window 3 replace the same 3 breakersp. 11
B4000.130 cost$3.045Mp. 11
MeetingTEAC May 6, 2025, Reliability Analysis Update (scope change and cost updates)p. 1
Scope change, b3800.360 (May 2025)Revised cost estimate $70.14M to $46.53M; projected in service 6/1/2028 to 12/1/2028p. 5
Reason, b3800.360Due to right-of-way considerations, Dominion proposes double-circuit 230/230kV structuresp. 5
Scope change, b3800.300/b3800.301 (May 2025)Scope change for b3800.300 & b3800.301, previously presented 12/5/2023p. 6
Revised cost, b3800.300/b3800.301b3800.300 $19.4M and b3800.301 $12.6M on double-circuit capable 230 kV poles; $53.96M revised to $32.0M; projected in service 6/1/2028p. 6
Scope change, b3800.304 (May 2025)Revised scope: Charlottesville substation switch 205415 and line leads to 4000A for 230 kV line No. 2054, instead of a Hollymeade switchp. 7
b3800.304 cost and date$0.3M; projected 6/1/2028 changed to 12/30/2028p. 7
Referenced by Dominion supplemental DOM-2024-0051 (June 2025)A Dominion supplemental need slide lists B3800.373-374 and B3800.359 as existing reliability projects in the Elmont to Fredericksburg corridorp. 10
MeetingTEAC December 8, 2025, Reliability Analysis Updatep. 1
Scope change, b3800.313 (December 2025)Scope change to 2022W3 b3800.313: reconductor the existing 500kV Yeat – Vint Hill line to 6000Ap. 86
b3800.313 scope change costTotal estimated cost $0M; required and projected in service 6/1/2032p. 86
MeetingTEAC May 8, 2026, Reliability Analysis Updatep. 1
Scope change, b3800.357 (May 2026)On the new Yeat substation slide, b3800.357: new 500kV line printed as Morrisville / Culpeper / Yeat to Vint Hill, length 19.71 then 27.21 miles, cost $101.89M then $150.64Mp. 19
Cost change, b3800.346 (May 2026)b3800.346 Morrisville terminal equipment: $17.54 then $12.54p. 19
b3800.313 scope change withdrawn (May 2026)The b3800.313 scope change from 2025W1 is no longer required; B3800.313 remains as originally specifiedp. 20

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $54.85 M6/1/2028
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $103.79 M12/1/2027
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $842.19 M6/1/2028
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $7.14 M6/1/2028
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $36.50 M12/1/2027
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $183.49 M6/1/2028
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 32022W3 – Recommended Solutions: South Cluster $37.89 M6/1/2028
May 6, 2025Item 10 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline 230kV Line #2135 Hollymeade – Gordonsville $32.0 M6/1/2028
May 6, 2025Item 10 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline Hollymeade/Charlottesville Switch Upgrades $0.3 M12/30/2028
May 6, 2025Item 10 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline 230kV Line #2054 Charlottesville-Proffit $46.53 M12/1/2028

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.