Thelma - Big Sandy - Busseyville 138 kV
Thelma, KY/Big Sandy, KY/Busseyville, KY. Presented by AEP in PJM planning materials (AEP zone, KY).
Profile
AEP submitted this rebuild of the Big Sandy - Thelma 138 kV circuit for inclusion in its 2026 Local Plan in September 2026, at a transmission cost estimate of $169.555 million and a projected in-service date in November 2030. (p. 1, p. 67, p. 68) The driver listed is equipment condition: AEP describes a line of about 25.5 miles first installed in 1963, with 112 of its 127 structures being 1963 wood structures. (p. 67) The problem statement counts 5 momentary and 5 permanent outages causing 3.4 million minutes of customer interruption, and says the line serves 33 MVA of peak load at Busseyville station. (p. 67) Almost all of the cost is two line rebuilds: 19 miles from Thelma to Busseyville at $120 million and a 7 mile section from Big Sandy to Busseyville at $48.4 million, with relay and terminal work at Big Sandy and Thelma substations. (p. 68) AEP says rehab work could leave 1963 structures and conductor in service, and that retiring the line is not possible because it is a major 138 kV path through Kentucky and a source to Busseyville. (p. 68) The need was first presented in November 2025 with no cost; the solution meeting in May 2026 printed the same $169.555 million estimate and in-service date that the October 2026 Local Plan carries. (p. 4, p. 15, p. 68) AEP lists the project status as Scoping. (p. 68)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Thelma - Busseyville 138 kV | Rebuild the 19 mile 138 kV line from Thelma to Busseyville; estimated $120 M | p. 68 |
| Big Sandy - Busseyville 138 kV | Rebuild the 7 mile section of the Big Sandy - Busseyville 138 kV line; estimated $48.4 M | p. 68 |
| Big Sandy Substation | Relay settings update; estimated $0.055 M | p. 68 |
| Thelma Substation | Replace jumpers, line trap, CCVT and tuner on the Big Sandy line, control cables and relay settings; estimated $1.1 M | p. 68 |
Details as printed
| Previously presented | Need Meeting 11/14/2025, Solution Meeting SRRTEP-W - 05/15/2026 | p. 67 |
|---|---|---|
| Supplemental project ID | s3954.1-4 | p. 68 |
| Project driver | Equipment Condition/Performance/Risk | p. 67 |
| Line in the problem statement | Big Sandy - Thelma circuit: installed 1963, ~25.5 mi, 127 structures, wood and lattice aluminum | p. 67 |
| Structure vintage | 112 of 127 structures (88%) are 1963 wood; 11 of 127 are 1963 lattice | p. 67 |
| Outages | 5 momentary and 5 permanent outages causing 3.4M minutes of CMI | p. 67 |
| Load served | The line serves 33 MVA of peak load at Busseyville station | p. 67 |
| Alternatives considered | Rehab work was the alternative but could leave 1963 structures and conductor in service; retirement is not possible because the line is a major 138 kV path through Kentucky and a source to Busseyville | p. 68 |
| Need meeting, November 2025 | Need presented at the SRRTEP-Western meeting of 11/14/2025 with the same problem statement; no cost or solution printed | p. 4 |
| Solution meeting | Solution Meeting SRRTEP-W - 05/15/2026 | p. 15 |
| Solution meeting, May 2026 | $169.555 M | p. 15 |
| In-service, May 2026 | 11/01/2030 | p. 15 |
| Model | 2030 RTEP model | p. 68 |
| Model, May 2026 | 2024 RTEP model for 2029 Summer & Winter (50/50) | p. 15 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| November 14, 2025 | Item 03 - AEP Supplemental Projects PDF | Thelma, KY/Big Sandy, KY/Busseyville, KY | not printed | not printed | Need Meeting 11/14/2025 |
| May 15, 2026 | Item 01 - AEP Supplemental Projects PDF | Thelma, KY/Big Sandy, KY/Busseyville, KY | $169.555 M | 11/01/2030 | Scoping |
| October 6, 2026 | Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 PDF | Thelma, KY/Big Sandy, KY/Busseyville, KY | $169.555 M | 11/01/2030 | Scoping |
| Date not printed | AEP  PDF | Thelma, KY/Big Sandy, KY/Busseyville, KY | $169.555 M | 11/01/2030 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Big Sandy (AEP)
- Busseyville (AEP)
- Thelma (AEP)
Not printed
- No county is printed for Thelma, Big Sandy or Busseyville; the slides print only KY.
- The November 2025 need deck prints no cost, in-service date or status.
- No customer load request is part of this need; the driver is equipment condition only.
- No news article about this rebuild could be found and opened; none is listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.