EKPC Mason County, KY
Maysville, KY/Mason County, KY/Spurlock, KY/Maysville, KY. Presented by EKPC in PJM planning materials (EKPC zone, KY).
Profile
East Kentucky Power Cooperative (EKPC) presented this solution to PJM's Transmission Expansion Advisory Committee in May 2025, with a total transmission cost estimate of $566.35 million and a projected in-service date of September 2028 for the last phase. (p. 1, p. 3, p. 7) The driver is customer service: EKPC first presented the need in March 2025, stating that a new customer has requested transmission service in Mason County, Kentucky, with 110 MW expected by December 2026 and a ramp to 530 MW by February 2028, 850 MW by August 2028 and 2,200 MW by January 2031. (p. 3, p. 3) The solution requires work by two utilities, EKPC and Dayton Power & Light (DP&L), and builds a campus of three new 345/138 kV switching stations, Mason County 1, 2 and 3, serving the customer at 138 kV. (p. 4, p. 5, p. 6, p. 7) The stations are fed by a loop-in of the existing Spurlock - North Clark 345 kV line, a new double circuit of about 4.0 miles from EKPC's Spurlock Station and a new double circuit of about 11.0 miles from DP&L's Stuart station, after a temporary Phase 0 tap to two existing 138 kV lines. (p. 4, p. 5, p. 6, p. 7) The phase estimates are $0 M for Phase 0, $122 million for Phase 1, $182.35 million for Phase 2 and $262 million for Phase 3, and each phase slide notes that all associated costs are borne by the customer. (p. 4, p. 5, p. 6, p. 7) EKPC lists no reasonable alternatives for serving the requested load on the customer's timeline and gives the project status as Engineering. (p. 7)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Phase 0: temporary 138 kV taps | Two ~1.5 mile temporary 138 kV tap lines from the Spurlock - Goddard and Spurlock - Plumville 138 kV lines; estimated $0 M, in service 12/19/2026 | p. 4 |
| Mason County 1 345/138 kV station (Phase 1) | New switching station: six 345 kV and fifteen 138 kV breakers, two 345/138 kV transformers | p. 5 |
| Spurlock - North Clark 345 kV loop-in (Phase 1) | Extend the intercepted line ~1.5 miles into Mason County 1; Phase 1 estimated $122 M, in service 5/28/2027 | p. 5 |
| Mason County 1 expansion (Phase 2) | Three more 345 kV and eleven more 138 kV breakers, one more 345/138 kV transformer | p. 6 |
| Mason County 2 345/138 kV station (Phase 2) | New switching station: eight 345 kV and six 138 kV breakers, two 345/138 kV transformers | p. 6 |
| Spurlock - Mason County 1 & 2 345 kV double circuit (Phase 2) | New ~4.0 mile double circuit from Spurlock; North Clark re-terminated at Mason County 2; Phase 2 estimated $182.35 M, in service 3/11/2028 | p. 6 |
| Mason County 2 expansion (Phase 3) | Three more 345 kV and fourteen more 138 kV breakers, one more 345/138 kV transformer | p. 7 |
| Mason County 3 345/138 kV station (Phase 3) | New switching station: eight 345 kV and seventeen 138 kV breakers, two 345/138 kV transformers | p. 7 |
| Stuart - Mason County 2 & 3 345 kV double circuit (Phase 3) | New ~11.0 mile double circuit from DP&L's Stuart station; Phase 0 removed; Phase 3 estimated $262 M, in service 9/01/2028 | p. 7 |
Details as printed
| Need presented | Need Meeting 03/04/2025 | p. 3 |
|---|---|---|
| Project driver | Customer Service | p. 3 |
| Customer request, Mason County | New customer in Mason County, KY: 110 MW by 12/2026, 530 MW by 2/2028, 850 MW by 8/2028, 2200 MW by 1/2031 | p. 3 |
| Utilities involved | Work by two utilities, East Kentucky Power Cooperative (EKPC) and Dayton Power & Light (DP&L) | p. 4 |
| Plan overview | Loop in the Spurlock - North Clark 345 kV line, two new 345 kV lines from Spurlock Station and two from DP&L's Stuart substation; a campus of three 345/138 kV switching stations serving the customer at 138 kV | p. 4 |
| Cost note | All associated costs is borne by the customer (printed on each phase slide) | p. 7 |
| Alternatives considered | No reasonable alternatives to provide the requested load in the customer's timeline | p. 7 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| March 4, 2025 | Item 13 - EKPC Supplemental Projects PDF | Mason County, KY | not printed | not printed | Need Meeting 03/04/2025 |
| May 6, 2025 | Item 06 - EKPC Supplemental Projects PDF | Maysville, KY/Mason County, KY/Spurlock, KY/Maysville, KY | $566.35 M | 9/01/2028 | Engineering |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Mason County 1 (EKPC): described as new
- Mason County 2 (EKPC): described as new
- Mason County 3 (EKPC): described as new
- Goddard (EKPC)
- North Clark (EKPC)
- Plumville (EKPC)
- Spurlock (EKPC)
- Stuart station (EKPC)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Mason County official says data center could bring 400 jobs averaging $80,000; would require massive amounts of power and water, WEKU, August 21, 2025. WEKU reported that East Kentucky Power Cooperative reported in May a request from an unnamed potential customer for a project requiring 2.2 gigawatts by 2028, and that the local industrial development director described the applicant as a Fortune 20 tech company.
- Kentucky could be on the eve of a data center boom. But in Mason County details are sketchy., Kentucky Lantern (via Yahoo News), August 21, 2025. The Kentucky Lantern reported that officials under non-disclosure agreements described a Fortune 100 company considering a technology campus of more than $1 billion on land near the Ohio River and EKPC's Spurlock Generating Station, and that local officials said the developer would cover infrastructure costs.
- Mason County gives final approval on rezoning properties for data center construction, WEKU, May 26, 2026. WEKU reported that Mason County gave final approval to rezoning properties for an undisclosed company's data center, and that an EKPC spokesperson spoke in support of the project.
Not printed
- The PJM slides name the customer only as a new customer; they do not say what the load is. None of the news articles cite the PJM need number; the link to the reported data center is the press's, by location and timing.
- No county or state is printed for Mason County 1, 2 or 3 beyond the Mason County, KY request; no site location is printed.
- No later EKPC or Dayton (DP&L) slide in the tracked PJM materials cites EKPC-2025-001; the cost and dates are those of the 05/06/2025 solution meeting, and no supplemental project ID (s-number) is printed.
- The Stuart station's state is not printed in these slides.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.