Maysville, KY/Mason County, KY/Spurlock, KY/Maysville, KY. Presented by EKPC in PJM planning materials (EKPC zone, KY).

$566.35Mcost estimate as printed p. 7
9/01/2028projected in service p. 7
Engineeringstatus as printed p. 7

Profile

East Kentucky Power Cooperative (EKPC) presented this solution to PJM's Transmission Expansion Advisory Committee in May 2025, with a total transmission cost estimate of $566.35 million and a projected in-service date of September 2028 for the last phase. (p. 1, p. 3, p. 7) The driver is customer service: EKPC first presented the need in March 2025, stating that a new customer has requested transmission service in Mason County, Kentucky, with 110 MW expected by December 2026 and a ramp to 530 MW by February 2028, 850 MW by August 2028 and 2,200 MW by January 2031. (p. 3, p. 3) The solution requires work by two utilities, EKPC and Dayton Power & Light (DP&L), and builds a campus of three new 345/138 kV switching stations, Mason County 1, 2 and 3, serving the customer at 138 kV. (p. 4, p. 5, p. 6, p. 7) The stations are fed by a loop-in of the existing Spurlock - North Clark 345 kV line, a new double circuit of about 4.0 miles from EKPC's Spurlock Station and a new double circuit of about 11.0 miles from DP&L's Stuart station, after a temporary Phase 0 tap to two existing 138 kV lines. (p. 4, p. 5, p. 6, p. 7) The phase estimates are $0 M for Phase 0, $122 million for Phase 1, $182.35 million for Phase 2 and $262 million for Phase 3, and each phase slide notes that all associated costs are borne by the customer. (p. 4, p. 5, p. 6, p. 7) EKPC lists no reasonable alternatives for serving the requested load on the customer's timeline and gives the project status as Engineering. (p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Phase 0: temporary 138 kV tapsTwo ~1.5 mile temporary 138 kV tap lines from the Spurlock - Goddard and Spurlock - Plumville 138 kV lines; estimated $0 M, in service 12/19/2026p. 4
Mason County 1 345/138 kV station (Phase 1)New switching station: six 345 kV and fifteen 138 kV breakers, two 345/138 kV transformersp. 5
Spurlock - North Clark 345 kV loop-in (Phase 1)Extend the intercepted line ~1.5 miles into Mason County 1; Phase 1 estimated $122 M, in service 5/28/2027p. 5
Mason County 1 expansion (Phase 2)Three more 345 kV and eleven more 138 kV breakers, one more 345/138 kV transformerp. 6
Mason County 2 345/138 kV station (Phase 2)New switching station: eight 345 kV and six 138 kV breakers, two 345/138 kV transformersp. 6
Spurlock - Mason County 1 & 2 345 kV double circuit (Phase 2)New ~4.0 mile double circuit from Spurlock; North Clark re-terminated at Mason County 2; Phase 2 estimated $182.35 M, in service 3/11/2028p. 6
Mason County 2 expansion (Phase 3)Three more 345 kV and fourteen more 138 kV breakers, one more 345/138 kV transformerp. 7
Mason County 3 345/138 kV station (Phase 3)New switching station: eight 345 kV and seventeen 138 kV breakers, two 345/138 kV transformersp. 7
Stuart - Mason County 2 & 3 345 kV double circuit (Phase 3)New ~11.0 mile double circuit from DP&L's Stuart station; Phase 0 removed; Phase 3 estimated $262 M, in service 9/01/2028p. 7

Details as printed

Need presentedNeed Meeting 03/04/2025p. 3
Project driverCustomer Servicep. 3
Customer request, Mason CountyNew customer in Mason County, KY: 110 MW by 12/2026, 530 MW by 2/2028, 850 MW by 8/2028, 2200 MW by 1/2031p. 3
Utilities involvedWork by two utilities, East Kentucky Power Cooperative (EKPC) and Dayton Power & Light (DP&L)p. 4
Plan overviewLoop in the Spurlock - North Clark 345 kV line, two new 345 kV lines from Spurlock Station and two from DP&L's Stuart substation; a campus of three 345/138 kV switching stations serving the customer at 138 kVp. 4
Cost noteAll associated costs is borne by the customer (printed on each phase slide)p. 7
Alternatives consideredNo reasonable alternatives to provide the requested load in the customer's timelinep. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
March 4, 2025Item 13 - EKPC Supplemental Projects PDFMason County, KY not printednot printedNeed Meeting 03/04/2025
May 6, 2025Item 06 - EKPC Supplemental Projects PDFMaysville, KY/Mason County, KY/Spurlock, KY/Maysville, KY $566.35 M9/01/2028Engineering

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.