Bernheisel Substation
Bernheisel 500/138 kV substation (New Kingston, PA). Presented by PPL in PJM planning materials (PPL zone, PA).
Profile
PPL submitted this customer service project for inclusion in its 2024 Local Plan on May 29, 2024, at an estimated project cost of $244 million. (p. 1, p. 28, p. 29) The need, presented in February 2024 with a solution presented in April 2024, is a customer request to serve a facility from a 138kV source in New Kingston, Pennsylvania, with a total load of approximately 1,275 MW by 2032 and a requested in-service date of March 2026. (p. 28) PPL lists the load at 40MW in summer 2026 and 108 MW in winter 2026-27 at initial in-service, then 405 MW summer and 540 MW winter in 2028, and 1,000 MW summer and 1,040 MW winter in 2030. (p. 28) The solution breaks the existing Juniata - Three Mile Island 500kV line and extends it 0.1 miles into a new four bay Bernheisel 500kV breaker-and-a-half yard, and rebuilds 13.3 miles of that line to double circuit between Juniata and Bernheisel. (p. 29) At Bernheisel it adds four 500-138kV transformers, a six bay 138kV yard and two 138kV capacitor banks, with six 138kV lines extended to the customer facility. (p. 29) PPL lists two alternatives: an all-230kV option estimated at $293M and a 500kV and 230kV option estimated at $260M. (p. 29) The local plan gives in-service dates (printed as RIS) of June 30, 2026 for five of the six upgrades and June 1, 2027 for s3311.2, and lists the project status as Conceptual. (p. 29)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Juniata - Three Mile Island 500kV line / Bernheisel 500kV yard | Break the existing Juniata - Three Mile Island 500kV line and extend the lines 0.1 miles into a new four bay Bernheisel 500kV breaker-and-a-half yard | p. 29 |
| Juniata - Bernheisel 500kV rebuild | Rebuild the existing JUNI-TMIS 500kV line to double circuit for 13.3 miles from Juniata to Bernheisel; PPL's standard is three sources into a BES substation | p. 29 |
| Bernheisel transformers | Four 500-138kV transformers | p. 29 |
| Bernheisel 138kV yard | Six bay 138kV yard | p. 29 |
| 138kV capacitor banks | Two 138kV capacitor banks | p. 29 |
| 138kV customer lines | Six 138kV lines to the customer facility | p. 29 |
Details as printed
| Project driver | Customer Service | p. 28 |
|---|---|---|
| Customer request, New Kingston | Facility served from a 138kV source in New Kingston, PA; approximately 1,275 MW total (2032); requested in service 03/2026 | p. 28 |
| Load ramp | Initial in-service: Summer 2026 40MW, Winter 2026-27 108 MW; projected 2028: Summer 405 MW, Winter 540 MW; projected 2030: Summer 1,000 MW, Winter 1,040 MW | p. 28 |
| Alternative considered (230kV) | 230kV Option: four bay 230kV BAAH yard (BERN) with four 230-138kV transformers and line rebuilds from Juniata, Cumberland and Williams Grove; estimated $293M | p. 29 |
| Alternative considered (500kV & 230kV) | 500kV & 230kV Option: five bay 230kV BAAH yard (BERN) and a three bay 500kV BAAH yard with two 500-230kV transformers, plus a third 500-230kV transformer at Juniata; estimated $260M | p. 29 |
| Added to the 2024 Local Plan | Local plan version 6, dated 9/27/2024, added s3311.1-.6 | p. 32 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| Date not printed | PPL  PDF | $244M | s3311.1, s3311.3, s3311.4, s3311.5, s3311.6. RIS 6/30/2026. s3311.2 RIS 6/1/2027 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Bernheisel (PPL): described as new
- Juniata (PPL): expansion described
- Three Mile Island (PPL)
Not printed
- No program title is printed; the slides carry only the need number PPL-2024-0001 under 'PPL Transmission Zone: Supplemental'. The name used here is taken from the printed new station, Bernheisel.
- The local plan names the customer only as a customer; it does not say what the facility is.
- No county is printed; New Kingston, PA is the only location given for the customer site, and no location is printed for Bernheisel itself.
- No cost is printed per upgrade (s3311.1-.6); only the $244M project total.
- The February and April 2024 TEAC decks that first presented the need and solution are referenced on the slides but are not in the archive, so the 2024 Local Plan is the only cited source and the history has a single, undated observation.
- No later archived deck (2025 or 2026 local plans, TEAC decks) mentions Bernheisel, PPL-2024-0001 or s3311.
- No news coverage naming Bernheisel or this New Kingston request was found as of 2026-11-27.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.