Fredericksburg to Possum Corridor 230kV Lines
Fredericksburg to Possum Corridor – Add 3rd and 4th 230kV Lines. Presented by Dominion in PJM planning materials (Dominion zone).
Profile
Dominion submitted this supplemental project for inclusion in its 2025 Local Plan at an estimated cost of $180.0 million ($120.0 million for transmission line and $60.0 million for substation work), with a projected in-service date of June 2029. (p. 1, p. 8) Dominion lists the driver as operational flexibility and efficiency, and its problem statement says reliability projects will rebuild most of the Fredericksburg to Possum Point corridor over the next 3-4 years so that two 230kV lines are available. (p. 6) The deck says DEV Distribution has submitted delivery point requests for thirteen new substations to serve data center load in the corridor, projected at over 1700 MW by 2029 and over 3000 MW by 2032; it lists requests for fourteen more new substations south of Fredericksburg Substation, with projected loads exceeding 2000 MW by 2029 and 3000 MW by 2032. (p. 6) Dominion says that without diverse transmission sources, the first interconnections to the two 230kV lines would have to be reworked as more lines are added, which it expects to cause customer interconnection delays, longer outages and higher overall cost. (p. 6) The selected solution builds a new Allman switching station north of Fredericksburg Substation with ten 230kV line terminals in GIS equipment, a second 12-mile 230kV double-circuit pole line from Aquia Harbour to Possum Point, and two additional 230kV lines on the vacant arms of the double-circuit structures. (p. 8) About 41 lattice structures (about 7.1 miles) of the adjacent 500kV Line #568 would be replaced with monopoles to make room for the new line. (p. 8) The need was first presented at a need meeting on April 30, 2024 and a solution meeting in August 2024; Dominion lists the project status as Conceptual. (p. 6, p. 8)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Allman Switching Station (new) | New 230kV switching station north of the existing Fredericksburg Substation, ten line terminals (six north, four south) | p. 8 |
| Allman Switching Station equipment | GIS equipment because of limited space | p. 8 |
| Line #2157 | Rebuild approx. 4.5 miles, Allman to Cranes Corner, double-circuit, 1573 MVA minimum summer rating | p. 8 |
| Line #2083 | Rebuild approx. 0.7 miles, Allman to Hospital Jct, double-circuit, 1573 MVA minimum summer rating | p. 8 |
| Cranes Corner substation | Expanded to accommodate a new backbone for line re-alignment | p. 8 |
| Aquia Harbour - Possum Point 230kV line | Second 230kV double-circuit pole line, approx. 12 miles; approx. 41 lattice structures (~7.1 miles) of adjacent 500kV Line #568 replaced with monopoles | p. 8 |
| 3rd and 4th 230kV lines | Two additional 230kV lines, 1573 MVA minimum summer rating, on vacant arm positions of the double-circuit structures | p. 8 |
| Possum Point substation | 230kV terminals reconfigured for the two new line terminations | p. 8 |
Details as printed
| Project ID | Supplemental Project ID s3701 | p. 8 |
|---|---|---|
| Previously presented | Need meeting 04/30/2024; solution meeting 08/06/2024 | p. 6 |
| Project driver | Operational Flexibility and Efficiency | p. 6 |
| Corridor rebuild already under way | Reliability projects will rebuild most of the corridor over the next 3-4 years so that two 230kV lines are available | p. 6 |
| Load requests in the corridor | Delivery point requests for thirteen new substations to serve data center load in the corridor; over 1700 MW by 2029, over 3000 MW by 2032 | p. 6 |
| Load requests south of Fredericksburg | Delivery point requests for fourteen new substations south of Fredericksburg Substation; exceeding 2000 MW by 2029 and 3000 MW by 2032 | p. 6 |
| Problem statement | Without diverse transmission sources, initial interconnections to the two 230kV lines would have to be reworked; expected to cause interconnection delays, longer outages and higher cost | p. 6 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| October 8, 2025 | Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 PDF | Fredericksburg to Possum Corridor – Add 3rd and 4th 230kV Lines | $180.0M | 06/01/2029 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Allman (DOM): described as new
- Aquia Harbour (DOM)
- Cranes Corner (DOM)
- Fredericksburg (DOM)
- Possum Point (DOM)
Not printed
- No state or county is printed on the cited pages (the slides name stations only).
- The deck does not name the data center customers behind the delivery point requests, or say which of the requested substations would connect to these lines.
- Only one tracked document carries this project: the 2025 Local Plan submission. The need meeting (04/30/2024) and solution meeting (08/06/2024) decks are not archived.
- No news article about adding the 3rd and 4th 230kV lines or the Allman switching station was found; coverage found was about the earlier Fredericksburg - Possum Point rebuild.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.