Substation Scout

Fredericksburg to Possum Corridor 230kV Lines

Fredericksburg to Possum Corridor – Add 3rd and 4th 230kV Lines. Presented by Dominion in PJM planning materials (Dominion zone).

$180.0Mcost estimate as printed p. 8
06/01/2029projected in service p. 8
Conceptualstatus as printed p. 8

Profile

Dominion submitted this supplemental project for inclusion in its 2025 Local Plan at an estimated cost of $180.0 million ($120.0 million for transmission line and $60.0 million for substation work), with a projected in-service date of June 2029. (p. 1, p. 8) Dominion lists the driver as operational flexibility and efficiency, and its problem statement says reliability projects will rebuild most of the Fredericksburg to Possum Point corridor over the next 3-4 years so that two 230kV lines are available. (p. 6) The deck says DEV Distribution has submitted delivery point requests for thirteen new substations to serve data center load in the corridor, projected at over 1700 MW by 2029 and over 3000 MW by 2032; it lists requests for fourteen more new substations south of Fredericksburg Substation, with projected loads exceeding 2000 MW by 2029 and 3000 MW by 2032. (p. 6) Dominion says that without diverse transmission sources, the first interconnections to the two 230kV lines would have to be reworked as more lines are added, which it expects to cause customer interconnection delays, longer outages and higher overall cost. (p. 6) The selected solution builds a new Allman switching station north of Fredericksburg Substation with ten 230kV line terminals in GIS equipment, a second 12-mile 230kV double-circuit pole line from Aquia Harbour to Possum Point, and two additional 230kV lines on the vacant arms of the double-circuit structures. (p. 8) About 41 lattice structures (about 7.1 miles) of the adjacent 500kV Line #568 would be replaced with monopoles to make room for the new line. (p. 8) The need was first presented at a need meeting on April 30, 2024 and a solution meeting in August 2024; Dominion lists the project status as Conceptual. (p. 6, p. 8)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Allman Switching Station (new)New 230kV switching station north of the existing Fredericksburg Substation, ten line terminals (six north, four south)p. 8
Allman Switching Station equipmentGIS equipment because of limited spacep. 8
Line #2157Rebuild approx. 4.5 miles, Allman to Cranes Corner, double-circuit, 1573 MVA minimum summer ratingp. 8
Line #2083Rebuild approx. 0.7 miles, Allman to Hospital Jct, double-circuit, 1573 MVA minimum summer ratingp. 8
Cranes Corner substationExpanded to accommodate a new backbone for line re-alignmentp. 8
Aquia Harbour - Possum Point 230kV lineSecond 230kV double-circuit pole line, approx. 12 miles; approx. 41 lattice structures (~7.1 miles) of adjacent 500kV Line #568 replaced with monopolesp. 8
3rd and 4th 230kV linesTwo additional 230kV lines, 1573 MVA minimum summer rating, on vacant arm positions of the double-circuit structuresp. 8
Possum Point substation230kV terminals reconfigured for the two new line terminationsp. 8

Details as printed

Project IDSupplemental Project ID s3701p. 8
Previously presentedNeed meeting 04/30/2024; solution meeting 08/06/2024p. 6
Project driverOperational Flexibility and Efficiencyp. 6
Corridor rebuild already under wayReliability projects will rebuild most of the corridor over the next 3-4 years so that two 230kV lines are availablep. 6
Load requests in the corridorDelivery point requests for thirteen new substations to serve data center load in the corridor; over 1700 MW by 2029, over 3000 MW by 2032p. 6
Load requests south of FredericksburgDelivery point requests for fourteen new substations south of Fredericksburg Substation; exceeding 2000 MW by 2029 and 3000 MW by 2032p. 6
Problem statementWithout diverse transmission sources, initial interconnections to the two 230kV lines would have to be reworked; expected to cause interconnection delays, longer outages and higher costp. 6

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
October 8, 2025Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 PDFFredericksburg to Possum Corridor – Add 3rd and 4th 230kV Lines $180.0M06/01/2029Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first