Olive - Reynolds 345kV

Olive - Reynolds 345kV. Presented by AEP in PJM planning materials (AEP zone).

$452.64 Mcost estimate as printed p. 19
05/30/2031projected in service p. 19
Local Plan submissionstatus as printed p. 19

Profile

AEP's 2025 local plan submission lists a rebuild of about 68.1 miles of the Olive - Reynolds 345kV double circuit line at a transmission cost estimate of $452.64 million, with a projected in-service date of May 30, 2031. (p. 1, p. 19) It is AEP's solution to a need titled Western Indiana and Central Ohio, presented at a needs meeting on May 9, 2023, which concerns paper expanded and air expanded (PE/AE) conductor; AEP counts approximately 570 miles of such lines in its 345kV footprint and has concerns of increased core corrosion. (p. 18, p. 15) On this line, 299 of 306 structures are 1957 double circuit steel lattice towers, 135 of the 136 miles of conductor is ACSR/PE, and 168 structures, 55% of the line, had at least one open condition. (p. 18) AEP says retiring the line is not viable because of about 28 queue projects connecting on both sides of it, and that reconductoring was considered and not selected because of tower conditions. (p. 19) The solution was first presented at the December 2024 solutions meeting at $452.64 million and May 30, 2031, and the 2025 local plan slides print the same figures. (p. 15, p. 10, p. 19)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Olive - Reynolds 345kV lineRebuild ~68.1 miles of double circuit 345kV on centerline, including line removal, OPGW and right of way; $452.64p. 19

Details as printed

Need titleWestern Indiana and Central Ohio: Paper Expanded/Air Expanded (PE/AE) Lines in AEPp. 18
Previously presentedSolutions Meeting 12/03/2024; Needs Meeting 5/9/2023p. 15
Supplemental IDs3594.1p. 19
Project driverEquipment Material/Condition/Performance/Riskp. 15
PE/AE fleetApproximately 570 miles of PE/AE lines in AEP's 345kV footprint, about 1,114 conductor milesp. 15
Conductor concernAEP has concerns of increased core corrosion on the PE/AE conductor fleetp. 15
Line condition68.1 miles; 299 of 306 structures are 1957 double circuit steel lattice towersp. 18
Conductor135 of the 136 miles of conductor is 1,414,000 CM ACSR/PEp. 18
Open conditions168 structures with at least one open condition, 55% of the structuresp. 18
Alternative: retirementNot viable, given about 28 projects in the queue connecting on both sides of the circuitp. 19
Alternative: reconductorReconductoring the 68.1 miles was considered and not selected because of tower conditionsp. 19
Cost at the solutions meeting (12/03/2024)$452.64 Mp. 10
In-service at the solutions meeting (12/03/2024)05/30/2031p. 10

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 3, 2024Item 08 - AEP Supplemental Projects PDFWestern Indiana and Central Ohio $452.64 M05/30/2031Solutions Meeting 12/03/2024
October 8, 2025Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 PDFAEP Transmission Zone M-3 Process Western Indiana and Central Ohio $452.64 M05/30/2031Submission of Supplemental Project for inclusion in the Local Plan 4/7/2025
Date not printedAEP&nbsp PDFWestern Indiana and Central Ohio $452.64 M05/30/2031Submission of Supplemental Project for inclusion in the Local Plan 4/7/2025

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.