Olive - Reynolds 345kV
Olive - Reynolds 345kV. Presented by AEP in PJM planning materials (AEP zone).
Profile
AEP's 2025 local plan submission lists a rebuild of about 68.1 miles of the Olive - Reynolds 345kV double circuit line at a transmission cost estimate of $452.64 million, with a projected in-service date of May 30, 2031. (p. 1, p. 19) It is AEP's solution to a need titled Western Indiana and Central Ohio, presented at a needs meeting on May 9, 2023, which concerns paper expanded and air expanded (PE/AE) conductor; AEP counts approximately 570 miles of such lines in its 345kV footprint and has concerns of increased core corrosion. (p. 18, p. 15) On this line, 299 of 306 structures are 1957 double circuit steel lattice towers, 135 of the 136 miles of conductor is ACSR/PE, and 168 structures, 55% of the line, had at least one open condition. (p. 18) AEP says retiring the line is not viable because of about 28 queue projects connecting on both sides of it, and that reconductoring was considered and not selected because of tower conditions. (p. 19) The solution was first presented at the December 2024 solutions meeting at $452.64 million and May 30, 2031, and the 2025 local plan slides print the same figures. (p. 15, p. 10, p. 19)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Olive - Reynolds 345kV line | Rebuild ~68.1 miles of double circuit 345kV on centerline, including line removal, OPGW and right of way; $452.64 | p. 19 |
Details as printed
| Need title | Western Indiana and Central Ohio: Paper Expanded/Air Expanded (PE/AE) Lines in AEP | p. 18 |
|---|---|---|
| Previously presented | Solutions Meeting 12/03/2024; Needs Meeting 5/9/2023 | p. 15 |
| Supplemental ID | s3594.1 | p. 19 |
| Project driver | Equipment Material/Condition/Performance/Risk | p. 15 |
| PE/AE fleet | Approximately 570 miles of PE/AE lines in AEP's 345kV footprint, about 1,114 conductor miles | p. 15 |
| Conductor concern | AEP has concerns of increased core corrosion on the PE/AE conductor fleet | p. 15 |
| Line condition | 68.1 miles; 299 of 306 structures are 1957 double circuit steel lattice towers | p. 18 |
| Conductor | 135 of the 136 miles of conductor is 1,414,000 CM ACSR/PE | p. 18 |
| Open conditions | 168 structures with at least one open condition, 55% of the structures | p. 18 |
| Alternative: retirement | Not viable, given about 28 projects in the queue connecting on both sides of the circuit | p. 19 |
| Alternative: reconductor | Reconductoring the 68.1 miles was considered and not selected because of tower conditions | p. 19 |
| Cost at the solutions meeting (12/03/2024) | $452.64 M | p. 10 |
| In-service at the solutions meeting (12/03/2024) | 05/30/2031 | p. 10 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 3, 2024 | Item 08 - AEP Supplemental Projects PDF | Western Indiana and Central Ohio | $452.64 M | 05/30/2031 | Solutions Meeting 12/03/2024 |
| October 8, 2025 | Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 PDF | AEP Transmission Zone M-3 Process Western Indiana and Central Ohio | $452.64 M | 05/30/2031 | Submission of Supplemental Project for inclusion in the Local Plan 4/7/2025 |
| Date not printed | AEP  PDF | Western Indiana and Central Ohio | $452.64 M | 05/30/2031 | Submission of Supplemental Project for inclusion in the Local Plan 4/7/2025 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Indiana Michigan Power unveils $266M transmission line rebuild project, Inside INdiana Business, October 21, 2025. Inside INdiana Business reported that Indiana Michigan Power plans to invest $266 million to rebuild about 68 miles of line between Olive Substation in New Carlisle and Reynolds Substation in White County, through St. Joseph, LaPorte, Starke, Pulaski and White counties, with construction scheduled from winter 2027 to spring 2031.
- I&M to Invest $266 Million on Olive-Reynolds 345 kV Transmission Line Upgrade, T&D World, October 21, 2025. T&D World reported that I&M's roughly $266 million project also relocates about 2 miles of line east of Monon and upgrades Olive Substation, replacing equipment I&M said dates to the 1950s.
- I&M to Upgrade Area Power Lines, Hometown News Now, October 18, 2025. Hometown News Now reported that the rebuild starts at Olive substation near New Carlisle, that I&M put the total investment at about $266 million, and that the utility tied the project to rising demand from economic growth in the area.
Not printed
- No state is printed for the Olive - Reynolds line itself; the need title names Western Indiana and Central Ohio, and the press places both stations in Indiana.
- No county is printed for Olive or Reynolds in the slides.
- The slides print no project status (Scoping, Engineering, ...); the status shown is the process stage.
- The May 9, 2023 needs-meeting deck is not in the archive.
- The slides do not explain why the PJM estimate ($452.64 M) differs from the $266 million figure in press coverage.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.